APPLICATION OF QUALITY ASSURANCE
SPECIFICATIONS
FOR
ASPHALT CONCRETE MIXTURES
2016 Edition
Jointly Developed by
The Louisiana Transportation and Research Center
Technology Transfer and Training Section
and the Louisiana Department of Transportation and Development
La Gov 10305
Application of Quality Assurance Specifications for Asphalt Concrete Mixtures
ii
iii
APPLICATION OF QUALITY ASSURANCE
SPECIFICATIONS
FOR
ASPHALT CONCRETE MIXTURES
Developed by
TECHNOLOGY TRANSFER AND TRAINING
LOUISIANA TRANSPORTATION AND RESEARCH CENTER
For
Louisiana Department of Transportation and Development
2016
iv
v
CREDITS
This manual was developed by Brian Owens, DOTD Materials Engineer Administrator, with
the assistance of the technical review committee listed below. The manual was edited and
prepared for publication by the LTRC Publications Department
The Construction and Materials Sections of the Louisiana Department of Transportation and
Development and the DOTD Chief Engineer have approved this manual for publication.
Technical Advisory Committee
2016 Revised Edition
Mr. Brian Owens
Materials Administrator
Dr. Sam Cooper, Jr.
Director, LTRC
Mr. Paul “Marty” Farkas
DOTD Asphalt DCL Section 22
Dr. Sam Cooper III
Materials Research Administrator
Ms. Luanna Cambas
DOTD Construction Coordinator District 02
Mr. Scott Nelson
FHWA Asset Management/Pavement Engineer.
Mr. Michael Elliott
LTRC District Training Liaison
Posthumous
Special Thanks To
Mr. John Victory
for his expertise in Asphalt
Technology
vi
TABLE OF CONTENTS
vii
Topic Page
POLICY SECTION ....................................................................................................................................... 1
Documentation ........................................................................................................................................ 3
Definitions ................................................................................................................................................ 3
Safety ....................................................................................................................................................... 6
Environment Protection .......................................................................................................................... 7
Contractor Notification ............................................................................................................................ 8
Consequences of False Reporting or Misinformation ............................................................................. 8
Quality Assurance .................................................................................................................................... 9
Preliminary Source Approval of Materials ........................................................................................... 9
Certification or Qualification of Technicians ....................................................................................... 9
Certification of Equipment and Processes ......................................................................................... 10
Quality Control ................................................................................................................................... 12
Inspection, Sampling, and Testing ..................................................................................................... 12
Acceptance......................................................................................................................................... 13
Independent Assurance Program (IA)................................................................................................ 14
Laboratory Accreditation and Certification ................................................................................... 14
Independent Assurance Programs ..................................................................................................... 16
Independent Assurance ................................................................................................................ 16
System Independent Assurance Team ......................................................................................... 18
SECTION 501 THIN ASPHALT CONCRETE APPLICATIONS .................................................................... 20
Mix Design Steps and Approval ......................................................................................................... 20
Material Procurement and Approval ............................................................................................. 20
Aggregate ....................................................................................................................................... 20
Asphalt Cement ............................................................................................................................. 21
Additives ........................................................................................................................................ 21
Design of Asphalt Mixture, Job Mix Formula (JMF) ........................................................................... 21
Additional Requirements for OGFC Mixtures ................................................................................ 21
Trial Blends with Varying Asphalt Cement Contents (Except OGFC) ............................................. 24
Selection of Optimum Asphalt Cement Content ........................................................................... 24
Dust to Effective Asphalt Cement Ratio Evaluation....................................................................... 24
LWT, Loaded Wheel Test, (AASHTO T 324) .................................................................................... 24
Validation of JMF proposal ............................................................................................................ 24
Failure to Validate .......................................................................................................................... 25
Final Approval of JMF .................................................................................................................... 25
Materials Laboratory Sample Requirements ................................................................................. 25
Definition of a Lot (Thin Asphalt Concrete mixtures) ........................................................................ 26
Plant Testing for 501 Mixes ............................................................................................................... 26
Verification ......................................................................................................................................... 27
TABLE OF CONTENTS
viii
Roadway Acceptance ..................................................................................................................... 27
Plant and Stockpile Verification ..................................................................................................... 28
Asphalt Cement .............................................................................................................................. 28
Measurement and Payment .............................................................................................................. 28
Measurement ................................................................................................................................. 28
Payment ......................................................................................................................................... 28
Section 502 Asphalt Concrete Mixtures .............................................................................................. 29
Mainline Mixtures 1000 current plan ADT ....................................................................................... 29
Mix Design Steps and Approval ......................................................................................................... 29
Material Procurement and Approval ............................................................................................. 29
Approval Process for Plant-Modified Asphalt Cement ...................................................................... 32
Design of Asphalt Mixture, Job Mix Formula (JMF) ....................................................................... 34
Determination of Gradation and Bulk Specific Gravity (Gsb) for Aggregates ................................ 34
Bulk Specific Gravity (Gsb) ............................................................................................................. 35
Consensus Aggregate Test Evaluations .......................................................................................... 38
Coarse Aggregate Angularity (CAA) ............................................................................................... 39
Fine Aggregate Angularity (FAA) .................................................................................................... 39
Table 502-3 ........................................................................................................................................ 45
Aggregate Friction Rating ................................................................................................................... 45
Determination of RAP JMF Composite .......................................................................................... 46
Trial Blends at Varying Asphalt Cement Contents ......................................................................... 48
Validation of JMF Proposal ............................................................................................................ 53
Final Approval of JMF ..................................................................................................................... 55
Roadway Lot Tracking .................................................................................................................... 59
Quality Control ................................................................................................................................... 62
Plant Quality Control ...................................................................................................................... 62
Plant Quality Control Testing ........................................................................................................ 62
Plant Inspection ................................................................................................................................. 67
Department Certified ADI Responsibilities for Plant Verification .................................................. 67
Percent Anti-Strip ........................................................................................................................... 70
Roadway Quality Control ............................................................................................................... 72
Roadway Inspection ........................................................................................................................... 73
Inspection of Mixture on Roadway ................................................................................................ 73
Adjustment Factors for Pay and Calculating Yield ............................................................................. 75
Joint Construction .............................................................................................................................. 81
Segregation ........................................................................................................................................ 82
Coordination of Paving Operations .................................................................................................... 84
Roadway Acceptance ......................................................................................................................... 84
Mainline Lots: (92.0 min Density); 1000-ton Sublots; 5000-ton Lots ................................................ 85
Minor Lots: (90.0 min Density) five 1000 ton sublots ....................................................................... 86
TABLE OF CONTENTS
ix
Minor mix without density requirements is accepted based on contractor plant testing data. ... 87
Density by Non-Destructive Technologies (NDT): ............................................................................. 96
Device Off-set Procedure ............................................................................................................... 96
Offset computation example ......................................................................................................... 98
Roadway Testing Procedures ......................................................................................................... 99
Disputed NDT Device Readings ...................................................................................................... 99
Measurement and Payment ............................................................................................................ 102
Measurement .............................................................................................................................. 102
Payment ....................................................................................................................................... 102
Section 502.12 Surface Tolerance .................................................................................................... 103
Profiler Certification......................................................................................................................... 103
Longitudinal Surface Tolerance Testing ........................................................................................... 103
Pre-op Tests and Observations .................................................................................................... 104
Surface Tolerance Pay ................................................................................................................. 106
Section 503 Asphalt Concrete Equipment and Processes ................................................................ 107
Plant Certification ............................................................................................................................ 107
Initial Plant Certification .............................................................................................................. 107
Random Conformance Inspections .............................................................................................. 108
Re-Certification ............................................................................................................................ 108
Revoked Certification................................................................................................................... 108
Plant Laboratory Equipment and Documentation....................................................................... 109
Scales and Meters Certification ....................................................................................................... 110
Roadway Equipment Approval ........................................................................................................ 110
Inspection of Plant and Roadway Equipment .................................................................................. 111
Plant Inspection ........................................................................................................................... 112
Plant Equipment .......................................................................................................................... 112
Inspection of Mixture at Plant ..................................................................................................... 115
Haul Ticket ................................................................................................................................... 116
Roadway Equipment .................................................................................................................... 116
Section 504 Asphalt Tack Coats ........................................................................................................ 121
Application Rate Calculation ............................................................................................................ 121
APPENDIX ................................................................................................................................................. 0
Selection of Optimum Asphalt Cement Content .............................................................................. 6
Dust to Effective Asphalt Cement Ratio Evaluation......................................................................... 6
Moisture Susceptibility Analysis ...................................................................................................... 7
Loaded Wheel Tester, LWT Testing ................................................................................................. 7
Alternate Method for Calculating Roadway Yield Correction Factors ................................................. 8
High AC content mixes such as SMA may need an adjustment factor for calculating yield. .............. 9
Example of core sampling determination .......................................................................................... 10
Example PWL Calculation .............................................................................................................. 11
TABLE OF CONTENTS
x
Quality Index Values for Estimating Percent Within Limits ................................................................. 5
Generating and Using Random Numbers for Sampling Purposes ....................................................... 6
Application of Random Numbers for Roadway Core Location ............................................................... 8
Levels and Requirements for Asphalt Plant Qualified Tester and Certification ................................ 21
Asphalt Concrete Plant Review .......................................................................................................... 31
Asphalt Concrete Roadway Equipment Review ................................................................................. 37
Superpave Asphalt Roadway Report.................................................................................................. 44
Suggested Tie-In Procedure ............................................................................................................... 45
Weight Certification Tag (example) ................................................................................................... 46
xii
POLICY & GENERAL INFORMATION
1
POLICY SECTION
This document supports the implementation of Part V, 2016 Standard Specifications for Roads
and Bridges incorporating new policies: Contractor data used in the acceptance decision,
planned verification, dispute resolution, and System Independent Assurance.
This manual is part of project specifications by reference for inclusion and compliance with
Part V of Louisiana Standard Specification for Roads and Bridges 2016 Edition. By extension,
to any subsequent Special Provision and/or Supplemental Specifications not covered
otherwise.
The purpose of this manual is to supplement Part V of the 2016 LA Standard Specifications
for Roads and Bridges. To standardize policies and procedures, provide detail, explanation
and examples, denote personnel requirements, and denote equipment and process
requirements. All with the goal of facilitating uniform application of the specifications during
design, production and placement of asphalt concrete and associated work.
Specifications Use this manual in conjunction with the 2016 Edition of the Louisiana Standard
Specifications for Roads and Bridges, or “Spec Book. Relevant specifications are referenced
throughout this manual. Specifications may be repeated in order to further detail or
demonstrate how they are applied. All specifications, manuals, forms, and software are
subject to change. It is imperative that contract documents for each project be reviewed
for specific change, Special Provision, Supplemental Specification, update, and/or
addition.
Manuals Numerous manuals that are essential for performing DOTD asphalt-related work
are listed below. The latest edition of each shall be available at the asphalt mixture production
plant and district laboratory. Documents can be obtained from the Department at a published
price through General Files at 225-379-1107. Many manuals may be found at
http://wwwsp.dotd.la.gov , hereafter referred to as “website.
Documents are:
CONTRACT DOCUMENTS the legally binding written agreement between the
DOTD and the Contractor setting forth obligations for the performance of work for a
specific project. (not on website) This may include Special Provisions or
Supplemental Specifications.
2016 EDITION of the LOUISIANA STANDARD SPECIFICATIONS for ROADS and
BRIDGES (known as “Standard Specifications”) the terms and stipulations for
providing materials, services and the finished constructed product.
MATERIALS SAMPLING MANUAL (known as “MSM”) SAMPLING PLAN – The
MSM establishes and standardizes sampling and acceptance requirements for
Louisiana Department of Transportation and Development. The MSM determines
what contract items are sampled and tested. Documentation, frequency, quantity and
procedures for meeting project sampling requirements are detailed in the MSM. It
can be found on the Materials Lab website:
http://wwwsp.dotd.la.gov/Inside_LaDOTD/Divisions/Engineering/Materials_Lab/Pages
/default.aspx
POLICY & GENERAL INFORMATION
2
TEST PROCEDURES MANUAL all standardized DOTD test procedures, which are
denoted, “DOTD TR-xxx.”
ENGINEERING DIRECTIVES AND STANDARDS MANUAL (known as “EDSM”)
establishes policies and procedures for DOTD Design, Construction, and
Maintenance. An example is “haul truck certification.
APPROVED MATERIAL LIST (AML) - (Formerly known as “QPL”) a listing of
materials evaluated by DOTD. It lists companies that have demonstrated the ability
to supply a product of acceptable quality. Project acceptance or verification testing is
required of many products appearing on the Approved Materials list. Qualification
Procedures for Approved Materials are given.
DOTD CONSTRUCTION MEMORANDA The DOTD’s internal office documentation
to explain various construction issues. (Only available to DOTD Employees on the
Intranet. Go to Construction Home Page, to Construction Memos.)
CONSTRUCTION CONTRACT ADMINISTRATION MANUAL Instructions for DOTD
Project Engineers and their representatives includes procedures for change orders,
estimates, diaries and field book entries.
AASHTO TEST PROCEDURES a set of nationally recognized test procedures and
specifications published by the American Association of State Highway and
Transportation Officials.
http://www.transportation.org/ and go to the bookstore.
At the time of this writing, DOTD personnel have access through the LTRC
“Library/Information Services” through the intranet.
ASTM TEST PROCEDURES a set of nationally recognized test procedures
published by the American Society for Testing and Materials.
www.astm.org, go to Standards, then search. At the time of this writing, DOTD
personnel have access through the LTRC “Library/Information Services” through the
intranet.
ADMINISTRATIVE MANUAL for CONSTRUCTION TECHNICIAN TRAINING AND
CERTIFICATION certification and training requirements for performing construction
inspection.
http://www.ltrc.lsu.edu/certification.html
APPLICATION OF QUALITY ASSURANCE SPECIFICATIONS FOR ASPHALT
CONCRETE MIXTURES used in conjunction with and supplement Part V of the
Louisiana Standard Specifications for Roads and Bridges for the design, production,
and placement of Asphalt Concrete and associated work.
http://wwwsp.dotd.la.gov/Inside_LaDOTD/Divisions/Engineering/Materials_Lab/Pages
/default.aspx
POLICY & GENERAL INFORMATION
3
Documentation
Forms, Software and Spreadsheets Data input by the Contractor and DOTD personnel will
be required. The District Laboratory Engineer (DLE) will provide information on the current
program and software requirements.
Internet Connection An internet connection shall be required that is capable of connecting
to DOTD websites for data entry into LaPave.
Rounding for Test Procedures Site Manager Materials and DOTD approved software will
utilize computer rounding for all test results and sample locations.
Rounding for Pay Rounding for estimates and pay determination are to be in accordance
with the Construction Contract Administration Manual or current Site Manager® construction
policies. Asphalt mixture will be paid to the whole percent. If the tenths position is less than
5, round downward, if it is greater than or equal to 5, round upward. For example 99.3 rounds
to 99% and 99.5% rounds to 100% pay. Intermediate hand calculations are rounded two more
decimal places beyond the final answer.
LaPave Rounding LaPave carries intermediate calculation to infinite places. Reportable
calculations will be used to the reported decimal place in future calculations.
Example: G
mm
calculation of 2.4512578 - reported value of 2.451 will be used to calculate G
mb
values.
Definitions
Acceptance
The process of deciding, through inspection, whether to accept or reject a product, including
what pay factor to apply. [Where contractor test results are used in the agency’s acceptance
decision, the acceptance process includes contractor testing, agency verification, and
possible dispute resolution.]
Acceptance Program
All factors that comprise DOTD’s determination of the quality of the product as specified in the
contract requirements.
Aggregates
Material retained on the No. 4 sieve is coarse aggregate.
Material passing the No. 4 sieve is fine aggregate.
Approved Materials List (AML)
Formerly known as the Qualified Product List (QPL) - a list of qualified products available to
construction and maintenance personnel for use on Departmental projects. AML products are
subject to verification and acceptance testing.
Asphalt District Inspector (ADI)
DOTD Asphalt Plant Certified Inspector and is the representative of the District Laboratory
Engineer.
POLICY & GENERAL INFORMATION
4
Asphalt Technology Laboratory (ATL)
DOTD laboratory located at the Materials and Testing Section. The ATL may be used for
resolution and/or forensic testing of asphalt mixtures.
Conditional Validation
A Job Mix Formula (JMF) has met plant parameters for continued production, but is awaiting
plant produced Loaded Wheel Test (LWT) or Tensile Strength Ratio results (or other testing
required on plant produced mix.) The final approval comes from the DLE. Until density
requirements and roadway performance are achieved and evaluated, a JMF is deemed
Conditionaly Validated.
District Laboratory Engineer (DLE)
The coordinating authority of the district’s quality assurance program and the representative
of the Department in the area of materials quality. This coordination is in conjunction with the
DOTD Materials Engineer Administrator.
GPC Analysis
Gel permeation chromatography: Used to fingerprint asphalt cements and test for polymers in
polymer modified asphalt cements. Samples containing crumb rubber or latex for “grade
bumping” will employ methods other than GPC analysis. In areas referenced in this manual
for GPC testing, it may be necessary for DOTD to use other methods for analysis.
Independent Assurance Program (IAP)
The IA Program is covered by regulation 23 CFR 637. The technical brief can be viewed at,
http://www.fhwa.dot.gov/pavement/materials/hif12001.pdf.
Independent Assurance can be defined as: Activities that are an unbiased and independent
evaluation of all the sampling and testing procedures used in the acceptance program.
Independent assurance
A management tool that requires a third party, not directly responsible for process control or
acceptance, to provide an independent assessment of the product or the reliability of test
results, or both, obtained from process control and acceptance. IA testing may be used for
dispute resolution when the Contractor and Department test results differ.
LaPave
The current DOTD approved software for asphalt mixture design submittal and reporting of
asphalt mixture testing.
LWT Loaded Wheel Test
LWT is also referred to as Hamburg Wheel Track Testing. It is used to test samples for rutting
and moisture susceptibility. For design, JMF submittals, plant produced specimens, the data
from two separate wheel paths shall be submitted to DOTD (AASHTO T 324 9.1.b). When
testing roadway cores for rutting, field conditions and/or directives of the DLE will determine
the number of samples tested.
Maximum Size (MS)
One sieve size larger than the nominal maximum size
POLICY & GENERAL INFORMATION
5
Mix Design
JMF mix designs for 501 and 502 mixes shall use AASHTO M323 (Superpave Volumetric Mix
Design) or AASHTO M 325 (Stone Matrix Asphalt SMA) guidelines for designing asphalt
mixes submitted for DOTD approval.
Nominal Maximum Size (NMS)
One sieve size larger than the first sieve to retain more than 10% by weight of the combined
aggregates.
Non Destructive Testing (NDT)
The use of Nuclear, Low Nuclear or Non-Nuclear density testing equipment for roadway
density determination. The use of such equipment is subject to Department quidelines.
Producer/Supplier (PS)
DOTD registered entities that produce and/or supply materials for use or potential use on
DOTD projects.
Proficiency Samples
Homogeneous samples that are distributed and tested by two or more laboratories. Test
results are compared to assure that the laboratories are obtaining the same results.
Qualified Laboratories
Laboratories that are capable as defined by appropriate programs established by DOTD. As
a minimum, the qualification program shall include provisions for checking test equipment and
the laboratory shall keep records of calibration checks. Qualified laboratories shall be
accredited by AMRL, CMEC, or other DOTD approved accreditation body.
Qualified Sampling and Testing Personnel
Personnel who are qualified as defined by LTRC programs established and defined in The
Department Administrative Manual for Inspector/Technician Training and Certification.
Quality Assurance (QA)
All those planned and systematic actions necessary to provide confidence that a product or
service will satisfy given requirements for quality.
Quality Control (QC)
A procedure or set of procedures intended to ensure that a manufactured product or performed
service adheres to a defined set of quality criteria or meets the requirements of the client or
customer. Performed by the contractor to assess and adjust production processes so the end
result adheres to specifications.
Random Sample
A sample drawn from a lot in which each increment in the lot has an equal probability of being
chosen.
Rolling Five Average
When a total of five samples are reached, the average of the five is computed. As the sample
population increases, the newest sample is added and the oldest is removed from the average
of five samples. This creates the “Rolling Five Average.”
POLICY & GENERAL INFORMATION
6
Verification Sampling and Testing
Sampling and testing performed to authenticate the test procedures, testing equipment, and
test results for the product. Non-verifying results may warrant further investigation.
Safety
Both DOTD and Contractor personnel are to exercise caution while performing their duties at
the plant/laboratory and in the field. They are to follow all safety procedures during sampling,
testing, and routine plant/roadway inspection in accordance with the Testing Procedures
Safety Guidelines.
For sanitary, health and safety provisions refer to Section 107.06
POLICY & GENERAL INFORMATION
7
Environment Protection
Activities that negatively affect the environment potentially exist on every construction project,
whether at construction sites, material producing plants, or equipment staging areas. Potential
hazards can come from:
Storm water runoffit carries residues from asphalts, oils, fuels, fertilizers, and
chemicals that can be hazardous to the environment.
Airvapors from materials such as fuel and oils can be carried away from the site.
Noisevibrations that can cause soil subsidence resulting in structural damage to
buildings and water table changes, and high noise levels can affect hearing of
individuals.
There are local, state, and federal guidelines that control these activities to minimize
environmental harm. The Contractor shall abide by these regulations and take every step
necessary to prevent damage to the environment. Section 107.14 of the Standard
Specifications covers Environmental Protection procedures.
Erosion control is critical on a project. Pursuant to the Clean Water Act and the Louisiana
Environmental Quality Act, coverage under a Louisiana Pollution Discharge Elimination system
(LPDES) General Permit is required from the Louisiana Department of Environmental Quality
for any construction activity meeting the threshold for land disturbance under the required
permit. One single permit is required: for any project that disturbs one or more acres of land,
and less than one acre of total land area that is part of a larger common plan of development
or sale if the larger plan will ultimately disturb equal to or greater than one acre. DOTD projects,
meeting this threshold for land disturbance, are automatically covered and authorized to
discharge under this permit (LAR600000). A site specific Storm Water Pollution Prevention
Plan (SWPPP) is required for these projects and also normally consists of:
Plan sheets indicating the location of erosion control items
Standard Plan EC-01
Section 204
If there is no erosion control plan in the project plans, the Project Engineer is to contact the
Headquarters Construction Section to find out if one should be added. The SWPPP shall be
discussed at the pre-construction meeting.
POLICY & GENERAL INFORMATION
8
Contractor Notification
The Contractor shall notify the DLE and/or their designated representative by 3:00 pm of the
preceding business day of anticipated plant production. This ensures the DLE the opportunity
for inspection during production and shipping.
The Contractor shall make an effort to include, as accurate as possible, the Project(s), JMF(s),
anticipated load out time, and anticipated tonnage. Compliance with providing notification shall
be part of maintaining asphalt plant and asphalt plant laboratory certification.
Consequences of False Reporting or Misinformation
If an employee of DOTD or the Contractor is performing substandard work and is not able to
satisfactorily perform duties routinely required of certified or authorized personnel, or engages
in unethical activities, certification or authorization may be revoked.
Proceedings to revoke a certification or authorization may be initiated by DOTD
representatives or industry, including, but not limited to: Department Certified Inspectors,
District Training Specialists, DLEs, Area Engineers, Project Engineers, Construction
Engineers, or any member of the Certification Committee. The appropriate representative of
the employing firm may also request revocation of certification or authorizations granted to
non-Department personnel
Proceedings to revoke a certification or authorization must be directed to the Materials
Engineer Administrator, who is the Certifying Authority, and accompanied by documentation
of the unsatisfactory performance. The Certification Committee will evaluate the request. The
certification committee membership is in accordance with Engineering Directives and
Standards III.1.1.26 “DOTD Certification Committee Duties and Responsibilities” The
certification committee is chaired by the Certifying Authority. The committee is empowered to
create, revise, or rescind policies and procedures for the training, certification, and
authorization of QA/QC personnel.
Recording and reporting accurate production data into DOTD approved software shall be part
of requirements for maintaining laboratory and/or technician certification.
Policy and procedures for revocation of certification or authorization will be conducted and
adhered to in accordance with the latest version of the “Administrative Manual for Construction
Technician Training and Certification.This document may be found on the LTRC website at
http://www.ltrc.lsu.edu/certification.html
POLICY & GENERAL INFORMATION
9
Quality Assurance
Quality Assurance is the combined efforts of Quality Control and acceptance processes to
assure a project will provide the public with a durable product exhibiting a high level of
performance. A quality assurance system provides a level of confidence that our finished
product will be of good value.
Preliminary Source Approval of Materials
The Materials Sampling Manual, located on the Materials Section website, outlines the
inspection, sampling, and testing requirements of all materials. Source materials requiring
long-term testing and regular source verification testing are required to comply with
qualification procedures and testing requirements. When approved, the product will be listed
in the Approved Materials List (AML) on the Materials website.
Manufacturer’s representatives who wish to have products placed on the Approved Materials
List must submit the AML Form, all information listed in the qualification procedure and a
sample to the proper AML coordinator at the Materials and Testing Section. A list of AML
contacts is located on the Materials Lab Website under Approved Materials List.
A qualification procedure for each listing in the AML has been established. This procedure
contains a list of information required from the manufacturer of the product including an AML
submittal form, sample size, typical laboratory testing time, typical field testing time, tests
performed, specification requirements and project acceptance requirements.
Certification or Qualification of Technicians
Certified and/or Qualified Technicians are required to be adequately trained and capable of
performing design, sampling, testing, and inspections. The Contractor’s Technicians shall be
qualified to sample and test, certified to design, produce, control, and adjust their operations.
Requiring the use of Certified/Qualified Technicians, equipment and processes further ensures
the likelihood of acceptable quality. When producing asphalt concrete, the Contractor shall
employ a Certified or Qualified Asphalt Concrete Plant Technician in accordance with
specification requirements. The Technician must be present at the plant whenever plant
operations are supplying materials to a DOTD project. Daily plant operations shall not
commence unless a Certified Technician is present. Technicians for both the Contractor and
DOTD shall be qualified and/or certified for testing according to the levels listed below.
During plant operations, the Quality Control Technician for the contractor shall not also serve
in another capacity (i.e. plant operator, loader operator, laborer.)
The qualification/certification levels for an Asphalt Plant Technician are as follows:
Qualified Aggregate Tester
Qualified Asphalt Concrete Plant Level I
Certified Asphalt Concrete Plant Level II
Certified Asphalt Concrete Plant Level III
See Appendix for detailed training requirements.
POLICY & GENERAL INFORMATION
10
Requirements for certification as outlined in the Department’s Administrative Manual for
Inspector/Technician Training and Certification. The manual is available at
http://www.ltrc.lsu.edu/certification.html.
All Technicians involved in QA/QC sampling and testing of asphalt mixtures for DOTD are
required to complete the appropriate level of training in accordance with the Structured Training
Program for Asphalt Mixture Plant Technicians.
Personnel must participate in the proficiency sample program to be active and keep
certifications current. Failure to update by the established expiration date will result in the
expiration of the certification. The certification will remain expired until required steps are taken
to re-establish certification credentials.
The Department’s Paving Inspector will be certified in the area of Asphalt Concrete Paving
Inspection. Certification in this area requires successful completion of an examination.
Following a minimum six months experience, a performance evaluation in roadway paving is
administered.
It is expected all Department and non-Department Technicians and Inspectors to continually
monitor the production process for conformity to specifications and consistency. Certified
personnel are expected to conduct their duties of Quality Control and Quality Assurance in a
cooperative, professional, and ethical manner.
It is a requirement of asphalt concrete Technicians to complete all testing, documentation, and
submittals in a neat, orderly, and timely fashion. Required documentation is discussed
throughout this manual.
Certification of Equipment and Processes
The certified asphalt plant will have a sticker issued showing the date certified. Asphalt plant
lab testing equipment shall be calibrated, standardized, and/or verified in accordance with
AASHTO R 18, Section 503 of the Standard Specifications and Section 503 of this manual.
All plant scales, meters, and measuring devices shall be officially calibrated, standardized,
and/or verified by a private, licensed testing company, or the Weights and Standards Division
of the Department of Agriculture and Forestry. Contractors utilizing traceable
verified/calibrated weights, instruments, and measuring devices may use and properly
document the use of for laboratory equipment calibration, standardization, and/or verification
and/or calibration.
Calibration:
Performed under specific conditions such as temperature, humidity and includes
measurement uncertainties.
You must periodically calibrate your instruments, identify if there is a “drift” in the
measurements and eliminate it through calibration
It is performed as per calibration SOP (standard operation procedure.)
POLICY & GENERAL INFORMATION
11
Calibration performance of any equipment is compared against a reference standard.
(comparing and unknown to a known)
Calibration is a process that ensures accuracy is maintained in measurements
produced by your equipment.
Calibration assures accuracy of measurements.
Calibrations can be used to establish adjustment factors.
In summary:
1. Calibration is a comparison
2. Conducted by following a procedure
3. Corrects for known systematic error (bias)
4. Estimates the measurement uncertainty
Verification:
Checks an instrument or equipment against a standard or reference to confirm it is meeting
the broad and specific specifications set by the manufacturer.
Validation:
A documented program that provides a high degree of assurance that a specific process,
equipment, method, or system consistently produces a result meeting pre-determined
acceptance criteria.
A reference standard is not used in validation.
It provides documented evidence a process, equipment, method, or system produces
consistent results.
Standardization:
Standardization can be thought of the same as calibration, but without the “estimate of the
measurement uncertainty.
Asphalt plant labs must be AASHTO R18 accredited by AMRL, CMEC, or other accreditation
body approved by DOTD. It is mandatory that all required tests reported for design submittals
and daily production be performed by an accredited laboratory and Certified Technician.
Certified equipment and processes ensure the plant and paving equipment are in good working
condition and capable of producing the required level of quality. The Contractor shall provide
plant, field and testing equipment that is in good condition and appropriate for the tasks for
POLICY & GENERAL INFORMATION
12
which it is used. A list of required plant laboratory equipment is included in Section 503 of this
manual.
Prior to the beginning of construction on a project, a DOTD Roadway Inspector will inspect the
roadway equipment to be used on the project to ensure it is in good working condition and
appropriate for the activity and intended use. The Inspector will require equipment that does
not perform adequately, (leaks, damaged, disrepair, etc.) be removed, repaired and/or
replaced before being allowed to operate on the project. The contractor shall give sufficient
notice to the DOTD inspector to allow for equipment inspection before construction activities
begin.
Quality Control
Quality Control is the process used by the Contractor to monitor, assess, and adjust material
selection, production, and project construction to control the level of quality so that the product
continuously and uniformly conforms to specifications.
Minimum requirements for Quality Control sampling and testing are noted in the specifications
and the Materials Sampling Manual. The Contractor shall sample and test as needed to ensure
quality. All Quality Control required testing listed in the specifications shall be entered into
LaPave.
When approaching borderline conditions, a Contractor may adjust operations or materials.
When materials or operations result in out of specification plant gradation and volumetric tests,
or roadway density tests, immediate adjustments shall be required to correct the deficiency
and prevent reoccurrence.
Inspection, Sampling, and Testing
Inspection is the observation of materials, samples, tests, equipment, processes and finished
product to determine the quality of the product, to determine the quantity or the amount to pay
for the product. Plant technicians document plant test results. Roadway technicians document
product placement. Inspection may reveal areas of concern resulting in additional discussion,
investigation, or further testing. The Project Engineer is the direct representative of Chief
Engineer for the administration of the contract and represents the Department directly, as well
as the inspection staff.
Sampling and testing is a support for visual inspection. Although the random, statistically
based sampling and testing performed by the Department represents the entire area or lot
tested, this methodology does not replace visual inspection. Department personnel will
observe the Contractor's operations and inspect the project throughout its construction. When
non-uniform materials or non-uniform processes result in areas which do not appear to be
acceptable or which are obviously not in conformance with the quality of construction expected,
the Department will require the Contractor to correct these deficient areas. It has never been
the intent of the Department to accept a project solely on a sampling and testing program. It
is always necessary for the Project Engineer and Inspector to be aware of the quality of
construction and performance of the project during construction and acceptance phases before
final acceptance.
Sampling and testing requirements for materials or processes specified in Supplemental
Specifications or Special Provisions are not usually included in the Materials Sampling Manual.
POLICY & GENERAL INFORMATION
13
If sampling or testing requirements are not published, the Project Engineer will determine
sampling and testing.
Validation Testing
Validation is a specific type of verification testing, performed jointly by the Contractor and
DOTD, used to determine the viability of a laboratory-designed asphalt Job Mix Formula based
upon test results of plant-produced mixtures. Validation is performed on the first lot of asphalt
plant production and determines if the plant-produced mixture conforms to the proposed job
mix formula and Department specifications. Validation testing may occur over multiple days
and multiple projects, if allowed by the DLE.
If the project that initially receives mix from a validation does not have enough tonnage to
complete the validation, the validation shall be continued on the next project.
A validation may have multiple lot numbers when multiple projects are used to achieve the
required tonnage for validation.
Validation data establishes JMF production targets and tolerances for plant produced asphalt
mixes.
Documentation
Documentation provides a history of each project and a chronicle for Contractors and/or
Technicians. Documentation shall be maintained within LaPave and other means specified.
Contractor provided summary reports shall be required to close out DOTD projects with asphalt
concrete unless otherwise directed by the DLE. Reports are generated from LaPave.
The Contractor shall maintain records of all testing related to state projects at the production
plant. Contractor documentation shall be available to DOTD.
The Contractor shall document all Quality Control testing in LaPave. In addition, the
Department shall summarize the project-specific sampling and testing at the end of the project
in the 2059, or Summary of Test Results, in accordance with EDSM III.5.1.2.
The Contractor shall make all accreditation and asphalt mix testing documents available for
review upon the Department’s request.
Acceptance
Acceptance is the process of sampling, testing, and inspection that defines the degree of
contract compliance. Acceptance is based on the degree of compliance with specifications for
acceptance of materials and/or a Contractor’s work. Acceptance sampling, testing, and
inspection are the responsibility of DOTD. Use of Contractor sampling and testing in the
acceptance decision is allowed by specifications. At the end of the construction phase, through
evaluation of all sampling, testing, and visual inspection, the Department will determine pay
and provide final acceptance notice to the Contractor.
POLICY & GENERAL INFORMATION
14
Independent Assurance Program (IA)
The IA Program provides confidence that uniform testing and equipment exists in all facets of
the Quality Assurance Program. See the section on Independent Quality Assurance Program
for more detailed information.
Laboratory Accreditation and Certification
DOTD District Labs, Materials Lab, ATL, and Contractor asphalt plant labs require
accreditation by AMRL, CMEC or other accreditation body approved by DOTD in accordance
with AASHTO R 18.
DOTD Materials Engineer is the certifying authority for all laboratories (Contractor and District
Labs). AMRL or CMEC accreditation does not guarantee DOTD certification.
DOTD reserves the right to decertify laboratories when Contractors fail to rectify noted non-
conformance to policies.
POLICY & GENERAL INFORMATION
15
General testing requirements of DOTD District Labs, Asphalt Production & Design
Laboratories for Accreditation through AMRL, CMEC or other DOTD approved accreditation
body are listed in Table-1.
Table 1
Test Methods for Accreditation
Description
DOTD Test Method
AASHTO/ASTM
Specific Gravity & Density of Compressed
Asphalt Concrete Mixtures
1, 2, 3
DOTD TR 304
T 166/D2041
Theoretical Maximum Specific Gravity, G
mm
1, 2, 3
DOTD TR 327
T 209/D2041
Asphalt Cement Content, P
b
1, 2, 3
DOTD TR 323
T 308/D6307
Mechanical Analysis of Extracted
Aggregate
1, 2, 3
DOTD TR 309
T30/D5444
Moisture Content of Loose Asphalt Mixtures
1
DOTD TR 319
T 329
Coarse Aggregate Angularity (% Double
Faced Crushed)
1,
2, 3
DOTD TR 306
T 335/D5821
Conditioning of Asphalt Mixtures (Aging)
1, 2
R 30
Preparing Gyratory Samples
1, 2, 3
T 312
Asphalt Cement Drain Down
1, 2
D6390
Splitting & Quartering Samples
1, 2
DOTD TR 108
Reducing Samples of Asphalt Mixtures to
Testing Size
1, 2, 3
R 47
Sieve Analysis of Fine & Coarse Aggregate
1, 2
DOTD TR 113
T 27/C136
Determination of Moisture Content (Stockpile
Aggregates)
1
DOTD 403
T 255/C566
Amount of Material Finer than the 75 µm (#
200) Sieve in Aggregate by Wash
1, 2, 3
DOTD TR 112
T 11/ C117
Fine Aggregate Angularity
2, 3
DOTD TR 121
T 304/C1252
Flat & Elongated Particles
2, 3
D4791
Sand Equivalent
2, 3
DOTD TR 120
T 176/D2419
Hamburg Wheel-Track Testing of
Compacted Asphalt Mixtures
2, 3
T 324
Moisture Sensitivity (Lottman Tensile
Strength Ratio)
2
DOTD TR 322
T 283/D4867
Coarse Aggregate Bulk Specific Gravity &
Absorption
2, 3
T 85
Fine Aggregate Bulk Specific Gravity &
Absorption
2, 3
T 84
Semi-Circular Bend Test (SCB)
2,4
D8044
1
Asphalt Production Laboratories
2
Asphalt Mix Design Laboratories
3
DOTD District Laboratories
4
Optional accreditation for contractors
POLICY & GENERAL INFORMATION
16
Independent Quality Assurance Program
Independent Assurance Programs
A system-based IA Program for asphalt materials will be employed which includes the
maintenance of accreditation by all laboratories and maintenance of certification and
proficiency of assessment of Certified Technicians. System independent assurance will
include a technician proficiency testing program and may include random plant and field visits
to view test performance, verify equipment calibration, and examine accreditation records.
Independent Assurance is required for National Highway System (NHS) federal funding.
FHWA Technical Brief FHWAHIF12001 describes Code of Federal Regulations 23CFR637
that addresses the evaluation necessary for FHWA requirements.
DOTD employs the “System Approach” for independent assurance for asphalt materials where
qualifications of involved personnel and facilities are assessed.
Independent Assurance
All laboratories, equipment, and technicians involved in the acceptance decision are covered
under the Department’s Independent Assurance Program.
Each laboratory performing testing involved in the acceptance decision are required to be
accredited to comply with AASHTO R18. This accreditation addresses equipment and test
procedures used for each laboratory. All covered laboratories will be AASHTO R18
accredited to maintain DOTD certification and will submit documentation to verify current
accreditation to the Independent Assurance Team upon request. Failure to maintain
accreditation or failure to submit requested documentation may result in loss of DOTD lab
certification.
The Technician Proficiency Testing Program is the primary Independent Assurance
procedure used to monitor the proficiency of each technician involved in the acceptance
decision for asphalt materials. Typically, the Independent Assurance Team will send two
sets of proficiency samples per year to all technicians performing tests used in acceptance
decisions. Technicians will maintain “active” status by participating in at least one round of
proficiency sample testing per year and submitting appropriate responses for any
deficiencies noted upon analysis of proficiency testing results.
Note: Information on each technician will be maintained electronically by the Independent
Assurance Team. Therefore, it is imperative each technician provide proper contact
information and notify the Independent Assurance Team upon transfer to a different work
location (i.e. between District Labs or from one contractor’s lab to another).
For asphalt mixture materials, the following proficiency tests are required:
POLICY & GENERAL INFORMATION
17
Table 2
Proficiency Sample Testing
Asphalt Samples
Frequency
Gyratory Briquettes,
Minimum 1 per year
Loaded Wheel Test (Level 2
& 3 certification)
Minimum 1 per year
Oven Extracted Gradation
Minimum 1 per year
Loose Mix
Minimum 1 per year
Satisfactory performance for participants in the proficiency program will be test results less
than 2 standard deviations from the mean. Any technician with unsatisfactory performance
will submit a written response to address each deficiency noted. Depending on the
magnitude of the deficiency, the technician may be placed on notice and/or required to
perform additional testing to verify proficiency. Repeated deficiencies or failure to provide
appropriate responses to deficiencies may result in suspension of “active” status and / or
certification.
POLICY & GENERAL INFORMATION
18
System Independent Assurance Team
The system Independent Assurance team will be housed at the Asphalt Technology Lab (ATL)
at the Materials Lab facility and personnel will be comprised of the Field Quality Assurance
Engineer and Independent Assurance Technician(s). The ADI in each District will be
responsible for assisting with IA duties such as coordinating IA functions within their district.
The team will perform the following:
1. Material Quantity Report: Annual Summary Report by district, by plant, by project
will be maintained within LaPave.
2. I
ndividual Lab review:
Each district lab reviewed annually by an AASHTO R 18
accrediting entity. Independent Assurance Technician(s) assist the District Lab
personnel with maintaining documentation and preparation for accreditation.
Proficiency Sample Report:
a.
Analyze proficiency data to determine technician compliance and obtain
responses from technicians to address deficiencies.
b.
Annual report of proficiency sample program. Report will include number
of certified technicians, number of “active” technicians, number of
technicians covered by the IA program, number of IA reports that had
deviations, and a summary of how the deviations were addressed along
with the potential systematic solutions to reoccurring deficiencies.
3. Accreditation/Certification report: Summary report listing all accredited labs and
ongoing accreditation status of each laboratory.
4. Independent Assurance (IA) Responsibilities for Plant Verification on System
Based Frequency: The Technician(s) may randomly visit asphalt plant facilities to
verify plant operations and audit the quality of production with no advance notification
to the contractor or the Department.
The IA Inspector may take a random independent sample or split sample with the
Contractor or District personnel for state projects. The asphalt mix may be run at the
Contractor’s facility, the District Lab, or the ATL. Enough mix shall be sampled to
complete the following tests:
G
mm
TR 327
Gyratory compacted to N
design
T 312, TR 304
Mix moisture TR 319 if tested at the production facility
Loose mix for %AC and gradation TR 323, TR 309
The IA Inspector shall perform test independently of the Contractor or Department
personnel. The gyratory briquettes will be tested for bulk specific gravity G
mb
, V
a
, %G
mm
@ N
des
, VFA, and VMA.
POLICY & GENERAL INFORMATION
19
In addition, Quality Control charts, equipment maintenance logs, proficiency sample
records, or other record keeping required for certification may be reviewed at the time
of inspection.
If the tolerances listed in Table 7 of the QA manual are not met, the Technician(s) will
advise the Materials Engineer Administration for disposition and further handling.
5. Dispute Resolution, Forensic Analysis and Other Requests: When needed, the
Independent Assurance Team will be called upon to perform dispute resolution,
forensic analysis and/or technical assistance. Any of the nine District Laboratories or
the Contractors certified laboratory may be used at the direction of the Field Quality
Assurance Engineer for Dispute Resolution and/or Forensic Analysis. The Technician
(s) will provide testing, documentation, and test reports to assist DOTD in the dispute
resolution(s) and forensic analysis as needed.
SECTION 501 – THIN ASPHALT (Design)
20
SECTION 501 – THIN ASPHALT CONCRETE APPLICATIONS
DESIGN
This section describes procedures and documentation required for designing, validating, and
producing an asphalt concrete mixture for use on a DOTD project applying Section 501 of the
Standard Specifications (Thin Asphalt Concrete Applications). It details plant Quality Control and
acceptance, roadway Quality Control and acceptance, and how to pay for 501 asphalt mixtures.
This section shall be used in conjunction with Section 502 (Asphalt Concrete Mixtures) and
Section 503 (Asphalt Concrete Equipment and Processes) of the Standard Specifications.
Information in this section applies to Section 1002 (Asphalt Materials and Additives) and Section
1003 (Aggregates).
A finish course is defined as a 501 thin lift mix placed over a new or existing502 asphalt concrete
pavement or a Portland cement concrete pavement.
The District Laboratory will verify the Contractor’s values of stockpile bulk specific gravities, water
absorption, and consensus properties.
Applicable test procedures are listed in Table 502-1 of the Standard Specifications. A copy of the
following shall be available at the production facility:
Contract documents
Current edition of the Standard Specifications and any Supplementals/Special
Provisions
Material Sampling Manual and Sampling Plans
All applicable testing procedures
Approved Materials List
JMF
AASHTO R18 Documentation
Section 501 mixture specifications differ from Section 502 in the methods and testing as
describe herein.
Mix Design Steps and Approval
Material Procurement and Approval
Material procurement and approval procedures are the same as for Section 502 except the
Contractor will submit a Certificate of Analysis for Micro Deval for conformance to Table 501-2
and subsection 501.02.4.
Aggregate
Coarse Aggregate
The combined aggregates shall be in accordance with design gradation requirements in Table
501-3.
Friction requirement shall meet requirements of 502.02.3.1 and Table 502-3.
SECTION 501 – THIN ASPHALT (Design)
21
Fine Aggregate
. Fine Aggregate Angularity (FAA) of each fine aggregate source shall be measured and the
calculated average blend (AASHTO T 304) or weighted average of individual components shall
be measured in accordance with DOTD TR 121 (mineral filler excluded).
RAP
RAP used in Dense Mix shall meet RAP requirements referenced in sections 502.02.3.2,
1003.01.3.2, and 1003.06.5. All RAP for dense mix shall be processed to pass a 1” screen.
Asphalt Cement
Asphalt cement shall be from an approved source listed on the Approved Materials List. Asphalt
cement grade shall be in accordance with Table 501-1. Substitutions in accordance with Section
501.02.2 are allowed.
Asphalt cement is accepted at the plant by a Certificate of Delivery (CD). A Certificate of Delivery
shall accompany each load delivered to the plant. Asphalt cement testing shall be in accordance
with Section 502. The Contractor shall collect, scan , and email asphalt cement CDs to the
DOTD ADI or DLE. When blending PG67-22 to increase the performance grade of the AC, the
contractor shall submit documentation and testing on blending to support quantities produced.
Additives
Anti-strip or hydrated lime (if used) The Contractor shall collect scan and email CDs for
additives to the DOTD ADI or DLE.
Cellulose or mineral fibers, . The specific requirements for fibers are listed in Section 501.02.6
and Section 1002.02.5. A Certificate of Compliance (CC) shall be submitted to the DLE for fibers.
Design of Asphalt Mixture, Job Mix Formula (JMF)
Mix design steps and approval process are the same as for Section 502. Except for the
following requirements:
Ensure aggregates meet requirements of Table 501-2
A Micro Deval Certificate of Analysis must accompany OGFC and
Coarse Mix JMF submittals for each aggregate.
Gradation bands for Dense Mix, Coarse Mix, and OGFC are in Table
501-1
Gyratory N
design
revolutions will be in accordance with Table 501-1.
Additional Requirements for OGFC Mixtures
OGFC mixture must have a coarse aggregate (+ No. 4 sieve) skeleton with stone-on-stone
contact. Stone-on-stone contact within an OGFC mixture is defined as the point at which the
percent voids of the compacted mixture is less than the Voids in Coarse Aggregate (VCA) .
The VCA of the coarse aggregate only fraction (VCA
DRC
) is determined by compacting the stone
with the dry-rodded technique according to ASTM C29.
SECTION 501 – THIN ASPHALT (Design)
22
When the dry-rodded density of the coarse fraction has been determined, calculate the VCA
DRC
using the following equation from ASTM C29:
100
G
- G
VCA
wCA
swCA
DRC x
Where:
G
CA
= Bulk specific gravity of the coarse aggregate
γ
s
= Bulk density of the coarse aggregate fraction in the dry-rodded condition,
γ
w
= Density of water
V
a
, and VCA
MIX
:
Select three trial blends of aggregate within the aggregate gradation bands as detailed in
Table 501 - 3, “JMF Extracted Gradation and Production Tolerances.
Determine the dry-rodded voids in the coarse aggregate, retained on the No. 4 (4.75 mm)
sieve, of the coarse aggregate only, VCA
DRC
as described above.
Add between 6.5% to 7.0% asphalt cement to each trial blend and compact blend to 50
gyrations in a Superpave gyratory compactor. (Note: At this stage of design, fiber should
be added at the manufacturer’s recommended rate. Fibers are required only if the drain
down requirements are not met. Typical fiber rates are 0.2% to 0.5% of the total weight
[mass] of the mix.)
Determine the % air voids (V
a
), and % voids in the coarse aggregate for each of the
compacted mixes (VCA
MIX
).
o Determine the bulk specific gravity of the mix (G
mb
), using the physical volume.
o Determine the theoretical maximum specific gravity of the mixture (G
mm
), in
accordance with DOTD TR 327.
o Determine the bulk specific gravity of the coarse aggregate fraction (G
CA
), in
accordance with ASTM C127.
o Calculate V
a
, and VCA
MIX
using the following equations:
mm
mb
a
G
G
1100V
CA
mb
CAMIX
G
G
P-100 VCA
Where:
P
CA
= % coarse aggregate in the total mixture
G
mb
= bulk specific gravity of the compacted mixture
G
mm
= theoretical maximum specific gravity of the mixture
G
CA
= bulk specific gravity of the coarse aggregate fraction
Select the aggregate gradation blend that achieves a minimum 18% air voids (V
a
).
To determine the optimum percent of asphalt in the mixture prepare two additional
mixtures using 0.5% and 1.0% additional asphalt cement using the desired aggregate
blend as selected previously and compact using 50 gyrations of the Superpave gyratory
compactor. The optimum percent of asphalt will be determined based on specification
SECTION 501 – THIN ASPHALT (Design)
23
compliance for % air voids and asphalt cement draindown. The percent VCA
MIX
shall be
reported for information.
For design, the asphalt cement draindown test shall be conducted in accordance with
ASTM D6390 on the loose mix at a temperature 18
o
F (10
o
C) higher than normal mixing
temperatures. A maximum 0.3% draindown of asphalt cement by weight (mass) will be
allowed. Draindown will be in accordance with Table 501-1.
For OGFC mixes, use the Physical Volume
Open or coarse asphalt mixtures may be tested for voids using ASTM D3203 (Percent Air Voids
in Compacted Dense and Open Bituminous Paving Mixtures) (Physical Volume) if voids are
greater than 10.0% or water absorption of the compacted gyratory sample is greater than 2.0%
by volume as measured per T 166 7.2.
Where:
A = mass of the specimen in air, g:
B = mass of the surface-dry specimen in air, g: and
C = mass of the specimen in water, g.
Percent of water absorbed by volume =



Traceable calibrated or standardized calipers will be used for measurements used in calculating
volume.
Four measurements for thickness will be at approximately quarter points along the periphery of
the gyratory. Average the four measurements for height for use of calculations. Make two
measurements perpendicular to each other (for a total of four) on both flat surfaces and average
for diameter of the gyratory.
An example for measuring voids using Physical Volume is as follows:
3915.0g = Dry weight of gyratory
2.355 = G
mm
of mix
150.0mm = Averaged diameter of gyratory
Radius (r) = 150mm (diameter) ÷ 2 = 75mm
115.0mm (h) = Averaged height of gyratory
= 3.1416
0.99707 = factor to convert from density (g/cm
3
) to bulk specific gravity (G
mb
)
v = volume
V
a
= voids
h = height of gyratory sample
Volume of a cylinder (gyratory), 

(3.1416)(75.0mm
2
)(115.0mm) = mm
3
(3.1416)(5625)(115.0) = 2032222.5 mm
3
x 0.001 (convert mm
3
to cm
3
) = 2032.2225 cm
3
SECTION 501 – THIN ASPHALT (Design)
24
Rounded to 2032.223 (two places past the final answer)
Density of the gyratory sample = mass (g) ÷ volume ()
3915g ÷ 2032.223cm
3
= 1.926 grams per cubic centimeter (g/cm
3
)
1.926 ÷ .99707 = 1.932G
mb
Converts from density to bulk specific gravity
100 [100 (G
mb
÷ G
mm
)] = % voids in gyratory sample
100 - [100 (1.932 ÷ 2.355)] = V
a
100 [100 x .82038] = V
a
100 82.0 = V
a
18.0 = V
a
STEPS IN SUBMITTAL PROCESS:
Trial Blends with Varying Asphalt Cement Contents (Except OGFC)
Refer to Section 502: Trial Blends with Varying Asphalt Cement Contents of this manual.
Selection of Optimum Asphalt Cement Content
Conform to requirements of Table 501-1. Refer to Section 502 and Table 501-1: Selection of
Optimum Asphalt Cement Content to determine optimum values.
Dust to Effective Asphalt Cement Ratio Evaluation
Dust to Effective Asphalt Cement Ratio of 0.6 1.6 applies to Dense 501 mixes only, not Coarse
Mixes or OGFC.
LWT, Loaded Wheel Test, (AASHTO T 324)
The Contractor will submit LWT results for specimens indicating conformance to Table 501-1.
LWT may be tested at the plant laboratory or using the district laboratory LWT equipment.
Validation of JMF proposal
Validation procedures shall be in accordance with Section 501.05.
A 501 validation lot is the first 1200 tons of a JMF comprised of three 400-ton sublots. Test each
sublot as follows to ensure conformance with Table 501-1:
One aggregate gradation and %AC
One briquette tested for volumetrics (V
a
)
One corresponding Maximum Theoretical Specific Gravity (G
mm
)
In addition, for the validation lot, the contractor shall take for QC:
One asphalt cement draindown (ASTM 6390) for OGFC and coarse mix
One % anti-strip additive rate verification
One Boil Test AASHTO T195 for 98% minimum aggregate coating
With mutual agreement of the contractor and the Department, a fourth sample of plant mixture
may be taken during validation. This sample may be used in place of the first validation plant
sample for purposes of determining lot averages and establishing JMF targets.
SECTION 501 – THIN ASPHALT (Pay)
25
LWT (Rut Testing) Validation of JMF Proposal
After conditional validation, LWT testing shall be performed the next day of production in
accordance with Section 502A minimum of four gyratories or roadway cores that include the top
lift of the underlying surface may be used for LWT testing.
Once completed, the validation data is promptly forwarded to the DLE, the average gradation and
G
mm
measured during validation will be become the JMF targets as per Table 501-3.
The JMF is validated if all of the below are met:
1. The average of test results shall meet 100% pay requirements in Table 501-4
2. The individual test results must meet the tolerances of Table 501-3.
Upon validation of the JMF, the validation results shall be used for acceptance. The average of
the validated results will be used to establish the JMF targets and tolerances.
The Department will evaluate the performance of the mixture on the roadway and ensure the JMF
is not contributing to laydown deficiencies, such as segregation, tenderness, workability, or
surface texture problems. Mixtures identified as causing any laydown deficiency will not be
approved. The Project Engineer or the DLE may reject a JMF or not validate a JMF due to
roadway deficiencies or visible mixture deficiencies.
Individual tests must meet the tolerances of Table 501-3. For validation, if the first sublot does
not meet the tolerances in Table 501-3, the Contractor may exclude that sublot from the validation,
provided adjustments are made to the mix. The validation tonnage may be extended if necessary
to include a fourth sublot and tests. The tonnage for the excluded first validation sublot will be
paid according to table 501-4 and paid as a separate lot.
Failure to Validate
If the mix fails to validate, the DLE may allow one additional attempt before requiring a redesign
of the mixture.
If a JMF fails to validate on a second attempt, a new JMF must be submitted and validation testing
repeated or the Producer may use a previously approved Job Mix Formula. If the JMF does not
validate, the DLE will disapprove the JMF in DOTD’s software. The DLE will notify the Producer
and Project Engineer of the termination of the JMF.
Final Approval of JMF
After meeting the Validation requirements, the DLE makes final approval.
Materials Laboratory Sample Requirements
Approximately 20 grams of No. 4 and +No. 8 asphalt coated aggregate from loose mix obtained
during validation will be submitted to the Materials Lab for GPC analysis.
One quart can of Asphalt Cement will be submitted along with asphalt coated aggregate for GPC
analysis (finger printing) from the validation.
SECTION 501 – THIN ASPHALT (Pay)
26
When an asphalt cement source is changed, one quart can and loose mix as referenced above
shall be submitted to the Materials Lab for GPC analysis.
Definition of a Lot (Thin Asphalt Concrete mixtures)
A standard lot size is 2400 tons comprised of 3 800 ton sublots in accordance with
Section 501.04.
The final sublot of the project may be increased to 1200 tons with the mutual agreement of the
Contractor and Project Engineer. The total tons for the final lot can be increased up to 2800 tons.
Plant Testing for 501 Mixes
A Qualified DOTD Inspector will perform acceptance testing for 501 mixtures.
General requirements are the same as for Section 502, except that draindown must be performed
on OGFC and Coarse Mix to ensure the mixture is within specification limits. Gradation, %AC,
G
mm
, and air voids shall be measured in accordance with Section 501.
The sample requirements for each sublot shall be as follows:
1. Air void contents - QC
2. Theoretical Maximum Specific Gravity Tests, G
mm
- Acceptance
3. Asphalt content determination by ignition- QC
4. Extracted gradations QC for Dense Mix, Acceptance for OGFC and Coarse Mix
5. Coarse Aggregate Angularity QC
One draindown test per lot shall be performed on OGFC and Coarse Mix for QC
LWT testing will be performed every 10,000 tons of production per JMF (4 - 60mm gyratory
specimens). The LWT may be witnessed by the ADI at the plant or sent to the district lab for
testing.
If the average tests for the lot are not within specification requirements, corrective actions shall
be taken or operations ceased. Test results are recorded along with other Contractor/Producer
data within LaPave.
The specified Quality Control Program is a minimum requirement and should not prevent the QC
Technician from performing any tests to ensure consistent production, meeting specifications.
For production days that do not require acceptance testing, the contractor and DOTD inspector
shall jointly sample and test for Quality Control when production is 100 tons or greater. Test data
for this testing shall be entered into LaPave as QC.
The asphalt cement content is based on the Ignition Oven (TR 323) test results along with
correction factors. One correction factor accounts for moisture performed each sample set. The
other for fibers, and loss of aggregate during ignition (JMF correction factor). If the plant delivery
rate of asphalt cement (metered) plus the asphalt credit from RAP (if used) differs by more than
±0.3% from the Ignition Oven (with correction factor) for two consecutive tests, take corrective
SECTION 501 – THIN ASPHALT (Pay)
27
action. Corrective action can be reestablishing the correction factor, recalibrating the asphalt
cement metering system or other systems of the plant. Document and forward to the DLE the
cause and corrective action taken.
The Contractor shall check the rate of anti-strip, mineral filler, lime, or fibers at the beginning of
each operational period, and when necessary thereafter, to ensure the mixture is receiving the
JMF amounts of each material.
Verification
Project sample requirements are as follows:
1. One sample per shipment or Certificate of Compliance (CC) for fibers
2. One transport sample per grade per project for asphalt cement submitted for complete
analysis.
3. One working tank sample per day per grade used for 501 for verification.
Verification sample requirements are as follows:
1. Verify aggregates are on the Approved Materials List with current Micro-Deval (Note:
The Materials Lab will test one full sample sack per project if Micro-Deval values are in
question.)
2. Tests for Flat and Elongated and CAA should be performed on the 12-month or new-
source stockpile samples at the district lab.
3. Verify Anti-Strip additive quantity from meter each production day.
The ADI will sample for verification, to be tested at the district lab, a minimum of one per project
for 501 mixes and every 9600 tons thereafter per project. Adequate mix will be collected and sent
to the district lab to perform the following tests:
District Laboratory Verification of plant results are as follows:
1. One loose mix for G
mm
testing
2. Enough loose mix for one gyratory specimen prepared at N
design
and subsequent V
a
,
VMA, and VFA volumetric calculations. Except for OGFC.
3. One loose mix for asphalt extraction, gradation (No. 4 and No. 200) and %CAA for
OGFC
Applicable tolerances from Table 7 in section 502 in this manual will be used for verification.
Roadway Acceptance
Tack coat application rates will be for acceptance once per lot. Tack coat rate will be measured
and calculated for proper application rate. Tack coat visual acceptance will be in addition to
measurable criteria.
Tack coat application rates for OGFC and Coarse Mix are subject to payment adjustments in
accordance with table 501-4.
Tack coat application rates above the minimum specified in Table 501-1 must be approved by the
Engineer.
For surface tolerance, see Section 502.12 Surface Tolerance and Table 501-5 in the Standard
Specifications.
SECTION 501 – THIN ASPHALT (Pay)
28
Thin lift mixes with high AC content and high voids may need adjustment factors to adjust for yield
and payment. See Appendix
Plant and Stockpile Verification
The DLE will verify the Contractors aggregate gradations, bulk specific gravities, absorptions,
and consensus properties, a minimum of, once every 12-months.
Asphalt Cement
When AC is questionable, send mix and/or asphalt cement to the Materials Lab for analysis. See
GPC testing in section 502 of this manual.
See Additives in the 502 section of this manual for requirements of blending Latex or Crumb
Rubber (CR).
Measurement and Payment
Measurement
Weight measure by the ton will be based on Section 501. Measure the square yards paved and
total gallons of tack coat applied. Report in gallons per square yards. Record tonnage received
based on truck tickets as delivered to roadway.
Payment
Payment for Thin Asphalt Concrete mixtures will be made at the contract unit price per ton. Apply
pay adjustment based on Table 501-4 for G
mm
and Gradation. Pay adjustment is the lowest
determined value. A separate payment adjustment for IRI will be applied per travel lane to the
theoretical tonnage of each lane for the entire length of the project in accordance with Table 501-
5
Asphalt tack coat is a pay adjustment item for OGFC and Coarse mix, but is considered incidental
to 501 Dense Mix. It will be applied in accordance with Section 504. If the engineer adjusts the
application rate of tack coat from that specified by the contract document, payment for the asphalt
mixture will be increased or decreased based on the difference in the applied quantity of asphalt
emulsion shown on paid invoices. The contractor shall provide copies of paid invoices for this
determination.
SECTION 502 – ASPHALT (Design)
29
Section 502 – Asphalt Concrete Mixtures
This section describes the procedures and documentation required for designing, validating, and
producing an asphalt concrete mixture for use on a DOTD project while applying Section 502 of
the Standard Specifications (Asphalt Concrete Mixtures). It details Plant Quality Control,
Roadway Quality Control and Acceptance, and How to Pay for Asphalt Mix. Sections 503 (Asphalt
Concrete Equipment and Processes), 1002 (Asphalt Materials and Additives) and 1003
(Aggregates) also apply.
Applicable test procedures are listed in Table 502-1 of the Standard Specifications. A copy of
each applicable test procedure shall be available at the plant for immediate reference. The
preface contains a listing of appropriate manuals.
Warm Mix Asphalt (WMA) is defined as asphalt concrete mixture that is modified by approved
foaming methods or chemical additives to reduce mixing and compaction temperatures.
Mainline Mixtures 1000 current plan ADT
Projects with current plan ADT 1000 have an option for the contractor to have Mainline Mixture
pay calculated by PWL or average core density.
The contractor shall declare the method of pay calculation for Mainline Mixtures at the Pre-
construction Conference for the project with 1000 current plan ADT. If the contractor does not
make a declaration at the pre-construction conference on Mainline Mixture pay method for
1000 current plan ADT, pay shall be calculated by PWL.
When the contactor chooses Mainline Mixture average core density pay calculations, Table 502-
6b shall be used for JMF design and production specifications.
Payment for Mainline Mixture average core density shall be in accordance with 502.15.2.2.
Mix Design Steps and Approval
Material Procurement and Approval
The Contractor selects and procures materials to utilize in the mix design process. Materials for
an asphalt mix design include, but are not limited to, aggregates, asphalt cement, and anti-strip.
Source ApprovalAll materials are to be on the Approved Materials List (AML). RAP is not listed
on the AML. It is approved by the district lab that the production facility is covered by. RAP is
assigned a Producer Supplier code.
Aggregate
All aggregates used for production of asphalt mixtures shall be submitted to the district laboratory
for verification.
SECTION 502 – ASPHALT (Design)
30
Stockpile SamplesStockpile samples will be tested for verification of the Contractor’s submitted
values, a minimum of, every 12-months. Samples for new sources shall be submitted at least
three weeks prior to the submission of a job mix proposal (JMF). No proposed JMF will be
accepted until all mix components have been verified and approved. RAP stockpiles will be
sampled and tested every six-months.
The contractor shall report results for aggregate properties when the district lab tests for
verification and again in six months. The contractor’s six-month interval report between district
lab verification testing will include G
sb
, absorption, and gradation.
Qualification requirements for coarse aggregate and fine aggregates will comply with section
1003.06 and 502.02.3 Aggregates. Plus No. 4 sieve material is considered coarse aggregate and
minus No. 4 sieve material is considered fine aggregate. Individual aggregate sources with
greater than 10% material passing the No. 4 sieve of a primarily coarse material shall require both
fine and coarse aggregate consensus property testing. Individual aggregate sources with greater
than 10% material retained on the No. 4 sieve of a primarily fine material shall require fine and
coarse aggregate consensus properties. Aggregates tested for fine and coarse properties shall
be mathematically combined for a single value.
For JMF submittals, whatever percentage of a stockpile passes or is retained on the No. 4 sieve
greater than 50.0 percent will classify the material as either fine or coarse for LaPave JMF entry
purposes.
Aggregates shall comply with Table 502-6 or 502-6b Asphalt Concrete General Criteria and Table
502-4 Plant Produced Asphalt Mixture Requirements and Tolerances.
Reclaimed Asphalt Pavement (RAP) is allowed in 502 mixtures at specified percentages. RAP
shall be tested for G
mm,
%AC and gradation. G
se
shall be calculated from the G
mm
, and a G
sb
shall
be calculated from the G
se
. Working stockpiles of RAP will be verified by the District Lab. Verified
RAP stockpiles receive a SiteManager Materials “Producer Supplier” code (PS code). RAP
shall be cold planed in accordance with Section 509, and shall meet the requirements of Section
1003.
The %AC, gradation, G
mm
, calculated G
se
and calculated G
sb
of RAP shall be reported to the
District Lab by the Contractor when stockpile verification samples are taken. The procedures are
in the Determination of Gradation and Bulk Specific Gravity (G
sb
) for Aggregates section of
this manual.
RAP is allowed in 502 mixes except for airports and SMA when:
RAP is stockpiled separately with all material passing a 1 in. screen.
RAP may be further separated into different stockpiles based on gradation and
asphalt content
RAP shall be processed (screened) to pass the 1 sieve before testing.
Friction Rating - For travel lane wearing courses, the total aggregate combination shall comply
with Table 502-3 Aggregate Friction Rating. The table specifies allowable usage according to
mixture type and current plan average daily traffic (ADT). The mixture type will be shown on the
pavement typical sections in the contract plans.
SECTION 502 – ASPHALT (Design)
31
Asphalt Cement
Asphalt cement shall be on the AML. Asphalt cement grade shall comply with Subsections 1002
and 502.02.1 and Table 502-2 Asphalt Cement Usage. Substitutions are allowed in accordance
with Table 502-2. A Certificate of Delivery shall accompany each load delivered to the plant. The
District Laboratory will test working tank samples. The Materials Laboratory will request the
District Laboratory sample transports for refinery verification samples. District Lab employees will
coordinate plant production and transport delivery with Materials Laboratory sample request.
The Contractor shall collect asphalt cement CDs, scan, and email to the DOTD ADI or DLE.
Additives
The Contractor shall collect scan and email CDs, CCs and/or CAs for additives to the DOTD
ADI or DLE.
Anti-Strip
Anti-strip shall be added to all mixtures at the minimum rate of 0.6% by weight of asphalt cement
in accordance with Subsection 502.02.2.1. Anti-strip used shall be on the Approved Materials
List. A Certificate of Delivery for Asphalt Anti-strip Additives shall accompany each load of anti-
strip. Rates less than 0.6% for new formulations of anti-strip shall be approved on a case by case
basis by the DLE.
Hydrated lime, if used, shall be in accordance with Subsection 502.02.2.2 and from a source
listed in the AML. The minimum rate shall not be less than 1.5% by weight of the total mixture.
Hydrated lime shall be added to and thoroughly mixed with aggregates in accordance with
Subsection 502.02.2.2. Hydrated lime may be also added as mineral filler in accordance with
Subsection 502.02.3.3. A Certificate of Delivery shall accompany each load of hydrated lime.
Mineral filler, if used, shall be in accordance with Subsection 502.02.3.3 and Subsection
1003.06.1.6 and an approved product listed in the AML. It shall consist of limestone dust,
pulverized hydrated lime, Portland cement, or cement stack dust. A Certificate of Delivery,
matching a format similar to the CD for Asphalt Materials, shall accompany each load of mineral
filler.
Waste Tire Rubber additive, when used, shall be blended with an AML PG 67-22 material. Add
Crumb rubber as required to meet grade PG 76-22rm. Use a maximum size rubber particle of 30
mesh crumb (90-100% passing the No. 30 sieve). In accordance with 1002.02.2, Waste Tire
Rubber additive shall require the Contractor to perform DSR testing of the blended material. The
contractor shall test DSR daily while in production and enter test results in LaPave.
Latex Additive, when used, shall be in accordance with Subsection 502.02.2.4. Latex added at
the Contractor’s plant shall be blended at a minimum of 1.0% residual latex by weight of asphalt
cement to an AML PG 67-22 material and in accordance with Section 503.05.2. Latex blended
asphalt shall meet PG 70-22m specification requirements using pre-qualified asphalt material and
latex. Latex additive shall require the Contractor perform DSR testing of the blended material.
The contractor shall DSR test daily while in production and enter test results in LaPave.
SECTION 502 – ASPHALT (Design)
32
Approval Process for Plant-Modified Asphalt Cement
The following procedures are required for plant blending latex or crumb-rubber with a
Performance Graded (PG) asphalt cement (AC), listed on the Approved Materials list, to meet a
higher Performance Grade. This is also referred to as grade bumping. Pre-blended and post
blended AC shall meet the requirements of Section 1002 and Table 1002-3 of the Louisiana
DOTD Standard Specifications.
The initial request for approval of plant blending for modifying asphalt cement shall be submitted
to the Materials Engineer Administrator.
The contractor shall maintain equipment and conform to DOTD specifications to maintain approval
for blending. After initial approval for plant blending from the Materials Engineer Administrator,
continuing approval shall be part of the biennial plant certification.
1. Plant
a. Submit a proposed Plant Equipment Design Diagram to the Materials
Engineer Administrator
b. Provide manufacturer documentation stating the equipment is appropriate for
the proposed materials and flow rates. Mixers, Mills, etc.
c. Latex blending requires an inline sampling point after mixing and before the
addition of anti-strip
d. A totalizing meter or other verifiable measuring system shall be used to
measure the quantity of additive and verify AC quantities used
e. Documentation for equipment calibration shall be provided and maintained for
review
f. Documentation for additive quantities and AC quantities used shall be
maintained and provided on request
g. The DLE shall inspect the plant and blending equipment before it’s use for
DOTD projects
2. Asphalt Design Blend (ADB) for DOTD Materials Lab Submittal
a. Provide complete laboratory tests results for the proposed asphalt cement.
The test results shall be of the proposed AC and modifier at the proposed
mixing ratios.
b. The blend shall conform to the specifications of Table 1002-3 in the Standard
Specs
i. AC feed stock shall be PG 67-22
ii. Latex shall meet specifications for PG 70-22m
iii. Crumb-rubber shall meet specification for PG 76-22rm
c. All proposed types, brands, and percentages shall match those actually used.
NO SUBSTITUTIONS or MODIFICATIONS
d. Any changes to products or percentages shall require a separate sample
submittal to the Materials Lab for verification
e. The supplier shall provide verification of the compatibility of materials
f. The contractor shall provide a split sample for DOTD verification (see
Sampling and Testing)
g. All blends shall be approved by the Materials Engineer
h. Modifications to the blend shall require a new blend submittal and approval
SECTION 502 – ASPHALT (Design)
33
3. Sampling, Testing and Approval
a. Process Approval Sample Prior to producing mix for a DOTD project,
provide 5 split samples of production plant-modified liquid AC. The contractor
shall provide a full analysis of production material for at least 2 of the 5 split
samples. The Materials Lab shall randomly select and test 2 of the 5 split
samples to verify results. No mix shall be produced for DOTD projects until
the complete analysis results are complete and approved the Materials Lab.
b. Approval for production by the Materials Engineer shall be based on
compliance of testing results and review of documentation. Approval shall be
communicated to the contractor and the District Lab Engineer.
c. During production, the quantity of additive shall be monitored and
documented twice daily by approved methods for conformance to Asphalt
Design Blend
d. Quality Control
i. The Contractor shall provide full analysis on at least 2 samples per
month (approximately every 15 days)
ii. The contractor shall provide high-temperature analysis of the material
on a daily basis using the Dynamic Shear Rheometer (DSR).
Samples shall be taken during JMF validation days, but not required
to test until validation is complete.
iii. Samples shall be taken and documented daily for visual observation
to determine if there is any incompatibility. Documentation shall be
reviewed by the ADI during plant visits. Signs of incompatibility are
white or yellow flecks, clumps of rubber or polymer, sludge,
separation of materials, and/or an obvious skin of material over the
top of the sample. If any of these are observed, reject the material
and/or process based on incompatibility.
e. Verification - The ADI shall take a minimum of one additional random sample
per project per type of AC to send to the Materials Lab for complete analysis.
f. Substandard material Projects that have identified substandard material will
be subject to:
i. Removal and replacement, or at the Chief Engineer’s option:
ii. 50% pay
Fibers, when used, shall be in accordance with Subsection 1002.02.5. Fibers shall be a cellulose
or mineral fiber. Fibers shall be added at a minimum rate of 0.1% by weight (mass) of mixture
and at a rate sufficient to prevent draindown.
Natural sand, when used, shall be in accordance with the requirements of Table 502-6 or 502-
6b, and Section 1003.06.3 with a maximum of 25% passing the No. 200 sieve.
Warm Mix additives, when used, shall be in accordance with Section 1002.02.4.
Foaming with water or chemicals may be used for warm mix with approval of the DLE.
SECTION 502 – ASPHALT (Design)
34
Design of Asphalt Mixture, Job Mix Formula (JMF)
Listed below are the general steps required to design, validate, and approve an asphalt mixture
according to Section 502. Using the material and procurement process listed above, proceed
with the following steps for approval of JMFs.
Determination of Gradation and Bulk Specific Gravity (Gsb) for Aggregates
Gradation
The Contractor shall obtain samples from each proposed stockpile for gradation determination.
An accurate gradation analysis is required for blending analysis, and the determination of the
consistency of incoming material. The District Lab will perform gradation testing on 12-month
stockpile verifications. RAP stockpiles will be sampled and tested for verification from each
asphalt plant a minimum of every six-months.
It is recommended Contractors secure samples of all bulk shipments of aggregates delivered to
the plant site. The gradation results of these shipments should be determined prior to their
addition to a working stockpile. Documentation of these continuous stockpile gradation and
specific gravity results shall be kept on file so varying trends of the aggregate source may be
documented. The Contractor shall report stockpile gradations to the DLE every 12-months along
with G
sb
, absorption, and consensus properties. Gradation, G
sb
, and absorption shall be reported
by the contractor at the 6-month interval between complete stockpile sample verification. The
contractor shall continue to use 12-month District Lab verified values unless values change
enough to warrant full verification testing to establish new values.
Aggregates shall be handled in a manner that will not be detrimental to the final mixture.
Stockpiles shall be built in a manner that will not cause segregation. Segregation can be
minimized if stockpiles are built in successive layers, not in a conical shape. Constructing
stockpiles in layers enables different aggregate fractions to remain evenly mixed and reduces the
tendency of large aggregates to roll to the outside and bottom of the pile. Stockpiles shall be
located on a clean, stable, well-drained surface to ensure uniform moisture content throughout
the stockpile. The area in which the stockpiles are located shall be large enough for stockpile
separation, so no intermixing of materials occurs. Stockpiles shall not become contaminated with
deleterious materials such as clay balls, leaves, sticks or non-specification aggregates. Materials
shall not become contaminated nor segregated when they are transported from stockpiles to cold
feed bins. Aggregates are often moved from stockpiles to cold feed bins with a front-end loader.
The operator should proceed directly into the stockpile, load the bucket and move directly out,
and should not scoop aggregate from only the outside edges of the stockpile.
SECTION 502 – ASPHALT (Design)
35
Figure 2-1
There may be aggregate sources that have 10% or more passing or retained on the No. 4 sieve,
but because of the overall gradation, it may be impractical to obtain enough of the lesser material
to conduct testing associated with the smaller fraction. It will be at the discretion of the DLE to
exclude testing in such situations.
Bulk Specific Gravity (Gsb)
Coarse aggregate is defined as material retained on the No. 4 sieve.
Fine aggregate is defined as material passing the No. 4 sieve.
Once aggregate materials have been stockpiled at the plant and are approved for use, the bulk
specific gravity of each mineral aggregate shall be determined. The Department will verify G
sb
of
samples from each aggregate stockpile. The Contractor shall test a sufficient number of samples
to ensure consistency of their stockpiles.
Use AASHTO Test Procedure T 84 to determine bulk specific gravity (G
sb
) and absorption for each
proposed fine aggregate. When a primarily fine stockpile material has more than 10% retained on
the plus No. 4 sieve, both T 84 and T 85 shall be performed. The material tested for G
sb
shall be
washed (AASHTO T84 X1.1) over the No. 200 sieve.
The after wash gradation should have less than 4% passing the No. 200 sieve. If there is doubt
this has been met, the technician can check the sample by weighing the after washed-dried
sample, then re-sieve, calculating the passing #200. Divide the weight of the material in the pan
that passed the #200 by the after wash-dried weight of the whole sample. (Wt. of material in pan
(passing #200)/Wt. of dried washed aggregate) x 100 = % passing #200)
When a stockpile material has > 20% passing the No. 200, the sample shall be dry sieved over the
No. 100 sieve (the +100 material will be washed over the No. 200 sieve). T 84 will be used for the
G
sb
and absorption of the minus No. 4 to the plus No. 100. An Apparent Gravity will be run on the
minus No. 100 material.
The reason for breaking the sample at the No. 100 sieve is for ease of acquiring enough fine
material for testing.
Test as follows:
SECTION 502 – ASPHALT (Design)
36
AASHTO T-100 Specific Gravity of Soils
Modified:
Balance accurate to 0.1 gram
500 ml volumetric flask
Use boiling method
Allow sample to cool to room temperature
Condition in a 23° C ±1.7° C water bath for 1 hour
Sample size: 250 g ± 10 g
Gently boil the sample on a hot plate for 30 minutes
Allow sample to cool before placing in a 23° C ±1.7° C water bath
No. -4 G
SB
(T-84) Wash 200 Sieve
Material with greater than 20% passing the No. 200 sieve
The Apparent Gravity of the minus No. 100 material shall be mathematically combined in proportion
to the G
sb
of plus No. 100 and minus No. 4 material. Absorption will be that of the minus No. 4 and
plus No. 100
Example:
49% passing the No. 100 with a G
se
of 2.675
51% retained on the No. 100 with a AASHTO T 84 G
sb
of 2.642 and
absorption of 0.78
.49 x 2.675 = 1.31075
.51 x 2.642 = 1.34742
combined 2.65817 → 2.658 absorption 0.78
Use AASHTO Test Procedure T 85 to determine bulk specific gravity (G
sb
) and absorption for each
proposed coarse aggregate source.
For aggregate sources that are primarily coarse and contain 10% or less material by weight passing
the No. 4 sieve, a G
sb
determination on that passing portion will not be required. Should the
proposed aggregate stockpile contain more than 10% passing the No. 4 sieve, the finer portion
SECTION 502 – ASPHALT (Design)
37
shall be separated and tested in accordance with AASHTO T 84. The results, for both coarse and
fine portions, shall be mathematically combined in proportion to amounts retained on the No. 4 and
passing the No. 4 to produce a single G
sb
value for the source. The G
sb
is used to calculate VMA
and asphalt absorption. False high values for G
sb
will lead to false high VMAs and negative asphalt
absorptions. If negative asphalt absorptions are calculated, the G
sb
is in error. When negative
asphalt absorption is reported on a JMF or reported during production, the DLE shall investigate.
The Contractor may use the calculated (weighted average) values for G
sb
on the proposed JMF
provided each individual aggregate test value is within the ranges of Table 3 at the time of
verification testing when compared to the district laboratory’s values. The tolerances for stockpiles
tested using both T 84 and T 85 shall be a weighted average based on percentage of the fine and
coarse fractions.
Example:
-4 material 50% - tolerance - 0.030 = 0.015
+4 material 50% - tolerance 0.020 = 0.010
Combined gravity tolerance = 0.025
The values obtained for annual stockpile verification testing shall be used on JMF submittals until
the next yearly verification testing is completed. If the contractor has data to show values have
drifted before annual testing, they may present the data to the DLE and request re-testing.
The DLE is responsible for collecting data for each verification stockpile sample tested by the
Contractor and District Lab independently.
Table 3
Bulk Specific Gravity Tolerances
Multi-Laboratory Precision for Bulk Specific Gravity (G
sb
)
G
sb
Fine Aggregate No. 4 Sieve
±0.030
Coarse Aggregate +No. 4 Sieve
±0.020
Should the Contractor’s values be outside the range(s) shown in Table 3 when compared to the
district laboratory, both parties shall jointly run a third sample with results used for the proposed
JMF submittals.
Bulk specific gravity values agreed upon by this procedure shall be used on subsequent job mix
formula submittals. The G
sb
may be retested when requested by the contractor and at the
discretion of the DLE.
RAP must be dried to a constant mass in accordance with DOTD TR 323 prior to testing.
A minimum of three RAP samples representing each RAP stockpile will be tested and the results
averaged. The contractor is required to report the results of the individual tests along with the
averaged value. The averaged value shall be used on JMFs.
SECTION 502 – ASPHALT (Design)
38
RAP %AC will be determined in the ignition furnace per TR 323. A correction factor of 0.4 (at the
time of this publication the TR is in the process of being approved to match this value) will be
deducted from the “Percent Loss” obtained from the furnace. If contractor results are within ±0.3%
AC content of the District laboratory results, the Contractor %AC results will be approved for use
(this comparison and final value used will be automatically determined in LAPAVE). Aggregate
from the determination of %AC will be sieved to determine the RAP gradation. Measure the
G
mm(RAP)
to calculate the G
se(RAP)
of the minus 1” RAP. The G
se(RAP)
shall be used to back calculate
a G
sb
of the RAP aggregate for use on JMF submittals. G
mm(RAP)
, %AC, G
se(RAP)
, and back
calculated G
sb
of the RAP aggregate will be verified by the DOTD District Lab when conducting
six-month RAP stockpile sample testing. RAP values may be retested and reverified at the
discretion of the DLE. Contractors that fractionate RAP into different nominal sizes shall stockpile
and test separately.
Values used for RAP testing:
G
b
= 1.03
P
b(RAP)
= Ignition furnace percent loss minus the correction factor of 0.4
P
ba(RAP)
= 1.0%
Formula for determining G
se(RAP)
:
Formula for back calculating G
sb(RAP)
:







 
When determining the composite gradation for mixtures containing RAP, consider the RAP
aggregate as an aggregate source, so that the total aggregate percentages, including RAP
aggregate, equal 100%.
A water absorption of 1.0% will be used when entering RAP on the JMF input page.
Consensus Aggregate Test Evaluations
The consensus aggregate tests determine properties of aggregates that contribute to the
performance within asphalt pavements. The consensus tests are:
Coarse Aggregate Angularity (DOTD TR 306 Double Face)
Fine Aggregate Angularity (DOTD TR 121)
Flat and Elongated Count (ASTM D4791)
Sand Equivalency (DOTD TR 120)
b
RAP
b
RAPmm
RAP
b
RAP
se
G
P
G
P
G
)(
)(
)(
)(
100
100
SECTION 502 – ASPHALT (Design)
39
The required specifications for these aggregate properties are in Tables 502-6 and 502-6b. They
are based on traffic level and position within the pavement structure. Materials near the pavement
surface subjected to high traffic require more stringent consensus property specifications. They
are intended for application to a proposed aggregate blend, not to individual components.
However, they may be run on individual aggregate sources and mathematically combined.
Individual components may be tested so that poor materials may be identified.
Coarse Aggregate Angularity (CAA)
CAA is required only for aggregate stockpiles having 10% or more retained on the No. 4 sieve.
CAA is determined in accordance with TR 306 (Double Faced) on the coarse material. The test
ensures a high degree of aggregate internal friction and rutting resistance. [The minimum values
for the test are in Tables 502-6 and 502-6b for each Level, type of mix, and nominal maximum
size (NMS) aggregate.]
If contractor results are within ±3% CAA content of the District laboratory results, the Contractor
CAA results will be approved for use. If not, the Contractor shall run a third sample jointly with
the DLE’s representative. The Contractor shall use this jointly determined value for JMF
submittal.
The Contractor shall determine and report individual source CAA on the JMF. The CAA of the
composite mixture is calculated by weighted average based on aggregate proportions and
individual CAA values.
When mathematically combining CAA, use the following equation:
p3
T
3
p2
T
2
p1
T
1
A
P
P
A
P
P
A
P
P
C
Where:
C = Composite, CAA
P
1
, P
2
, and P
3
= % Aggregate From Cold Feed Used for Consensus Properties
P
T
= Total of % Aggregate Used for Consensus Properties
A
p
= Aggregate CAA Properties
Fine Aggregate Angularity (FAA)
FAA is required only for aggregate stockpiles having 10% or more passing the No. 4 sieve. To
calculate fine aggregate angularity for a blend, use a weighted average based on the percentages
of each aggregate in the blend that meets the above criteria.
FAA is determined in accordance with DOTD TR 121 using the bulk specific gravity, (G
sb
), of the
aggregate washed over the No. 200 sieve. The property ensures a high degree of fine aggregate
SECTION 502 – ASPHALT (Design)
40
internal friction and rutting resistance. Higher FAA values (voids) means more fractured faces.
(The minimum values for this test are in Tables 502-6 and 502-6b for each level, type of mix and
NMS size.)
If contractor results are within ±2% FAA of the District laboratory results, the Contractor FAA
results will be approved for use. If not, the Contractor/Producer shall then test a third sample
jointly with the DLE’s representative. The Contractor shall use the jointly determined value for
proposed JMFs.
Although the individual source (FAA) is reported on the JMF, the FAA of the composite mixture is
calculated by weighted average based on aggregate proportions and individual FAA values
reported on the JMF.
When mathematically combining FAA, use the following equation:
#100
2
#8
22
#100
1
#8
11
2
#100
2
#8
221
#100
1
#8
11
%P%PP%P%PP
Ap%P%PPAp%P%PP
C
Where:
C = Composite FAA
P
1
, P
2
= % Aggregate From Cold Feed Used for Consensus Properties
%P
1#8
& %P
2#8
= % Passing No. 8
%P
1 #100
& %P
2 #100
= % Passing No. 100
A
p
= FAA Aggregate Properties
There may be aggregate sources with 10% or more passing the No. 4 sieve, but because of the
overall gradation, it may not be practical to obtain enough material to perform FAA. It will be at
the discretion of the DLE to perform FAA testing on such stockpiles.
Flat and Elongated (F&E)
F&E is required only for aggregate stockpiles having 10% or more retained on the No. 4 sieve .
Flat and elongated is determined in accordance with ASTM D4791 using the coarse aggregate
portion retained on the No. 4 sieve. The characteristic is the percentage by weight of coarse
aggregates that have a maximum to minimum dimension greater than five to one. Elongated
particles are undesirable because they have a tendency to break during construction and under
traffic. The maximum values for this test are ins Tables 502-6 and 502-6b.
The district laboratory will verify the F&E value. If both are within specification limits, the
Contractor/Producer’s results may be used. If not, the Contractor/Producer shall test a third
sample jointly with the DLE representative. The Contractor shall use this jointly determined value
for JMF submittal.
The individual source results for F&E particles are reported on the JMF, the F&E of the composite
mixture is calculated by weighted average based on aggregate proportions and the individual F&E
values.
When mathematically combining F&E, use the following equation:
SECTION 502 – ASPHALT (Design)
41
p3
T
3
p2
T
2
p1
T
1
A
P
P
A
P
P
A
P
P
C
Where:
C = Composite, F&E
P
1
, P
2
, and P
3
= % Aggregate From Cold Feed Used for Consensus Properties
P
T
= Total of % Aggregate Used for Consensus Properties
A
p
= Aggregate F&E Properties
Sand Equivalent (SE)
SE is required for all natural sands, having 10% or more passing the No. 4 sieve and less than
25% passing the No. 200 sieve. Natural sands having greater than 25% passing the No. 200
sieve are not allowed (1003.06.3). Clay lumps shall not exceed 0.5 percent by weight when
tested in accordance with DOTD TR 119. Sand equivalency requirements shall apply to
individual natural sand sources only and do not apply to manufactured fines or fines
produced from crushing operations (e.g., screenings, No. 10s and No. 11s). The minimum
values for this test are in Tables 502-6 and 502-6b for each level, type of mix, and NMS size.
SE, sometimes referenced as clay content, is determined in accordance with TR 120 using fine
aggregate portions of the composite blend (natural sands only) passing the No. 4 sieve. Clay
content is the percentage of clay material contained in the aggregate fraction passing the No. 4
sieve.
The contractor shall determine the SE value for each individual natural sand used. The SE of the
composite mixture is calculated by weighted average based on aggregate proportions and the
individual SE values. The district laboratory will verify SE values. The district lab’s and
contractor’s results must meet specification limits. If not, the Contractor/Producer shall then test
a third sample jointly with the DLE representative. The Contractor shall use the jointly determined
values for JMF submittals.
When mathematically combining SE, use the following equation:
p2
T
2
p1
T
1
A
P
P
A
P
P
C
Where:
C = Composite SE
P
1
, P
2
= % of individual natural sands from the cold feed
P
T
= % of total natural sand from the cold feed
A
p1,
A
p2
= SE Properties
SECTION 502 – ASPHALT (Design)
42
Table 4
Contractor and DOTD Tolerances for Stockpile Testing
Test
Description
Tolerance
T 84
AASHTO G
sb
of Fine Aggregate
±0.030
T 85
AASHTO G
sb
of Coarse Aggregate
±0.020
T 84 & T 85
Water Absorption
±0.5%
TR 121
Fine Aggregate Angularity (FAA)
±2*
TR 306
Coarse Aggregate Angularity (CAA)
± 3%*
ASTM D4791
Flat and Elongated (5:1)
*
TR 323
RAP Asphalt Content - %AC
±0.3%
TR 120
Sand Equivalent
±9*
* Both DOTD district laboratory and the Contractor’s results must be within
specification. If the DOTD results are not within specification or tolerance, the
Contractor and DOTD will jointly perform the test that does not meet
specification.
Blending Aggregates to Meet Specified Gradation
Following bulk specific gravity (G
sb
) determinations, gradation, and aggregate consensus tests
analysis, the Technician must determine a master composite blend of the proposed, approved
aggregates to meet the requirements of the mixture type indicated on the typical sections in the
project plans. Table 502-4 in the Standard Specifications lists a nominal maximum size aggregate
for each type, a specification gradation limit for each mixture type, and tolerances for the proposed
JMF blend.
The following are defined as:
Nominal Maximum Size (NMS)One sieve size larger than the first sieve to retain
more than 10% by weight of the combined aggregates.
Maximum Size (MS)One sieve size larger than the nominal maximum size.
With the mixture type known, the Contractor can begin to mathematically blend the proposed
aggregates to meet requirements of Table 502-4. Tables 502-6 and 502-6b specify the maximum
percentage of natural sand and RAP allowed in asphalt concrete mixtures.
NOTE:
The aggregate source properties, Gradation, Gsb, CAA, FAA, F&E, and SE
must be verified by the District Lab personnel at minimum of every 12-
months. RAP must be verified at a minimum of every 6 months. If material
properties change beyond the allowable verification limits, the DLE will
disapprove the existing JMF.
SECTION 502 – ASPHALT (Design)
43
The maximum natural sand percentage is calculated by the percentage of
new aggregate
The maximum percentage of RAP is calculated by percentage of total mix.
Once the aggregates are mathematically blended to meet requirements of Section 502, the
composite gradation is plotted on the appropriate Asphalt Concrete Gradation 0.45 Power Curve
for the corresponding nominal maximum size aggregate. The 0.45 power curve uses a unique
graphing technique to show the cumulative particle size distribution of an aggregate blend. The
ordinate (vertical axis) of the chart is percent passing. The abscissa (horizontal axis) is an
arithmetic scale of sieve size in mm of the opening, raised to the 0.45 power. On these charts,
the maximum density grading for a particular maximum size corresponds to a straight line drawn
from the origin to the selected maximum aggregate size. This maximum density line is
approximate, but serves as a useful reference in proportioning aggregates. These power curves
also depict other features.
DOTD allows for all mixtures produced under Section 502 to be either on the coarse or the fine
side. A coarse and fine gradation plot on the 0.45 power curve is shown in Figure 2-2.
Figure 2-2 0.45 Power Curve with Coarse and Fine Gradations
Care should be taken in the selection of the final composite aggregate blend. Many coarse graded
blends may, if not properly designed and compacted, lead to very porous pavements that allow
water to permeate the base and subbase.
Following is an example of gradation requirements and a typical fine side proposed composite
gradation ½-in. NMS:
SECTION 502 – ASPHALT (Design)
44
Table 5
Example Gradation Tolerances and Limits
Sieve Size
Control
Points
Mix
Tolerance
Proposed
JMF
*Validated
JMF Limits
1.0 in.
± 4
100
100
¾ in.
100
± 4
100
100
½ in.
90-100
± 4
99
95-100
3/8 in.
89 max
± 4
89
*85-93
No. 4
± 4
57
53-61
No. 8
29-58
± 3
34
31-37
No. 16
± 2
23
21-25
No. 30
± 2
17
15-19
No. 50
± 2
12
10-14
No. 100
± 2
7
5-9
No. 200
4.0-10.0
± 0.7
5.1
4.4-5.8
For gradation purposes, all values are reported to the nearest whole number with the exception
of the No. 200 sieve size, which is rounded to the nearest tenth.
Note the mix tolerances are applied to the proposed JMF to determine the allowable upper and
lower limits. Tolerance limits may only exceed control points during production, but not on the
JMF, nor during validation. *For example, during validation, the JMF limits in the example above
for the 3/8-in. sieve are 85 89.
Blending Aggregates to Meet Friction Rating Requirements for Travel Lane Wearing
Courses
Friction Rating A friction rating is a relative indicator of the skid resistant properties of the
aggregate. Friction ratings are assigned by the DOTD Materials and Testing Section to an
aggregate source in accordance with Table 1003-3. These assigned friction ratings are listed for
each aggregate on AML.
Aggregates used in asphaltic mixtures for the final lift of the travel lane wearing course have
friction rating requirements in accordance with Table 502-3. Friction requirements are based on
current plan average daily traffic (ADT) as shown on the plans and based on mix use and type.
Generally frictional aggregates are not required in binder or base courses, shoulders, or in
mixtures used for bike paths, curbs, driveways, guardrail widening, islands, joint repair, leveling,
parking lots, patching, or widening. If the mixture type specified on the typical section of the plans
is Level 1F or 2F, special friction rating requirements apply. Level 1F or 2F asphalt mixtures
have the same requirements as travel lane wearing course with current plan ADT > 7000.
Table 502-3 on the next page is a reprint from the Standard Specifications:
SECTION 502 – ASPHALT (Design)
45
This chart shows the allowable usage of aggregates.
Table 6
ALLOWABLE USE
CURRENT
PLAN ADT
FR I
FR II
FR III
FR IV
> 7000
Allowed
Allowed
*Allowed only
with 30% FR I
or 50% FR II
Not Allowed
2500 to 7000
Allowed
Allowed
Allowed
Not Allowed
<2500
Allowed
Allowed
Allowed
*Allowed only
with 50% FR I
or 50% FR II
*In the two special “*Allowed only with…” cases above, the FR I or FR II aggregates must
not have more than 10 percent passing the No. 8 sieve. Otherwise, they are too fine to be
counted as a friction aggregate.
Consider aggregates C and D found in Example 1 on the next page. Using the Allowable Use
Chart above, notice that FR I is allowed. However, Aggregates A and B with FR III, are only
allowed if there are sufficient amounts of FR I or II in the blend. Combining the percentages
Table 502-3
Aggregate Friction Rating
Friction Rating
Allowable Usage
1,2
I
All mixtures
II
All mixtures
III
All mixtures, except mainline wearing courses with plan
current plan average daily traffic (ADT) greater than 7000
IV
All mixtures, except mainline wearing courses
1
When current plan ADT is greater than 7000, blending of Friction Rating III aggregates and Friction
Rating I and/or II aggregates will be allowed for travel lane wearing courses at the following
percentages. At least 30 percent by weight (mass) of the total aggregates shall have a Friction
Rating of I, or at least 50 percent by weight (mass) of the total aggregate shall have a Friction
Rating of II. The Friction Rating I and Friction Rating II aggregates used to obtain the required
percentages shall not have more than 10 percent passing the No. 8 (2.36 mm) sieve.
2
When the current plan average daily traffic (ADT) is less than 2500, blending of Friction Rating
IV aggregates with Friction Rating I and/or II aggregates will be allowed for travel lane wearing
courses at the following percentages. At least 50 percent by weight (mass) of the total aggregate
in the mixture shall have a Friction Rating of I or II. The Friction Rating I and Friction Rating II
aggregates used to obtain the required percentages shall not have more than 10 percent passing
the No. 8 (2.36 mm) sieve.
SECTION 502 – ASPHALT (Design)
46
of Aggregate’s C and D, equals 34% (14 + 20,) which is greater than the 30% required. Both
have more than 10% passing through the No. 8 sieve, and cannot be counted as frictional
aggregate, and are considered not approved as an appropriate blend. Note that RAP is not
considered frictional aggregate.
EXAMPLE 1:
Consider this JMF submitted for a travel lane wearing of current plan ADT 21,000.
AGGREGATE
NAME
% of Total
Aggregate on JMF
FR from AML
% passing No. 8
A - # 78 LS
22
III
0
B - # 7 LS
20
III
2
C - # 11
14
I
29
D Black # 11
20
I
16
E RAP
18
N/A
50
F Coarse Sand
6
N/A
86
100 % total
EXAMPLE 2:
Consider this JMF submitted for a travel lane wearing of current plan ADT 8200.
AGGREGATE
NAME
% of Total
Aggregate on JMF
FR from AML
% passing No. 8
A - # 78 SS
36
I
0
B - #7 LS
24
III
2
C - # 11 LS
25
III
29
D Coarse Sand
15
N/A
86
100 % total
Using the Allowable Use Chart from the previous page and Example 2, notice Aggregate A is
allowed. Aggregates B and C are allowed only if there is a sufficient % of FR I aggregate. The
% of Aggregate A is 36%, which is greater than the 30% required. Aggregate A has less than
10% passing the No. 8. It can be counted. This blend is approved.
Determination of RAP JMF Composite
Given:
15% RAP in mixture
0.8% AC from RAP
3.4% New AC to be added
SECTION 502 – ASPHALT (Design)
47
Step 1: Calculate % AC in reclaimed material.
Already completed in assumption
To determine total AC content that will be attributable by RAP:
(% RAP/100)(% AC Residual from RAP)
Step 2: Determine the % of RAP (by weight) in mixture.
Subtract %AC in RAP from % RAP in mixture
15% - 0.8% = 14.2% Total RAP aggregate in mixture
Steps 3 through 5 Determine Total New Aggregate.
For this example new aggregates have been given as follows for VCF%
35.0% - SST #78
33.0% - LS #78
17.0% - LS #11
15.0% - Coarse Sand
100% Total New Aggregate
Step 6: Calculate total material to be added to the new aggregate.
A) Add:
% RAP Aggregate (14.2%)
% Reclaimed Asphalt (0.8%)
% New Asphalt Cement (3.4%)
14.2% + 0.8% + 3.4% = 18.4%
B) Subtract this percentage of material to be added to the new aggregate
100% - 18.4% = 81.6%
C) Convert to Decimal
81.6% = 0.816
D) Multiply this decimal times the bin proportions to determine mix percentages.
(% Total of new aggregate for each material) determined in Steps 3 through 5.
SST #78
35.0% x 0.816 = 28.6%
LS #78
33.0% x 0.816 = 26.9%
LS #11
17.0% x 0.816 = 13.9%
Coarse Sand
15.0% x 0.816 = 12.2%
Step 7: Mix Percentages
SST #78
28.6%
LS #78
26.9%
LS #11
13.9%
Coarse Sand
12.2%
RAP
Aggregate
14.2%
%AC from
RAP
0.8%
% New AC
3.4%
SECTION 502 – ASPHALT (Design)
48
TOTAL:
100.00%
Step 8: Aggregate Percentages for Bulk Specific Gravity Computation
A.) Total aggregate = 28.6 + 26.9 + 13.9 + 12.2 + 14.2 = 95.8
B.) New % of each aggregate by % of total aggregate = (for example) 28.6/.958 = 29.9
SST #78
29.9%
LS #78
28.1%
LS #11
14.5%
Coarse Sand
12.7%
RAP Aggregate
14.8%
TOTAL:
100.00%
Trial Blends at Varying Asphalt Cement Contents
The Contractor, after determining the composite aggregate blend, shall prepare three trial blends
of asphalt mixtures with varying percentages of asphalt cement. Trial blends are usually produced
in the design laboratory but may be produced through the asphalt plant.
One blend shall be prepared at an asphalt cement content near anticipated optimum (as defined
by a specified air void content, V
a
). A second trial blend shall be prepared at an asphalt cement
content approximately 0.5% less than the first trial blend. A third trial blend shall be prepared at
an asphalt cement content approximately 0.5% greater than the first trial blend. A minimum of
two gyratory briquettes @ N
des
shall be prepared at each of the trial asphalt cement contents. The
mixing and compaction temperature used for preparing the trial mixes shall be as recommended
by the Supplier.
Unless procedures require otherwise, the laboratory produced mix shall be aged 2 hours and
plant produced hot mix shall be aged 1 hour at the compaction temperature (±10°F). Warm mix
aging time is 2 hours. When the aggregate water absorption is > 2%, the oven aging time
for plant-produced mix shall be 2 hours.
For design purposes, the Contractor may either:
1. test one loose mix near optimum AC content for G
mm
and calculate the new G
mm
’s
for the high and low AC content trials or
2. test 3 loose mix samples for G
mm
at each trial blend asphalt cement content.
Gyratory briquettes shall be tested for the following:
1. Bulk Specific Gravity, G
mb
at N
design
2. Air Voids, V
a
at N
design
3. Voids in Mineral Aggregate, VMA at N
design
4. Voids Filled with Asphalt, VFA at N
design
5. % G
mm
at N
initial
6. % G
mm
at N
design
SECTION 502 – ASPHALT (Design)
49
Plot % AC versus volumetrics (Voids, VMA, VFA). Select the %AC at the voids required by the
specifications for the type mix in order to create a verification blend with this %AC. This means
that design asphalt cement content of the mixture is selected at the percentage yielding the
median percentage of the range of air voids (which is 3.5% for all 502 asphalt mixtures) and
yielding the required design target for VFA (See note 5 Table 502-6 and table 502-6b). All
calculated and measured mix properties at this asphalt cement content should be evaluated and
compared to specified values in Table 502-6 or 502-6b. If all design criteria are not met, some
adjustment is necessary or the mix may need to be redesigned.
For this verification blend, retest G
mm,
%AC and the following volumetrics:
1. Bulk Specific Gravity, G
mb
at N
design
2. Air Voids, V
a
at N
design
3. Voids in Mineral Aggregate, VMA at N
design
4. Voids Filled with Asphalt, VFA at N
design
5. % G
mm
at N
initial
6. % G
mm
at N
design
7. % G
mm
at N
max
The verification blend will require two G
mm
tests averaged to report a single value.
Based on the above results, the Contractor will establish an AC Correction Factor according to
TR 323, subject to verification by the DLE. The DLE may require that additional mix for JMF
correction factors be submitted as part of the JMF submittal.
If required by specifications perform Loaded Wheel Tests (LWT), Semicircular Bend Test (SCB),
and Tensile Strength Ratio (TSR or Lottman).
Additional information regarding testing, definitions and mix details can be found at the end of this
section.
Stone Matrix Asphalt (SMA) Design Criteria
SMA is hot-mix asphalt consisting of two parts: a coarse aggregate skeleton and binder rich
mastic. SMA is a gap-graded stone-on-stone coarse graded asphalt hot mix. SMA shall have a
minimum 6.0% PG 76-22m or PG 76-22rm AC in design and production. VMA shall be a minimum
of 16.0% in design and production. Mineral fillers and/or fibers may be used to help minimize
draindown. Draindown shall not exceed 0.3% in design or production. Design criteria shall meet
specifications in Table 502-6 of the Standard Specifications. RAP is not allowed in SMA. SMA
will not have a maximum VFA limit.
SMA shall be designed according to the Superpave method utilizing these design steps:
1. Select proper aggregate materials in accordance to section 1003.06 of the Standard
Specifications
2. Determine an aggregate gradation yielding stone-on-stone contact meeting VCA
requirements as outlined below
3. Flat and Elongated percentages shall conform to footnotes 2 and 3 in Table 1003-2 of the
Standard Specifications
4. Ensure the chosen gradation meets or exceeds minimum VMA requirements
SECTION 502 – ASPHALT (Design)
50
5. Choose an asphalt content that provides the desired air void level
6. Evaluate moisture susceptibility and asphalt cement draindown
VCA (Voids in the Coarse Aggregate) determination
(AASHTO R46), Designing Stone Matrix Asphalt
(AASHTO T 19), Bulk Density (“Unit Weight”)
Calculate the dry rodded VCA
DRC
on the plus #4 aggregate portion of a ½” SMA mix to determine
stone on stone contact of the SMA mixture. Stone on stone contact is defined as the point which
the VCA
mix
of the compacted mixture is less than VCA
DRC
of the coarse aggregate in the dry-
rodded test.
The dry-rodded VCA of the coarse-aggregate is determined by compacting with the dry-rodded
technique in accordance with AASHTO T 19M/T 19. When the dry-rodded density of the stone
fraction has been determined, the VCA
DRC
can be calculated using:
VCA
DRC
=
G Y Y
G Y
CA w s
CA w
x 100
Where:
G
CA
= the bulk specific gravity of the coarse aggregate (T85)
Y
s
= the unit weight of the coarse aggregate (+4) fraction in the dry-rodded condition
[kg/m
3
(lb/ft
3
)] (T 19m/T19)
Y
s
= (G T)/V, where: G = mass of aggregate and measure vessel [kg/m
3
(lb/ft
3
)], T =
mass of the measure vessel [kg/m
3
(lb/ft
3
)], V = volume of the measure vessel
[kg/m
3
(lb/ft
3
)]
Y
w
= the unit weight of water [1000 kg/m
3
(62.4 lb/ft
3
)]
VCA
mix
= 100 (G
mb
/G
CA
)P
CA
Where:
G
mb
= bulk specific gravity of the compacted mixture
G
CA
= bulk specific gravity of the coarse aggregate. This is the composite bulk gravity of
the +4 aggregates of the mixture.
P
CA
= percent of coarse aggregate in the total mixture
SMA JMFs shall be submitted a minimum 10 days prior to anticipated production along with a
laboratory specimen at optimum design cut in half for stone-on-stone contact evaluation by the
DLE.
Any previously mentioned requirements for asphalt mixtures other than SMA that are not
redefined in this section must be met.
Submittal Process and Documentation (JMF Submittal Form)
Once the optimum asphalt cement content has been determined, for the proposed aggregate
blend, the consensus properties, dust to asphalt ratio, LWT results (or optionally TSR for Minor
SECTION 502 – ASPHALT (Design)
51
Mix) and SCB analysis have been completed, the certified Contractor Technician shall submit the
proposed JMF to the DLE through LaPave.
The JMF shall indicate the optimum mixing temperature and range as suggested by the asphalt
cement Supplier. The following information is also submitted to the DLE in LaPave.
1. A proposed blend summary with individual source and composite gradations, volumetric
analysis at optimum asphalt cement content, including two N
design
and one N
max
briquette.
2. Bulk specific gravity, G
sb
, of each aggregate and combined bulk specific gravity for the
mineral aggregate blend. Friction ratings if applicable. Calculated bulk specific gravity
(G
sb
) of RAP aggregate and %AC of RAP.
3. A graphical representation of:
Asphalt Concrete Gradation Power Curve form, showing proposed composite
gradation plotted to the 0.45 power curve
Design points along with the verification point for:
o Voids
o VMA
o VFA
4. A quantitative summary of three (minimum) trial blends at optimum and ± 0.5% asphalt
cement along with volumetric calculations. A minimum of two N
design
gyratory specimens
for each blend point.
5. A verification blend at Optimum Asphalt Cement Content Summary of Test Properties
showing VMA, V
a
, VFA, versus asphalt cement content.
6. Coarse aggregate angularity (CAA) test results
7. Fine aggregate angularity (FAA) test results
8. Flat and Elongated Count (FE) test results
9. Sand equivalency (SE) test results
10. LWT Testing Data.
11. SCB Testing Data.
12. Water Susceptibility (Lottman Test) results (Minor Mixes).
13. Draindown test for SMA mixes.
Verification point of the proposed JMF shall include:
1. Gyratory compactor test results for at least two samples (laboratory or plant produced)
prepared at optimum asphalt cement content for the proposed trial blend compacted to
N
design
and one sample compacted to N
max
.
2. Two loose mix samples tested for G
mm
at optimum asphalt cement and averaged for a
single value.
3. When required by the DLE, provide loose mix for correction factor verification as follows:
a. the contractor shall submit sufficient lab design loose mix, for a minimum of two
burns, to the district lab with documentation of the gradation, AC content and
correction factor the contractor determined for the contractor’s ignition furnace(s).
The district lab will burn the contractor-supplied mix in their furnace to establish a
correction factor for DOTD’s furnace. The correction factor will be the average of
the two burns. Gradation will be compared to the contractor submitted results to
evaluate aggregate breakage. If the difference of the two burns is greater than
0.15 (AASHTO T 308), perform 2 more burns.
b. If it is necessary to complete 4 burns because of a difference > than 0.15, the high
and low values will not be used. The average of the 2 middle values will be
averaged and used for the specific ignition furnace used for the burns.
SECTION 502 – ASPHALT (Design)
52
c. It is normal for furnaces to not match correction factors. They should be close, so
if there is greater than 0.4, it should be investigated and resolved as per direction
from the DLE. The purpose of the contractor submitted mix is to establish
correction factors for the district lab’s ignition furnace.
The JMF proposal shall be submitted to the DLE through LaPave software for approval no less
than 7 days before anticipated production is to begin.
Approval of JMF Proposal
Prior to approval of a submitted JMF, the DLE will review the following:
1. Header information
2. Aggregate properties
a. Listed on AML
b. Gradation
c. Specific gravities
d. Consensus properties
e. Friction rating for wearing courses
3. Asphalt cement
4. Anti-Strip
5. Additives (if used)
6. Asphalt mixture general criteria (Table 502-6 or Table 502-6b for low ADT option)
7. LWT or TSR (for Minor Mixes)
8. Draindown for SMA mixtures
9. All submittal documents
Upon approval, LaPave will issue the JMF a Sequence Number. The sequence number must be
legible on any printed copies of the JMF.
The DLE will electronically approve the JMF and notify the Contractor of approval. The DLE or
their representative must approve the JMF proposal before any mixture is produced for the
Department.
The JMF may be approved pending testing of the JMF correction factor.
It is the responsibility of the Contractor to verify with the Project Engineer that the approved JMF
proposal meets project specifications. The contractor shall coordinate the anticipated validation
schedule prior to production for a particular project with the Project Engineer. The Contractor
shall also coordinate with the DLE and ADI for DOTD staffing of validation testing in accordance
with the “Contractor Notification” in the Policy Section of this manual.
SECTION 502 – ASPHALT (Validation)
53
Validation of JMF Proposal
After DLE approval of the JMF and after the Project Engineer verifies that the mix type is
appropriate for its use according to project specifications, the plant may begin the validation
process by producing mix using the JMF, as approved.
The first production lot up to a maximum of 2000 tons of mix shall be used to validate a JMF. The
Contractor and the Department ADI using the stratified random sampling approach (See
Appendix) shall jointly take and test five samples, one per validation sublot. Validation of a
mainline JMF requires a minimum of 1000 tons. A multiple day validation is acceptable across
multiple projects. Validation shall consist of 5 tested sublots totaling between 1000 and 2000 tons
at the discretion of the DLE.
The Contractor, with the approval of the Department, may exclude the first sublot test set from
validation calculations provided a 6
th
test is taken within the validation lot. The dropped 1
st
sublot
test data is retained, but the data for the 6
th
test will be used to calculate validation PWL and
averages for setting JMF targets. The dropped 1
st
test will not be used for validation calculations.
It must be noted that roadway core PWL calculations are not related to JMF validation.
Acceptable roadway performance, as per specifications and to the satisfaction of the Project
Engineer, is a requirement for continued use of a JMF.
Pay on the validation roadway lot will be in accordance with acceptance pay parameters, based
on core density. The assigned roadway lot numbers must correspond to the assigned plant lot
numbers. The pay on the asphalt from the validation lot will be based on one roadway core per
sublot for each sublot. Calculations for pay for validation lots will be the same as regular roadway
lots, always based on 5 cores.
Roadway core density will be calculated on the corresponding plant sublot G
mm
. One acceptance
roadway core per sublot will be cut for acceptance and delivered to the District Lab. Quality
control cores are to be cut within 12 inches of the acceptance cores in the direction of traffic for
the contractor. After all cores are tested for density and the time has lapsed for the contractor to
question density results, the district lab will randomly choose one core for G
mm
verification against
the corresponding plant sublot G
mm
with a ±0.024 tolerance. If the G
mm
does not verify, the DLE
will notify the contractor. See the “Core Handling Flow Chart” in District Laboratory Acceptance
for testing protocol.
Approximately 20 grams of No. 4 and +No. 8 asphalt coated aggregate from loose mix obtained
during validation will be sent by the DLE to the Materials Lab (Section 22) for GPC analysis.
One quart can of Asphalt Cement will be submitted along with asphalt coated aggregate
for GPC analysis (finger printing) from the validation.
When an asphalt cement source is changed, one quart can and loose mix as referenced
above shall be submitted to the Materials Lab (Section 22) for GPC analysis.
SECTION 502 – ASPHALT (Validation)
54
Validation Lot Example
















































Density = D1A, D1QC, etc.
For each core, the corresponding plant sublot Gmm will be used for roadway density of each
validation sublot
However, if plant sample 1 test results are inconsistent with the other sublots, the contractor may
collect one additional plant sample at the end of validation and use in place of the first for
determining JMF targets and JMF validation acceptability.
The JMF proposal validation will be completed on the first production lot for that JMF in
accordance with specifications. The validation is intended to ensure the mixture produced in the
plant meets tolerances set forth in the JMF proposal and to establish the targets for the approved
JMF. The contractor is to ensure the minimum lift thickness is maintained based on the nominal
maximum size aggregate per Table 502-6 or 502-6b.
The performance of the mixture on the roadway will be evaluated to ensure the JMF is not
contributing to laydown deficiencies, such as segregation, tenderness, workability, compactability,
or surface texture problems. When the Roadway Inspector observes roadway deficiencies during
or after validation, they will inform the Plant Inspector, the Project Engineer, and the DLE. The
Project Engineer in charge of the project or the DLE may discontinue the use of a JMF because
of roadway deficiencies attributed to the JMF.
LWT (Rut Testing) Validation of JMF Proposal
The ADI shall prepare 4 gyratory specimens 60 mm in height at 7 ±0.5% air voids in accordance
with AASHTO T 312 (larger specimens may be gyrated and cut to height). The estimated weight
required for the specimen will depend upon the G
mm
of the mixture. The specimens shall be
delivered to the District Lab for LWT testing in accordance with AASHTO T 324. When the LWT
rut depth results exceed requirements in Table 502-6 or 502-6b, discontinue production and
reevaluate the JMF.
Plant
Sample 1
Plant
Sample 2
Plant
Sample 3
Plant
Sample 4
Plant
Sample 5
Plant
Sample 6
Cores
1A & 1QC
Cores
2A & 2QC
Cores
3A & 3QC
Cores
4A & 4QC
Cores
5A & 5QC
SECTION 502 – ASPHALT (Validation)
55
Failure to Validate Procedure
If a mixture design fails to validate, a second validation attempt is allowed.
If the first and second validation attempt fails any quality characteristic or roadway pay is less
than 100% on both attempts, then the contractor must redesign, submit the JMF proposal for
approval, and validate off site at no direct pay. While this off site validation remains incomplete
and unapproved, the Producer will not be allowed to submit any new JMF’s for approval for
mixtures of this type on any DOTD project. The off-site validation plan must be pre-approved
by the DLE. The validation data is entered into LaPave for DLE review. The DLE will determine
if an additional validation is required on the state project. If the Contractor must validate off-site,
they must coordinate with the DLE who may require that the ADI be present for the off-site
validation attempt in order to avoid another validation on a state project.
Pending off site validation, the Producer may use a previously approved JMF on DOTD projects.
If the Producer is not able to adjust the mix within allowable bin tolerances (±4% for validation),
disapprove the JMF.
If the JMF does not validate, the DLE will disapprove the JMF in LaPave.
Repeated validation failures indicate a possible problem with equipment, processes and/or mix
design.
Final Approval of JMF
Upon validation of the JMF, validation averages become JMF production target values.
For mixes that do not require validation, such as minor mixes, the average of the first five sublot
test results from a specific JMF become production target values. The ADI or DLE will duplicate
the data entry into the validation portion of LaPave.
The DLE, upon review of the validated JMF and supporting PWL calculations, will approve the
validated JMF for production. Once a completed mixture design has been validated and
approved, the same JMF may be assigned for use, with DLE approval, for any project having the
same specification requirements.
It is the responsibility of the Contractor to ensure the Project Engineer has received notification of
the approved JMF prior to production. The Project Engineer is responsible for sending a copy to
the Roadway Inspector.
LaPave will notify the Contractor, Producer, Department plant personnel, and the Project
Engineer who is receiving the mixture of final approval of the JMF.
In summary:
1. Contractor submits a proposed JMF to DLE
2. DLE approves the JMF for validation
3. Validation is performed, data analyzed
4. DLE (or designee) reviews and approves
SECTION 502 – ASPHALT (Validation)
56
5. Validated proposal becomes a new approved JMF
All JMF’s shall be re-validated a minimum of every 2 years. Re-validation may consist of
reviewing ongoing production plant data and plant verification data or a full validation, if required
by the DLE. If production data does not maintain specification requirements whether required for
pay or not, the DLE may require re-validation or terminate the JMF.
Figure 2-5 illustrates asphalt mix design and submittal steps.
SECTION 502 – ASPHALT (Validation)
57
Asphalt Concrete Mix Design Steps
Material Procurement
Coarse Aggregate
Fine Aggregate
RAP
Asphalt Cement
Approved Stockpile?
Approved Materials List?
Friction Rating OK?
G
sb
Determined?
CAA Determined?
Flat & Elongated
Determined?
Gradation Determined?
Gradation Determined?
Percent AC Determined?
Approved Materials List?
G
sb
Determined?
Gradation Determined?
FAA Determined?
SE Determined?
Approved Materials List?
Correct Grade?
Mixture Type Determined From Project Plans?
Blending Aggregates
Nominal Maximum Aggregate Size Determined?
Aggregate Mathematically Blended to Meet Table 502-4?
Composite Gradation Plotted on the 0.45 Power Curve?
Blended Gradation Within Control Points?
Blended Gradation Within FAA Specification?
Blended Gradation Within CAA Specification?
Blended Gradation Within SE Specification?
One Trial Blend Prepared At Optimum AC%?
One Trial Blend Prepared 0.5% Above Optimum AC%?
One Trial Blend Prepared 0.5% Below Optimum AC%?
Preparing Trial Blends Using Varying
Asphalt Contents
Two Specimens Prepared at Each Trial Blend?
Loose Mix Specimens Prepared at Each Trial Blend?
G
sb
Determined?
SECTION 502 – ASPHALT (Validation)
58
Figure 2-5: Asphalt Mix Design and Submittal Steps
Testing and Evaluating Trial Blends Using
Varying Asphalt Contents
G
mm
Determined?
G
mb
@ N
design
Determined for Each Blend?
V
a
@ N
design
Determined for Each Blend?
VMA @ Design Blend Within Specifications?
VFA @ Design Blend Within Specifications?
N
initial
@ Design Blend Within Specifications?
N
design
@ Design Blend Within Specifications?
N
max
@ Design Blend Withing Specifications?
Selection of Optimum Asphalt Cement Content
Blend Prepared at Optimum Asphalt Content?
V
a
"vs" Asphalt Content Plotted
on Graph?
VMA "vs" Asphalt Content Plotted
on Graph?
VFA "vs" Asphalt Content Plotted
on Graph?
Dust / Effective Asphalt Ratio Within Specifications?
Semi-Circular Bend Test (SCB) Within Specification?
Loaded Wheel Test (LWT) Within Specification?
VMA @ N
design
Determined for Each Blend?
VFA @ N
design
Determined for Each Blend?
Percent G
mm
@ N
initial
Determined for Each Blend?
Percent G
mm
@ N
design
Determined for Each Blend?
Percent G
mm
@ N
max
Determined for Verification Blend?
Asphalt Concrete Mix Design Steps
Job Mix Formula, JMF Submittal
Asphaltic Concrete Job Mix Release Form
Proposed Blend Summary
G
sb
of Each Aggregate and Combined G
sb
0.45 Power Curve With Control Points
Summary of Three Trial Blends
Optimum Asphalt Cement Content
Summary of Test Properties (Verification)
Coarse Aggregate Angularity, CAA Test
Results
Fine Aggregate Angularity, FAA Test
Results
Flat and Elongated Count, FE Test Results
Sand Equivilancy, SE Test Results
Gyratory Compactor Test Results For Two
Samples Prepared At Optimum AC
Loaded Wheet Test (LWT) or when allowed,
Tensile Strength Ratio, TSR Test Results
Signed Copies of JMF Forms
Optimum Blend Yeilding Design V
a
Determined?
SMA
requirements:
Select proper aggregate
gradation
Aggregate gradation yielding
stone on stone contact
Ensure gradation meets
minimum VMA Requirements
Asphalt
content provides
desired void content
The mix meets moisture
susceptibility and asphalt
SECTION 502 – ASPHALT (Lots)
59
Definition of a Lot
1 Lot is 5,000 tons consisting of 5 1,000 ton sublots.
For Quality Control and contractor plant testing, obtain a minimum of 1 mixture sample from each
1000 tons of plant-produced mixture using a stratified random sampling approach (see appendix).
A representative sample shall be of sufficient size for all Quality Control testing.
A lot is a segment of production of asphalt concrete mixture from the same JMF produced for the
Department at an individual plant for a specific project. Although the plant lot and sublots testing
data is used for quality assurance purposes, there are no pay adjustments associated with this
data. Plant lots will be specific to projects. Lot designation shall be reported on each haul ticket
delivered to each state project.
It may take multiple days to complete a lot, in which case the Contractor shall perform and report
multiple Quality Control tests on an individual lot, at a minimum of 1 set of tests per day when
production is 100 tons per day per “Mainline” JMF and/or 250 per day per “Minor” JMF.
Contractor QC testing shall be performed and reported into LaPave.
Minor adjustments will be made in the 5000-ton lot size to accommodate hauling unit capacity.
When total lot quantity of 5000 tons is reached in the partial load of a truck, the full legal load of
the truck shall be included in the lot. For example, if 4988 tons of asphalt mixture are produced
and sent to a project and the next truck hauls 24 tons, the actual lot size will be 5012 tons (4988
+ 24).
For 502 mixtures, the last lot of each mix type per project (Base, Binder, Wearing, Incidental) may
be extended 1 sublot up to a maximum total of 6000 tons. The last lot of each mix type that is
extended shall have six sublots.
The Contractor shall ensure “Haul Ticket’ information on each ticket includes:
Date
Project number
DOTD JMF sequence number
Mix Type
Lot No.
Ticket number
Quantity of mix in tons
Accumulated tons shipped
DOTD truck certification number
Roadway Lot Tracking
The corresponding roadway lot shall be tracked at 5000 tons from the plant. Roadway lots shall
be either mainline asphalt mix, minor asphalt mix use or a combination use of both from the
same JMF. Roadway lot numbers will be the same as the plant lot number. Tonnage and lot
placement is documented on each project using station to station placement locations. Daily
Work Reports (DWRs), field books and roadway reports are ways to document mix placement.
SECTION 502 – ASPHALT (Lots)
60
Roadway lot tonnage may be less than tonnage for a plant lot. Some reasons:
Rejected mix partial or whole loads
Too much mix sent to the roadway. Then sent back to the plant.
Mix has to be removed and replaced during laydown operations
The wearing course is the final lift placed. The binder course is the lift placed prior to the final lift.
When a 501 mixture is placed over a 502 mixture, it is a “Finish Course.”
Mainline mixtures include wearing, binder, and base courses for travel lanes, ramps greater than
300 ft., turnouts greater than 300 ft. interstate acceleration/deceleration lanes, center turn lanes,
and the two center lanes for airports.
Minor mixes include mixture used for bike paths, crossovers, curbs, detour roads, driveways,
guardrail widening, islands, joint repair, leveling, medians, parking lots, shoulders, turnouts less
than 300 ft., ramps less than or equal to 300 ft., patching, widening, miscellaneous handwork,
and any other mixture that is not mainline.
Mainline
Travel Lane Wearing, Binder, Base
Ramps >300’ long
Turnouts > 300’ long
Interstate Acceleration/Deceleration Lanes
Turn Lanes
Minor Mix with Density
Minor Mix without Density
Shoulders
Curbs
Patching
Driveways
Widening > 2.5’ wide
Widening ≤ 2.5’ wide
Leveling > 1.5” thick and uniform
Leveling ≤ 1.5” thick, and used in spots
Turnouts ≤ 300’ long
Turnouts < 300’ long
Ramps ≤ 300’
Detour Roads
Crossovers
Guardrail Widening
Bike Path
Islands
Parking Lots
Joint Repair
Tapers
Everything Else
When a roadway lot is a combination of mix uses, separate roadway reports, with station number
begin and end, shall be used to record the tonnage for each mix use. For example, roadway
paving and shoulder paving is a common combination mix use lot. Shoulders paved with mainline
mixture, would be considered a minor mix use. Theoretical quantity for the shoulder would be
part of the lot but tracked as minor mix. A separate roadway report would be made for the mainline
mix use as well as for the shoulder mix use.
Example:
If 200 tons is placed on a 12’ wide roadway and a 4’ wide shoulder (total paving is 16’ wide),
paved with the mainline, divide the tonnage as follows:
(12/16)*100 = 75% travel lane and (4/16)*100 =25% shoulder = 100% paved width
SECTION 502 – ASPHALT (Lots)
61
200 tons x 0.75 = 150 tons mainline mix
200 tons x 0.25 = 50 tons shoulder minor mix
Roadway Lot Sampling and Testing
Minor without density requirements compacted to the satisfaction of the Engineer
The P.E. may require coring 4 ft. shoulders when the contractor is not compacting to their
satisfaction
The sublot is divided into two equal sections with an acceptance and QC core from each section
Using random numbers (see appendix) for location, an acceptance core is taken from each
section.
If a sublot has both mainline and minor uses, at least one acceptance core is required to represent
the minor mix type. If the lot has any mixture used for mainline, a minimum of three cores is
required to represent the mainline portion. Take additional acceptance cores randomly from the
respective portions as needed to meet these requirements.
The Contractor will cut and trim all cores in the presence of the DOTD Inspector. The DOTD
Inspector will take custody of the cores for delivery to the district lab. Contractors may request to
transport roadway acceptance cores, via the approved method, to the district lab. The request
shall be in writing and approved by the DLE.
The Contractor will take Quality Control cores within 12 inches of the acceptance cores in the
direction of travel. If additional acceptance cores are taken, take additional quality control cores
approximately 12 inches in the direction of travel from the any additional acceptance core
collected. The contractor will take custody of these cores for testing at the asphalt plant.
Both the Contractor and Department shall report core results in LaPave on the same day tested.
All cores shall be properly identified by the corresponding roadway lot, core identification number,
and project number. The Certified Roadway Inspector shall list the generated random numbers
on the Roadway Report.
See the Roadway Acceptance section of this manual for core handling procedures.
Roadway Lot Pay Determination Based on Core Densities
Based on minor mix core densities, the portion of the lot that is minor mix is subject to pay
adjustments, based on averages, in accordance with 502.15.2, and Tables 502-5 and 502-7.
Based on mainline mix core densities, the portion of the lot that is mainline mix is subject to pay
adjustments, based on PWL or average, in accordance to 502.15.2 and tables 502-5, 502-7,
and/or 502-10.
For projects, or separate locations within a project, requiring less than 250 tons per mix type, the
job mix formula, materials, and plant and paving operations shall be satisfactory to the Engineer.
The Engineer may modify sampling and testing requirements and may waive the payment
adjustment for deviations.
SECTION 502 – ASPHALT (Production)
62
Minor mix without density requirements will be accepted based on contractor plant
testing data.
Quality Control
Plant Quality Control
Whenever asphalt mixtures are being produced for a DOTD project, the Contractor shall, at all
times during operations, have a Certified Asphalt Concrete Plant Technician (QC Tech) at the
plant with the ability and authority to conduct any test or analysis necessary to put the plant into
operation and produce a mixture meeting specifications. A Level I qualified technician or above
QC Tech may test mix for conformance with specifications. A Level III QC Tech shall be required
to design asphalt concrete mixtures and submit JMFs for approval to DOTD.
During plant operations, the QC Tech for the contractor shall not serve in another capacity (i.e.
plant operator, loader operator, laborer.)
QC Techs shall provide proof of Asphalt Concrete Plant Technician certification upon request by
the Department.
The primary responsibility of the QC Tech is to design asphalt mixtures and control production to
ensure it consistently meets Departmental specifications.
The Contractor must ensure all tasks necessary to begin plant operations are completed. This
includes, but is not limited to, checking asphalt cement working tanks, material stockpiles and
moisture content, aggregate bins, cold feed settings, meters, and scales. The QC Tech is
responsible for recommending appropriate actions and ensuring adjustments are made during
operations to ensure uniformity and conformance to specifications.
The Contractor shall oversee and monitor the complete production, transport, placement, and
compaction phases to ensure compliance with DOTD specifications and to promote consistency.
When the plant is in operation, the QC Tech shall monitor stockpiles to ensure proper construction
and moisture contents entered into the plant controls are consistent with actual values for each
material bin.
Continuously monitor plant operations to ensure:
Proper bag house operation (startup and shutdown loads do not impact the return of
fines from the dust collection system, causing inconsistent amounts of passing No.
200 material.)
Sufficient asphalt mix wasted at startup and shutdown to ensure adequate, sufficient,
and consistent asphalt cement rates and conformance to JMF specifications.
Proper loading of trucks to minimize material segregation.
Plant Quality Control Testing
SECTION 502 – ASPHALT (Production)
63
The Contractor shall conduct Quality Control tests to ensure production analysis is within
specification ranges. Sampling and testing shall be in accordance with the Materials Sampling
Manual.
The Contractor must demonstrate plant processes are under control for voids and G
mm
. The
Contractor will report testing data daily. The following may indicate that plant process or materials
are out of control:
a. One point is more than three standard deviations from the mean.
b. Nine (or more) points in a row are on the same side of the mean.
Further investigation may be required if the DLE determines for any reason that the plant process,
materials, equipment, etc. may be causing problems in the mix production.
The Contractor shall continuously enter test results of plant data as testing is completed. The
following records shall be entered or calculated in LaPave:
1. In LaPave, report results of each individual test and moving average for five samples for
the following:
a. G
mm
, air voids
b. VFA
c. VMA
d. % G
mm
at N
initial
,
e. Required gradation parameters
f. Asphalt content
2. In addition, LaPave will compute PWL (see Appendix for example calculation) for G
mm
and
air voids.
3. Corrective action when the PWL or average of the five fall outside the specifications limits.
4. Notes of proper adjustments prior to continuing production.
From 502.06, Quality Control and Plant Acceptance, the rolling five test must meet 71 PWL. If
the latest rolling five test results are less than 71 PWL, the Contractor will take corrective action
or cease production.
Through quality control procedures, the Contractor shall make efforts to maintain mixture-testing
tolerances within the ranges specified on the following table:
Table 7
Tolerances for Rolling Five Average
Parameters
Tolerances
1
G
mm
± 0.015 of the validated G
mm
G
mb
± 0.024
%Voids
± 1.0
%VMA
± 0.5
%AC
± 0.3
VFA
± 1.0
Gradation
No. 4
± 4
No. 8
± 3
SECTION 502 – ASPHALT (Production)
64
No. 200
± 0.7
1
Based on the latest QC average, (“rolling 5”)
If quality control data shows mixture production is not uniform, the Contractor shall correct
operations to produce a mixture conforming to specifications or discontinue operations for DOTD.
Production adjustments resulting in subsequent production tolerance adjustments will require a
new JMF should they exceed:
1. 4% of cold feed proportions from original submittal percentages
2. 0.3% virgin asphalt content
3. Greater than or less than 0.015 of the validated G
mm
as noted in Table 7.
The Contractor shall maintain a daily record of cold feed percentages and asphalt content
settings.
The Contractor shall document all corrections to control the mixture and prevent any aspect of
the mixture from moving outside specified limits or from varying erratically within limits. This
documentation shall include the action taken, date and time, and technician making corrections.
Minimum Contractor Quality Control Testing
*Loose Mix / Sublot
1. Theoretical Maximum Specific Gravity, G
mm
2. % Asphalt Content
3. Gradation
4. % Crushed
5. Temperature of Mix Minimum of 1 per sublot, per day, per JMF written on the haul
ticket
6. Mix moisture
*Compacted Specimen / Sublot
1. LWT (Every 20,000 Tons)
2. % G
mm
@ N
initial
3. %G
mm
@ N
design
4. % Air Voids, V
a
5. % VMA
SECTION 502 – ASPHALT (Production)
65
6. % VFA
7. %G
mm
@ N
max
1 per 5 Sublots for information only
Age all loose mix prior to testing for one hour (warm mix age: 2 hours) in a shallow pan in
accordance with AASHTO R 30. This includes G
mm,
LWT and mixture for gyratory briquettes.
*The Contractor will test for Quality Control when 100 tons or more are shipped per mainline per
JMF per day and/or 250 tons of minor mix per JMF per day. Test results will be entered into
LaPave with comments entered in the remarks section.
For WMA mixtures and JMFs with ≥ 2% composite water absorption, age samples for 2 hours.
LWT Testing
In addition to validation requirements, perform LWT testing in accordance with DOTD S 201 -
Asphaltic Materials for every 20,000 tons of plant-produced mixture.
4 60mm gyratory specimens compacted to 7.0 ± 0.5% air voids are tested.
Gradation
Proper sampling is crucial for accurate results that represent actual plant production.
The Contractor should regularly check to ensure the aggregate proportioning system, as well as
the RAP proportioning system, are in calibration. This may be a two-step process. Check
weighbridges to ensure they are in calibration. This is determined by running a known mass of
material, including moisture, over it and correcting the weighbridge factor to bring it in calibration
over the full span of expected flow rates. Each cold feed bin should be calibrated as needed to
ensure the proper mass of material/per unit time is being proportioned from the individual bin.
Should the extracted gradation begin to vary erratically, the aggregate and RAP proportion
systems should be immediately checked along with individual stockpile gradations and moisture
contents.
Additives
The Contractor shall check the rate of anti-strip at the beginning of each operational period, and
when necessary, to ensure the mixture is receiving the percentage of anti-strip required by the
JMF.
When other additives are used, the Contractor shall also check the rate at the beginning of each
operational period, and when necessary, to ensure the mixture is receiving the percent of additive
required by the JMF.
Temperature
The temperature of the asphalt cement and asphalt mixture is very critical. It is also critical
that the temperature of these two products be as specified and be consistent.
SECTION 502 – ASPHALT (Production)
66
Specifications require a thermometer to indicate mixture discharge temperature (typically at the
discharge of the drum mixer). Mixture temperature consistency is essential in obtaining consistent
roadway compaction. The QC Tech may check this thermocouple temperature against an
infrared gun-type thermometer device or a standardized dial thermometer.
The JMF stipulates an optimum mixing temperature range of ± 25°F of the optimum mixing
temperature for the asphalt cement used. The discharge temperature shall be within this range.
Mixing temperature must never exceed 350°F at the point of discharge, regardless of the
supplier’s recommendations. Section 502.09 of the Standard Specifications states: No
mixtures shall be delivered to the paver cooler than 25°F below the lower limit of the compaction
temperature as allowed by the JMF. The temperature of the mix going through the paver
shall not be cooler than 245°F.
Moisture
Stripping of asphalt mixtures is less likely to occur in the absence of moisture or moisture
vapor. All hot-mix asphalt materials shall be produced in a manner that minimizes internal
moisture because internal aggregate moisture can weaken the molecular bond between the
asphalt cement and the mineral aggregate.
The average annual rainfall and humidity present in Louisiana, makes it difficult to remove all free
and absorbed moisture from aggregate in the production process. In a typical plant, when fuel is
burned, a quantity of heat is produced. Heat transferred to the aggregate evaporates moisture
and heats the aggregate. As moisture evaporates, each pound of water expands to 33 ft
3
of
steam. This enormous volume of steam must be removed by the plant’s exhaust system. When
aggregate moisture values increase, the plant’s production rate and burner settings must be
adjusted to maintain and achieve consistent mixture temperatures and remove sufficient moisture.
Excessively worn or missing flights will greatly affect the plant’s ability to heat and dry aggregates.
The drum mixer shall be routinely inspected for excessive flight wear.
The presence of moisture also influences the process of accurately measuring mix volumetrics.
Excessive moisture in hot-mix asphalt may lead to an abrupt collapse in VMA.
The QC Tech shall monitor and record the moisture in LaPave for Quality Control purposes. The
stockpile moisture records shall be maintained in LaPave and plant laboratory.
Calculate moisture content (M.C.) for each aggregate by the following equation:
100
WeightDry
)WeightDryWeightWet(
.%C.M
To determine the dry mass/weight, knowing moisture content, the following equation may be
used:
.%C.M100
100WeightWetTotal
WeightDryTotal
SECTION 502 – ASPHALT (Production)
67
Report percent moisture (maximum 0.3% allowed by specification) in loose mix as part of QC
testing of plant-produced mixture. Test in accordance with DOTD TR 319. Mix moisture shall be
tested and entered into LaPave a minimum of once daily. Both the mix moisture and the AC
correction factor shall be used to determine AC content.
Plant Inspection
When QC/QA inspection or tests indicate the Contractor's QC program is ineffective, the ADI or
DLE will require modifications to the program. DOTD has the right to require changes in
personnel, equipment, construction methods, testing methods, or frequency. The Contractor will
not proceed with construction operations without an effective QC program, as determined by the
DLE, that complies with specifications.
A key element of inspection is the review of Contractor’s QC results and program. Evaluations of
the QC effort to ensure that out-of-specification mix does not occur may include, but are not limited
to, the following:
1. Observation of the Contractor's sampling and testing procedures for conformance to
Department procedures and proper testing techniques
2. Evaluation of the Contractor's testing equipment for proper working condition and
conformance to requirements of appropriate test procedure
3. Observation of construction procedures for uniformity of effort and results
Department Certified ADI Responsibilities for Plant Verification
The Department’s ADI is a Department official representative. The Department’s ADI will
randomly visit each plant at a minimum of once per month to verify plant operations and audit
quality of production without advance notification to the contractor.
The ADI will either take a random independent sample or split sample with the Contractor during
random plant visits for each JMF produced for state projects. The ADI will perform all testing,
independent of the contractor technician. The ADI will perform the following tests:
1. G
mm
TR 327
2. Gyratory compacted to N
design
T 312, TR 304
3. Mix moisture TR 319 - Completed during plant visit; and
4. Loose mix for %AC and gradation TR 323, TR 309
The sample will be aged for 1 hour for hot mix, 2 hours for warm mix and/or aggregates with
greater than 2% water absorption. After aging, the ADI may test using the Contractor’s laboratory
equipment or district lab equipment to perform required tests to specifications in Table 502-6 or
502-6b. Best practice is for the ADI to initially test a split sample using the contractor’s equipment
and the district lab equipment. Investigate any differences when results do not meet testing
tolerances.
The ADI will indicate in LaPave whether the sample is independent of the Contractor’s or a split
sample with the Contractor. The gyratory briquettes will be tested for bulk specific gravity G
mb
,
V
a
, %G
mm
@ N
des
, VFA, and VMA.
SECTION 502 – ASPHALT (Production)
68
When testing by the ADI and/or district lab does not verify with contractor reported data, the DLE
will investigate for the cause of the difference. The DLE may request assistance from the IA team
when cause cannot be identified. Inability to reconcile will justify the Department’s requirement
to use an independent certified lab to perform the Contractor’s plant testing.
The ADI shall also take a lot verification sample, a minimum of one per quarter per plant, to be
tested at the district lab for G
mm,
AC%, gradation, and voids (gyratory compacted to N
design
to be
made at the district lab) in order to ensure that Contractor and District Laboratory equipment
verify.
Individual sample test results shall meet parameters of Table 502-04.
Table 7
Tolerances between Plant Test and District Lab Verification Test
Parameters
Tolerances
G
mm
±0.015
G
mb
±0.024
%Voids
±1.0
%VMA
±1.0
%AC
1
±0.2%
No. 4
±4%
No. 8
±3%
No. 200
±0.7%
1
Differences between furnaces require a correction factor for the DOTD ignition furnace.
Research has shown variances between furnaces.
When tolerances listed in the table above are not met, the Department’s ADI will revisit the plant
and test split samples. Split samples will be tested by the Department’s ADI and QC Tech using
the same equipment until a cause is found.
Equipment maintenance logs, proficiency sample records, or other record keeping required for
certification will be reviewed quarterly by the ADI.
The Department’s ADI is responsible for ensuring plant equipment and processes are in
accordance with Section 503.
Asphalt Cement Content and Properties
Determine asphalt cement content by ignition furnace testing (DOTD TR 323) with the pre-
determined JMF correction factor and test results of moisture content (DOTD TR 319). When
the plant control delivery rate of asphalt cement plus the asphalt credit from RAP (if used) differs
by more than ±0.2% from the ignition oven (with correction factor) for two out of five on the rolling
5 average, take corrective action. Corrective action can be re-establishing the correction factor
or recalibrating the asphalt cement metering system or other systems of the plant. Document and
the cause and corrective action taken and enter in LaPave.
Excess moisture in the mix may falsely appear as asphalt cement during ignition furnace testing;
it may artificially decrease the G
mm
. Higher or lower asphalt content can reduce or raise the G
mm
.
The Contractor shall ensure asphalt cement strainers and screens are clear and operational.
SECTION 502 – ASPHALT (Production)
69
Asphalt cement shall be sampled and tested in accordance with Sections 502 of the Materials
Sampling Manual.
The Approved Materials List Asphalt Cement Supplier shall:
Sample and test the product
Provide a Certificate of Analysis to the Materials Laboratory (electronic media is
acceptable)
Provide a Certificate of Delivery (CD) with every transport representing the material
shipped to the asphalt production facility
Transports will arrive at the plant with a CD. The Contractor’s certified technician shall collect,
scan, and email (at a frequency approved by the DLE) the CD’s to the DOTD ADI or DLE.
CDs constitute acceptance for asphalt cement for the project. The contractor shall provide
sufficient CDs of the proper grade for mix produced. A representative of DOTD will sample
working tanks a minimum of once per month during random visits and transports as requested by
the Materials Laboratory. The samples are to be delivered to the district lab for proper handling.
CDs for asphalt cement shall be clearly identified with the following:
1. DOTD lab number/Site Manager Materials Number
2. Asphalt Cement Grade/Material Code
3. Product Source Code
4. Date Shipped
5. Quantity
6. Plant Code
Sample IDs for asphalt cement shall contain:
1. Asphalt mix plant Producer/Supplier Code
2. Asphalt Cement Grade/Material Code
3. Sample ID Number
4. Date Sampled
5. Quantity
It is the contractors responsibility to ensure asphalt cement added to the asphalt mix meets PG
grade requirements for the asphalt mix being produced.
The Department’s ADI will sample all asphalt cement working tanks for verification, once per
month per plant per grade, and submit for testing. Sampling quantity will be one quart can per
grade.
Specific attention shall be given to monitoring temperature in all asphalt cement working tanks
and ensure all materials added, particularly from transports, are also at the correct elevated
temperatures. Temperature directly correlates with viscosity, which will affect the material’s ability
to adequately coat the aggregate. The temperature of the asphalt cement and asphalt mixture
is very critical. It is also critical that the temperature of these two products be as specified
and be consistent.
The Materials Laboratory will request refinery verification samples through the District Laboratory.
The District Laboratory will coordinate refinery transport delivery with Contractor production to
ensure Materials Laboratory sample requests are met.
SECTION 502 – ASPHALT (Production)
70
District Laboratories may test and report Dynamic Shear and phase angle, and one Rotational
Viscosity per grade per month per refinery. If the sample meets all criteria, production continues.
Should the working tank sample not verify, the district laboratory will promptly notify the the
Contractor, who shall notify the Supplier. Additionally, the DLE must investigate to determine the
cause of failure. The following is general guidance for investigating differences:
Compare working tank results to refinery results, transport results, and previous
working tanks results. Does the material have a history of problems that would have
resulted in similar problems?
Send samples to the Materials Laboratory for complete analysis.
Check maintenance schedules for the working tank to find out what maintenance was
performed. For example: When the coils were last cleaned? When the tank was last
cleaned?
Inspect facilities, checking the history of the Supplier material, etc.
Check the temperature of the working tank.
Check whether a different brand or grade of material has been added to the tank. Was
the tank level sufficiently low before adding new material?
Test rotational viscosity.
If it is determined that material in the working tank does not meet specification requirements, then
plant production shall cease until corrections are made.
Asphalt cement in the plant’s working tank shall meet specifications of the asphalt cement
required on the JMF.
Percent Anti-Strip
An anti-strip additive shall be added to all mixtures at no less than the minimum rate on the
approved JMF.
The Department’s ADI and contractor technician will verify the amount of anti-strip. If the check
performed indicates the amount of anti-strip added is not in accordance with the JMF, the
Contractor must make adjustments so the correct amount of anti-strip additive is added to the
mixture. If the second check indicates, the mixture is still not receiving the correct percentage of
anti-strip, production for DOTD projects shall be terminated until adequate adjustments can be
made to the system or the system can be recalibrated.
The results of the percent anti-strip are entered into LaPave. Readings are to be reported, a
minimum, once per lot by the Contractor.
The basic method of checking the percent anti-strip in the mixture is to monitor the flow of additive
for a continuous time sufficient for an accurate calculation. In order to proceed with calculations
for percent anti-strip, the Certified Technician must know the unit weight of anti-strip additive at
any given temperature. The anti-strip Supplier must make the unit weight information available
or a one-gallon sample weighed at the plant to determine this value.
This example shows the process of determining percent anti-strip added to asphalt mixtures:
SECTION 502 – ASPHALT (Production)
71
1. Temperature Read and record the temperature of the anti-strip additive used in the
mixture from the thermometer on the anti-strip tank.
2. Readings Take an initial reading of the amount of anti-strip additive from the anti-strip
meter and take an initial reading from the asphalt cement totalizing meter. It is required
that the percent AC and the percent anti-strip be checked simultaneously during
continuous production to evaluate the quality of the mixture in terms of both
components.
a. For anti-strip, record the initial reading to the nearest readable increment (0.1
gallon, 0.25 gallon, or 0.034 gallon). Allow the plant to run for a continuous
recorded time sufficient to represent approximately half a lot. Take a final reading
to the nearest readable increment and record.
b. For asphalt cement, record the reading to the nearest gallon. (Some plants will
digitally display the mass of asphalt cement added on the computerized
operational controls.) Allow the plant to run for the same time as used for anti-strip
determination. Take a final reading of AC used and record to the nearest gallon.
Subtract the initial reading from the final reading to obtain gallons AC used.
Subtract the initial reading from the final reading to obtain the actual amount of
anti-strip used during the time.
3. Calculations Calculate the percent anti-strip in terms of the weight of asphalt cement in
pounds based on the suppliers unit weight.
7.28 lb/gal is used for this example. Manufactures and suppliers shall provide the
specific gravity for their product on the CD accompanying the transport.
a. Anti-strip Quantity Calculate pounds of anti-strip:
Unit weight of anti-strip = 7.28 lb/gal (from curve)
Gallons anti-strip used during check = 41.45 gal
7.28 lb/gal x 41.45 gal = 301.8 lb
b. Asphalt Cement Quantity Calculate pounds of asphalt cement:
Gallons AC used during check = 5820 gal
Weight of 1 gallon of water = 8.34 lb/gal
Specific Gravity of AC @ 60°F = 1.03
5820 gal x 8.34 lb/gal x 1.03 = 49,994.964 lb
c. Percent Anti-strip Calculate the percent anti-strip:
%AS=
pounds of anti-strip
pounds of asphalt cement
x 100
SECTION 502 – ASPHALT (Production, Roadway)
72
100x
49,994.964
301.8
AS%
= 0.604
= 0.6 % anti-strip
Report the final percent anti-strip additive to the nearest 0.1%.
4. Alternate Method An alternate method is to take a printout of anti-strip and
asphalt cement quantities at a specific start and stop point in time from the control
room. Divide the total anti-strip quantity for the recorded time by the total asphalt
cement for the same time. Results shall be within ±0.1 of the JMF. If not,
production shall be discontinued until the proper rate can be added.
If lime or other additives are proportioned in the asphalt mixture at the plant (and shown on the
JMF), then this rate shall be verified, via the plants meters/scales.
Roadway Quality Control
The Contractor shall perform roadway operations and quality control in accordance with the
specifications. The Contractor shall constantly monitor equipment, materials, and processes to
ensure density and surface tolerance meet specifications. Quality control testing and inspection
shall be sufficient to ensure a smooth and homogenous pavement, free from segregation, truck
ends, raveling, tearing, streaking, rutting, cracking, shoving, dragging of rocks, and rippling.
Mixture temperature has a substantial effect on density of the mat and shall be monitored. The
Contractor shall coordinate plant production rate with transportation and placement rates to
ensure continuous placement of mix. The Contractor shall monitor placement to ensure cross-
slope, grade, and transverse requirements meet requirements of specifications and the Materials
Sampling Manual.
A best practice recommendation for contractors:
When beginning plant production, dump the third, then second, then first load out of the plant silo
into the MTV or paver. Continue with dumping trucks into the MTV as they arrive to the project
thereafter.
Density
The contractor shall supply a sufficient number of rollers and experienced operators to ensure
consistent density transversely as well as longitudinally along the paving strip. The contractor
shall maintain consistent quality control to meet PWL requirements for mainline mixtures on
projects with > 1000 current plan ADT as well as required densities for minor mixes. For projects
1000 current plan ADT acceptance densities will be based on average densities or PWL per
sublot, as determined at preconstruction conference.
The contractor shall have roadway quality control that monitors density and smoothness for
consistency and implements needed adjustments to meet 100% compliance with specifications.
SECTION 502 – ASPHALT (Roadway)
73
Roadway Inspection
Inspection of Mixture on Roadway
Department personnel shall visually inspect the asphalt mixture. The Certified Inspectors are to
evaluate the mixture at the jobsite. Mixtures exhibiting the following deficiencies shall not be
placed:
Segregation
Contamination
Lumps
Non-uniform coating
Excessive temperature variations
Other deficiencies
Mixture contamination, alignment deviations, variations in surface texture and appearance or
other deficiencies apparent on visual inspection will not be accepted. Poor construction practices
such as inadequate handwork, improper joint construction, or other deficiencies apparent on
visual inspection will not be accepted. Deficiencies revealed by visual inspection both after
placement and before final acceptance shall be corrected at the Contractor’s expense.
If a load of asphalt mix is suspect of deficiencies, but placement is allowed, the paving Inspector
will sample the asphalt mix for testing. The paving Inspector will document the exact location of
material placement. Materials identified as being deficient may require subsequent removal and
replacement at the contractor’s expense. The contractor assumes risk when deficiencies are
suspected. Sample from a safe location. Have the MTV place mix in a safe location, sample from
the end of the paver, or in extreme situations sample from the roadway. Mix should be placed in
one-gallon friction top cans. When mix cannot be sampled in a safe manner during laydown
operations, the contractor will be required to provide loose mix sample or roadway cores for
testing.
Department personnel are to observe haul trucks for certification conformity. If haul trucks are
not maintained to truck certification standards, they shall not be allowed on state projects. Areas
of observation are:
Tight fitting tailgates
Dump beds tight, clean, and smooth
Tarps canvas or vinyl large enough to cover the top and extend over the sides (sand
tarps not allowed)
Sufficient tie-downs to secure the tarp
Certification sticker(s) are legible
No fuel or fluid leaks
Petroleum products such as diesel shall not be allowed in dump beds
Trucks that do not comply with certification and specification requirements will not operate on
state projects. Report continued nonconformance to the P.E. and DLE.
The DOTD Certified Paving Inspector at the laydown site is responsible for observing the
performance of surface tolerance testing, checking lane widths and other grade and alignment
SECTION 502 – ASPHALT (Roadway)
74
checks and equipment suitability. The Certified Paving Inspector is responsible for maintaining a
running total of tonnage delivered to the project from each plant lot. The Inspector must also
document mix placement on the roadway. Plant Lots are the same as Roadway Lots, and are
used to track mix placement. Continuous records of lot placement will be maintained. The
Certified Paving Inspector will check yield on a continuing basis during the project and calculate
yield for each portion of a lot delivered to the roadway. Beyond these duties, the Certified Paving
Inspector must observe the appearance of the mat behind the paver and rollers, for uniformity
and acceptability of mat thickness and width, joint construction and performance of the paving
train equipment. If material related problems occur at the jobsite, then the Certified Paving
Inspector shall make immediate contact with the Department’s ADI and DLE so adjustments can
be made in the manufacturing and transport processes.
Ensure the Contractor has adequate incidental equipment such as rakes, tampers, lutes, and
shovels available at the project for work being performed. Equipment must be clean and in
satisfactory condition.
Discarding Material
When dumping asphalt mix into the MTV at the start of paving operations, the contractor will
discard approximately the first 200 to 300 lbs of material (approximately a wheel barrow full). This
material shall be disposed of by the Contractor/Producer outside the limits of the right-of-way of
the project. No deduction in lot tonnage totals will be made for this material waste. The Paving
Inspector is to monitor the truck dumping operation for excessive waste.
Lumps, Contamination, Coating
Any material not properly coated, has lumps, or contaminated shall be rejected prior to placement.
Lumps may be indicative of moisture problems or a dryer/drum that needs cleaning. If the Paving
Inspector observes this deficiency, they are to notify the Contractor, DLE, and/or ADI. Discontinue
operations and clean the dryer/drum. Improperly coated mix will be sampled and a Ross Count
performed (AASHTO T 195). Contaminated material will also be sampled. When sampling
material for future Department investigation, the Inspector must be certain to obtain a sample that
is representative of the questionable material.
Temperature
The Paving Inspector is responsible for verifying temperatures of material at the roadway is within
specification tolerance. The temperature of material in the truck shall be within 25°F of the bottom
limit of the job mix formula (JMF). If the temperature is outside this tolerance or exceeds the
upper JMF temperature limit, it is out of specifications and shall not be placed. The paving
Inspector will record the job site temperature and tonnage rejected on the back of the haul ticket
and void the ticket. The paving Inspector will immediately notify the Contractor, DLE and/or ADI
and then check each subsequent truck until the material temperature is within acceptable limits.
Record the material temperature on the haul ticket. The temperature of the mix going through
the paver shall not be cooler than 24F. In such cases, record the temperature of the material
and the tonnage discarded on the haul ticket(s) and adjust payment quantities.
An infrared thermal heat-sensing device (temperature gun) shall not be used for
temperature acceptance. Questionable temperatures measured using an infrared device
shall be verified with a standardized dial (stick) thermometer.
SECTION 502 – ASPHALT (Roadway)
75
For the beginning of plant production, the first three loads of a JMF for a project may be above
the JMF limits but in no case greater than 350ºF. This allows for startup variances at the plant.
Theoretical Yield
The estimated quantity of asphalt mix shown on the plans is the amount for the project based on
mixture weights of 110 lbs per square yard per inch of thickness (lbs/yd
2
/in. When constructed in
accordance with the dimension and mat thickness shown on the plans, plan quantities should be
accurate. When asphalt mix placed is less than the plans call for, the mat will probably, on
average, be too thin.
When asphalt mix placed is more than the plans call for, the mat probably will be, on average, too
thick. Additionally, a cost overrun will result. Failure to keep the actual quantity of asphalt mix
used fairly close to plan quantity may require a change order. When using, extra material for
minor adjustments due to field conditions, it is imperative that current Departmental policy for
overruns are followed.
Plan quantity calculation is on asphalt mix weighing 110 lb/yd
2
/in. Some aggregates, such as
sandstone or slag, cause the unit weight of the mixture to differ from the standard 110 lb/yd
2
/in.
value.
To account for this weight difference , the Department established weight-volume adjustment
factors to determine theoretical yield of an asphalt mixture with a theoretical maximum specific
gravity (G
mm
) outside the range of 2.400 2.540. Factors (from section 502.14 of the Standard
Specifications) are shown in the following table.
Use Validated G
mm
to determine adjustment factors. Monitor G
mm
using QC data and verification
samples.
Table 8
Adjustment Factors for Pay and Calculating Yield
Theoretical Maximum Specific
Gravity, (G
mm
) (AASHTO T 209)
Adjustment Factor
(F)
2.340 2.360
1.02
2.361 2.399
1.01
2.400 2.540
1.00
2.541 2.570
0.99
2.571 2.590
0.98
The adjustment factor (F) for mixtures with theoretical maximum specific gravities (G
mm
) less
than 2.340 or more than 2.590 is determined by the following formulas:
Theoretical Maximum Specific Gravity (G
mm
) less than 2.340:
S
400.2
F
Theoretical Maximum Specific Gravity (G
mm
) more than 2.590:
SECTION 502 – ASPHALT (Roadway)
76
S
540.2
F
Where:
F = quantity adjustment factor; and
S = theoretical maximum specific gravity (G
mm
) on JMF.
Example:
Theoretical maximum specific gravity is 2.320.
320.2
400.2
F
F = 1.0345 = 1.03
The theoretical maximum specific gravity (G
mm
) is on the approved job mix formula.
For asphalt mixtures with an adjustment factor other than 1.00, the theoretical yield of the mixture
is determined by dividing the theoretical yield based on 110 lb/yd
2
/in thickness by the applicable
adjustment factor. Below is an example for the calculation of the adjusted theoretical yield.
Example:
If the material placed has a theoretical maximum specific gravity (G
mm
) of 2.390, the factor
of 1.01 (from Table 8) will apply. Assume the material placed is in a 2.0-in. lift.
T = Thickness in inches
Theoretical Yield = 110 x T
Theoretical Yield = 110 x 2.0 = 220 lb/yd
2
FactorAdjustment
YieldlTheoretica
YieldlTheoreticaAdjustment
Adjustment Theoretical Yield =
1.01
y d/inchlb /sq220
Adjusted Theoretical Yield = 217.8 lb/yd
2
A mixture with a theoretical maximum specific gravity (G
mm
) of 2.390 would
require 2.2 less lbs (220 217.8 = 2.2) of asphalt mixture per square yard
for the same volume (2.0 in. thick) as a mixture with a theoretical maximum
specific gravity (G
mm
) between 2.400 and 2.540, inclusive.
Factors used to adjust pay quantities, based on actual tonnage used, documented on haul
tickets. If plan quantity for a project is 11,620 tons and the material placed has a theoretical
gravity of 2.390 (factor 1.01), 11504.950 tons of this material would be needed to occupy the
same volume as a mixture with a theoretical maximum gravity (G
mm
) of 2.400-2.540 (factor 1.00).
The target tonnage for this project would be 11,504.950 tons. Assuming this target tonnage is
SECTION 502 – ASPHALT (Roadway)
77
the tonnage used on the project as documented on haul tickets to calculate payment tonnage,
multiply the tons used by the factor 1.01.
11,504.950 tons x 1.01 = 11,620.000 tons
To equal plant quantities, pay the Contractor for 11,620 tons of material. If the Contractor were
to place plan quantity (11,620 tons), the mat would be too thick. To be certain the amount of
material placed is correct; apply factors when doing yield calculations.
A quick check of theoretical yield can be calculated for paving operations as lbs/yd
2
/in. Use the
value in a variety of applications such as:
Establishing distances that one truck or multiple trucks should cover
Verifying sub lot and lot yield for travel lanes and shoulders
Determining the amount of asphalt mix needed for irregular areas, driveways, turnouts,
crossovers, etc.
Document Theoretical Yield in field books and on the Asphalt Concrete Pavement Report.
Below are examples of the different applications. Assume an Adjustment Factor of 1.00 for all
examples:
Establishing distances that one truck or multiple trucks should cover:
Weight of Asphalt Concrete in Truck in Tons x 2000
(Width of Paving Strip/9) (110 x Plan Thickness in Inches)
23.60 tons x 2000
(11.5 ft. wide paving strip/9) (110lbs x 2 in. plan thickness)
47200.00 lbs
(1.27 sq yds per linear ft.) (220 lbs)
47200.00 lbs
279.40 lbs per linear ft.
168.93 = 169 linear ft. that this truck should cover
An alternate method of tracking and monitoring yield for trucks is to convert the lbs per linear ft.
value to tons per linear ft.
279.40 lbs per linear ft./2000 = 0.1397 = 0.139 tons per linear ft.
Apply the converted value as a constant by dividing this value into the tonnage of asphalt mixture
delivered as reflected on a haul ticket. This is based on the width of the paving strip and the plan
thickness not changing. Note: There will be a slight difference in distances, because of the
conversion from lbs per linear ft. to tons per linear ft.
SECTION 502 – ASPHALT (Roadway)
78
23.60 Tons of Asphalt Concrete in Truck
0.139 tons per linear ft.
169.78 = 170 linear ft. that this truck should cover
SECTION 502 – ASPHALT (Roadway)
79
Confirming sublot and lot yield for travel lanes and shoulders:
Use 5000 ton lots to track asphalt mixtures shipped from the plant.
A roadway lot consists of 5 (five) 1000-ton sublots totaling 5000 tons.
Assume the typical section of a roadway is 24 ft. wide and 2 in. thick. The sequence of
construction will utilize an 11.5-ft. wide paving strip for a standard 1000-ton sublot. The full width
of the roadway would be accomplished by laying an adjacent paving strip of 12.5 ft. Adjacent
paving strips may not always be included in the same sublot.
Sublot in Tons x 2000
(Width of Paving Strip/9) (110 x Plan Thickness in Inches)
1000 Tons x 2000
(11.5 ft. wide paving strip/9) (110 lbs x 2 in plan thickness)
2,000,000.00 lbs
(1.27 sq yds per linear ft.) (220.00 lbs)
2,000,000.00 lbs
279.40 lbs per linear ft.
7158.19 = 7158 linear ft. paved from a 1000-ton sublot
Determining the amount of asphalt mixture needed for irregular areas, driveways, turnouts,
crossovers, etc.:
Assume an overlay project has 25 residential driveways, with each driveway having an area of 15
square yards and a plan thickness of 4 in. Below is the required calculation necessary to compute
the total tons to complete construction of the 25 driveways.
(Total Area in Square Yards) (110 lbs x Plan Thickness in Inches)
2000
(25 driveways x 15 Square Yards) (110 lbs x 4 in. plan thickness)
2000
(375.0000 sq yds ) (440.0000 lbs)
2000
165,000.0000 lbs
2000
82.5000 = 82.50 tons needed
SECTION 502 – ASPHALT (Roadway)
80
Actual Yield
Actual yield is the amount of asphalt mixture placed in terms of pounds per square yard. It is the
responsibility of the Certified Paving Inspector to maintain a constant check on actual yield during
paving operations to ensure actual yield and theoretical yield will match closely at the end of the
project. Check actual yield and compare to theoretical yield several times during a paving day,
at the end of a lot, and at the end of the project. Average mat thickness is not exact, actual yield
may vary slightly from theoretical yield on an individual truck or even for several truckloads. It
should never run consistently over or under theoretical yield. If actual yield is consistently over
or under theoretical yield, something may not be correct with the paving operation. The Contractor
will be required to identify and correct the problem, or the project will not conform to the plans.
The formula for computing actual yield is as follows:
Pav ementofYardsSquare
2000xUsedTons
YieldActual
Utilizing the example of establishing sublot limits in the previous section on Theoretical Yield, a
comparison against the Actual Yield shall be made and documented on the Superpave Asphalt
Concrete Pavement Report.
A sublot placed containing 1040 tons of asphalt mix in a paving strip 7158 ft. long, by 11.5 ft. wide
and 2 in. thick.
Square Yards = (7158 ft x 11.5 ft)/9 ft/yd
2
= (82317.00)/9 = 9146.33 = 9146 square yards
yardssquare9146
2000xUsed Tons1040
YieldActual
y ardssquare9146
lb s2,080,000
YieldActual
Actual Yield = 227.421 = 227.4 lbs/yd
2
The difference between Theoretical Yield of 220.0 lbs/yd
2
/plan thickness in inches and Actual
Yield of 227.4 lbs/yd
2
used is 7.4 lbs/yd
2
over. This indicates the mat may be too thick and an
overrun for this sublot has occurred.
One method for calculating percent overruns or underruns is from tonnage. 1000 tons was
needed for the area to be paved based on Theoretical Yield for the sub lot. The area uses 1040
tons.

 








 
SECTION 502 – ASPHALT (Roadway)
81
As stated earlier, Actual Yield should never run consistently over or under theoretical yield.
Overruns or underruns for the Contract Item may require a Change Order in accordance with the
DOTD Construction Contract Administration Manual.
High AC content mixes such as SMA may need an adjustment factor for calculating roadway
yield. See the appendix for roadway yield correction factor calculations.
Joint Construction
Construction of all pavement joints shall be according to requirements of the specifications. As
described in this manual and Standard Specifications, they shall be inspected by the
Department’s Inspectors for satisfactory compliance to Department standards and procedures.
Longitudinal Joints
Department specifications stipulate, during construction of a longitudinal joint, no material will be
scattered loosely over the uncompacted mat. Overlapped material shall be pushed back to form
a vertical edge above the joint. The vertical edge shall then be compacted by rolling to form a
smooth, sealed joint.
Coarse aggregate shall not be raked from the asphalt mixture at the joint. Excess material or
spillage shall not be pushed onto the uncompacted mat. If workers cast the overlap onto the
uncompacted mat, this material will be segregated and not visually appealing. Such material will
ravel under traffic. If this occurs, the Inspector must require removal of the material from the fresh
mat before the roller approaches the area.
After compaction, a properly constructed longitudinal joint should not be high or low when
compared to the adjacent mat. There should be no rough material at the joint location. The
contractor shall properly seal the joint. There can be no opening allowed between the mats. The
joint should not overlap onto the previously compacted mat. The Inspector must check the joint
for all applicable variables after compaction. The Inspector should also place a 10-ft. static
straightedge, provided by the contractor, across the joint, transverse to the centerline. If there is
any deviation greater than the transverse surface tolerance applicable to the course listed in Table
502-5 of the Standard Specifications, corrective action is required. Checking the joint with a 10-
ft. static straightedge is effective on a tangent slope. It will not work on a two-lane roadway with
center crown. For a roadway with center crown, the Inspector will place a 10-ft. static straightedge
across the joint with approximately 1 ft. resting on the new mat. If the fluff is not adequate, there
will be a dip at the joint and the paver shall be adjusted.
Transverse Joints
Form a transverse joint whenever paving operations are discontinued long enough for the
temperature of the asphalt mixture being placed to fall more than 50° F from the lower limit of the
JMF. This includes the interruption of paving operations at the end of the day. Equipment
malfunctions, plant problems, or weather conditions can also cause an interruption of the paving
operations, which will require construction of a transverse joint.
The Inspector will visually inspect the joint longitudinally and transversely to determine if there are
any apparent deviations in the area. The Inspector will then place a 10 ft. metal static
straightedge, provided by the contractor, at several locations across the joint location and attempt
SECTION 502 – ASPHALT (Roadway)
82
to push a shim the thickness of the applicable specification deviation beneath the straightedge.
The joint shall comply with Subsection 502.08.3.2.
If the transverse joint does not meet specification requirements, the Contractor shall correct it
before the paving operation proceeds. The paving operation shall not proceed further than
100 ft. from the transverse joint until the transverse joint meets specifications. Only the
minimum amount of handwork required to correct the deficiency is allowed and only the affected
area shall be worked. This handwork must be completed so the area can be recompacted before
the mat surface has cooled beyond the point where compaction can be achieved. If the deviation
at the joint is excessive (i.e., beyond that which can be satisfactorily repaired with a minimum
amount of handwork) the contactor is required to completely remove the material placed and
reconstruct the joint with the paver.
After any required corrections are completed and the area compacted, the Inspector must recheck
the joint to ensure that the corrective action has met all Department surface finish requirements.
The surface texture of the corrected area must be acceptable. If the Inspector is still unable to
approve the joint, the Contractor must take additional corrective measures.
Segregation
If material appears segregated in the truck, the Inspector shall determine if the degree of
segregation is severe enough to warrant rejection. If placement of the load is allowed, the
Inspector is to sample the material for subsequent testing. If the material appears segregated in
the truck, the Inspector must check the mat carefully behind the paver. If segregation is apparent,
the Inspector shall notify the Project Engineer and the ADI. Future trucks showing segregation
will be rejected until the problem is corrected. If material does not appear segregated in trucks,
but the mat exhibits segregation, the Inspector shall require the Contractor to identify and correct
the problem immediately. Operations shall be discontinued when problems are not corrected.
Segregated areas of compacted asphalt mix are subject to Department investigation for
acceptability and may be removed and replaced at the Contractor’s expense.
As previously stated, Section 503.14 of the Standard Specifications require the use of a material
transfer vehicle (MTV) when placing the final two lifts of asphalt mix on the roadway travel lanes.
The three main objectives in requiring the MTV are to reduce segregation, improve surface
smoothness, and promote continuous, non-stop paving. Asphalt mixtures placed without the use
of a MTV when placing base course mixtures, leveling, and shoulders or as allowed by Subsection
503.14. The Certified Paving Inspector should continually monitor the finished mat for any
segregated area.
When paving without a MTV (dumping asphalt mix directly into the paver hopper from the haul
truck), proper truck exchange is critical to the production of a smooth, uniform mat. The truck
should never bump the paver and should not rest on the paver hopper. Dumped or spilled material
in front of the paver is not allowed. The material should be dumped into the paver in a large mass
to prevent segregation.
Segregation on Mat
Segregated areas of the mat will have a different look from the rest of the roadway surface. These
areas will be open-textured. The size of these areas will vary depending on the severity of the
cause. It is not uncommon for such open-textured area to be 30 ft. long and the full width of the
paver, although many of the areas are confined to 15-ft. lengths and just the center two-thirds of
SECTION 502 – ASPHALT (Roadway)
83
the paver’s width. The areas have a tendency to become more noticeable after being exposed
to traffic and can best be observed when the angle of reflective light is low (i.e., early morning or
late evening) or just after a rainfall. Under these conditions, the open-textured areas remain wet
and dark looking when compared to the drier surrounding areas.
Truck Ends
Truck end segregation is caused by coarse aggregate fractions separating from fine aggregate
fractions in either production, transport or laydown processes. In severe cases, separation can
be observed at the plant when noticeable roll-down of the coarse aggregate occurs toward the
sides, the tailgate, and the cab area of the haul unit. Such roll-down segregation results in a truck
end in one or more of the following ways.
Feeding segregated roll-down material at the tailgate onto an empty slat conveyor
back to the paver augers as segregated material causes a truck end.
Segregated roll-down material on the sides of the haul truck migrates to the wings of
the paver hopper. When the wings are dumped (i.e., the material in the wings is fed
to the slat feeder), this segregated roll-down material will cause a truck end.
Segregated roll-down material at the cab end of the truck (which is the last mix from
the truck) will roll down the entire length of the bed, and if fed by itself to the augers,
will cause a truck end.
Numerous investigations have identified the material at truck end locations to be inferior in quality,
possessing low asphalt content, with an extremely coarse gradation and a low roadway density.
The net result of these poor mix qualities is an area of roadway that will crack and/or ravel
if used as a wearing course or be structurally deficient and subject to moisture damage if
used as a binder or base course. Beyond poor mixture characteristics associated with truck
end segregation, a poor ride is often the result. Poor ride is identified by dips at the same intervals
previously described. Dips are due to a paver’s screed settling on the coarse mix during
construction (i.e., a mixture with high air voids offers less resistance to the screed) or dips develop
later under traffic, when high-void areas that have low initial density are compacted more than the
well-compacted areas immediately adjacent.
Regardless of where segregation is observed, truck-end segregation areas on the roadway are
to be eliminated or minimized to the best degree possible.
It is important to remember material is segregating through whatever handling processes it is
subjected to (e.g., coated in a dryer/drum, conveyed into a surge/storage silo, emptied into a large
trailer truck and dumped onto a paver’s empty slat feeder). It is equally important to know some
well-graded and well-coated mixes do not segregate given an identical handling process. Not all
attempts to eliminate or effectively minimize truck-end segregation have been taken until one or
more mixtures, processes, and handling changes have been tried and implemented.
Take the following steps whenever segregation is observed:
Paver wings should not be dumped until the end of the paving day. Asphalt mix
dumped from paver wings shall be discarded and not incorporated into the roadway.
SECTION 502 – ASPHALT (Roadway)
84
Haul trucks are to be loaded to minimalize segregation. When correcting segregation
issues, haul trucks should be loaded with a minimum of three drops, the last of which
shall be in the middle of the bed. It is the intent of this loading procedure to first load
as close to the tailgate and cab areas as possible to minimize roll-down and then
complete the load in the middle of the bed.
During the exchange of trucks at the paver (when no MTV is required), the level of
material remaining in the paver hopper should not drop so low as to expose the feed
slats. Keeping feed slats covered with material will aid mixing of whatever roll-down
material exists with non-segregated material before being fed to the paver augers.
The paver augers should run at minimum revolutions to reduce segregation. Maintain
the level of material to at least the auger shaft. Augers should run at least 95% of the
time.
Any segregated areas on the roadway that occur at regular intervals must be eliminated or
effectively minimized. The Paving Inspector must be aware of the potential problem and maintain
constant communication with the Contractor production and paving personnel when a problem
exists. The Project Engineer will instruct the Contractor/Producer to correct problems associated
with segregation.
Coordination of Paving Operations
Coordination of Paving Operations with Production and Transport
One of the most important elements of successful asphalt paving operations is the coordination
of paving speed to plant production and hauling capacity. A start and stop operation will not
produce a uniform mat and smooth riding surface. Start and stop paving operations are
prohibited by the specifications. The Standard Specifications require the Contractor/Producer to
coordinate and manage plant production, transportation, and laydown operations to ensure
reasonably continuous plant and paving operations with minimum idle time between loads.
Delivery of material to the paver must be at a uniform rate. There should be no waiting time
between truckloads; nor should a large number of trucks be waiting to discharge into the paver
or MTV. The correct paver speed is such that as one truck empties and pulls away, one truck is
waiting to move into discharge position immediately. If sufficient hauling vehicles are not
available to maintain a smooth, coordinated paving operation, specifications authorize the
discontinuance of operations or requirement of additional trucks. Paver speed and plant
production should also be tied to time required for rollers to achieve compaction in the paving
train.
Roadway Acceptance
Roadway lot pay will be based on tons received on the roadway. Pay adjustments will be based
on Pavement Density calculated by methods shown below. Surface Tolerance pay will be
calculated at the end of the project.
Lots and sublots shall be of the same JMF and sequence number.
SECTION 502 – ASPHALT (Cores)
85
Core sampling determination.
1. Each sublot will be divided into two equal sections with a randomly selected location
in each section for a total of two acceptance cores per sublot. Core location shall be
determined by application of random numbers.
2. One QC core will be taken within 12” of each acceptance core in the direction of travel.
Assume a sublot is composed of 1000 tons production of a specific approved JMF. Tonnage is
based on field conditions in place.
Sublots may be used for contain both mainline and minor mix use.
Tonnage shall be tracked by station-to-station methods and recorded according to Department
policies. Haul Tickets shall be tracked according to lot, JMF, mix type, mix use and mix
placement.
Pay adjustments will be applied to quantities:
By lot for mainline with >1000 current plan ADT,
By sublot for projects with ≤1000 current plan ADT, if declared at pre-construction
conference.
By sublot for all minor mixes.
Projects with ≤1000 current plan ADT:
Areas with <90.5% density will be isolated at the direction of the engineer
By further coring or NDT in both directions from the deficient core in increments
not to exceed 100 feet until minimum required roadway density is located
The localized deficient area will be removed and replaced or a 50% pay adjustment
will be applied at the discretion of the Chief Engineer
Mainline Lots: (92.0 min Density); 1000-ton Sublots; 5000-ton Lots
Travel lane base, binder and wearing; ramps > 300’, interstate accel/decel
lanes, turn lanes, turnouts >300’
Take 2 Acceptance cores per sublot = 10 per lot. (To District Lab)
Take 2 Quality Control cores per sublot = 10 per lot. (To Contractor Lab)
For lots and sublots with both mainline and minor use, identify according to the sublot the core
was taken from.
For projects with > 1000 current plan ADT, compute PWL on roadway density.
For projects with ≤1000 current plan ADT (when option is chosen) acceptance is based on
average core density per sublot. The average core density of 92.0% is required with no individual
core less than 90.5% density for 100% density pay.
If there is also minor with density mix in the sublot, and there is no minor mix core, take one
additional acceptance core, using random numbers, from the minor mix.
SECTION 502 – ASPHALT (Cores)
86
For lots with mixed mainline and minor mix use, a minimum of 3 Acceptance and 3 Quality
Control cores for mainline will be taken per lot. When minor mix densities apply, a minimum of
one core for minor mix shall be taken when minor mix tonnage is the lesser in the sublot.
For mainline lots <1000 tons, take a minimum of 3 Acceptance and 3 Quality Control cores
regardless of current plan ADT. For projects < 250 tons, the PE decides testing requirements.
Minor Lots: (90.0 min Density) five 1000 ton sublots
Bike paths, crossovers, detour roads, leveling > 1.5” thick, parking lots, shoulders > 4’ wide,
ramps < 300’, patching, and widening > 2.5’.
Take 2 minor cores per sublot. (To District Lab) (For < 250 tons, PE decides testing
requirements.)
Quality Control cores are taken within 12” from Acceptance cores in the direction of travel.
Mainline Roadway Cores ~5000 ton LOT
~1000 Ton Sublot
A
~1000 Ton Sublot
B
~1000 Ton Sublot
C
~1000 Ton Sublot
D
~1000 Ton Sublot
E
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
A1
Core
A2
Core
A3
Core
A4
Core
A5
Core
A6
Core
A7
Core
A8
Core
A9
Core
A10
Core
QC1
Core
QC2
Core
QC3
Core
QC4
Core
QC5
Core
QC6
Core
QC7
Core
QC8
Core
QC9
Core
QC10
Core
A = Acceptance QC = Quality Control
Quality Control cores taken within 12” from Acceptance cores in the direction of travel.
Minor ~5000 Ton Lot
~1000 Ton Sublot
A
~1000 Ton Sublot
B
~1000 Ton Sublot
C
~1000 Ton Sublot
D
~1000 Ton Sublot
E
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
A1M
Core
A2M
Core
A3M
Core
A4M
Core
A5M
Core
A6M
Core
A7M
Core
A8M
Core
A9M
Core
A10M
Core
1QCM
Core
2QCM
Core
3QCM
Core
4CM
Core
5QCM
Core
6QCM
Core
7QCM
Core
8QCM
Core
9QCM
Core
10QCM
Core
M = Minor QCM = Quality Control Minor
Quality Control cores taken within 12” from Acceptance cores in the direction of travel
Mainline with Minor ~5000 Ton Lot
~1000 Ton Sublot
A
~1000 Ton Sublot
B
~1000 Ton Sublot
C
~1000 Ton Sublot
D
~1000 Ton Sublot
E
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
~500 ton
Section
A1M
Core
A2M
Core
A3M
Core
A4M
Core
A5M
Core
A6M
Core
A7M
Core
A8M
Core
A9M
Core
A10M
Core
1QCM
Core
2QCM
Core
3QCM
Core
4CM
Core
5QCM
Core
6QCM
Core
7QCM
Core
8QCM
Core
9QCM
Core
10QCM
Core
M1 core and QCM1
Core
M2 core and QCM2
Core
M3 core and QCM3
Core
M4 core and QCM4
Core
M5 core and QCM5
Core
A = Acceptance .
M = Minor QCM = Quality Control Minor
SECTION 502 – ASPHALT (Cores)
87
Quality Control cores taken within 12” from Acceptance cores in the direction of travel
See example in appendix for core sampling with mainline and minor mixes in the same lot.
Minor without density requirements curbs, driveways, guardrail widening, islands, joint
repair, spot leveling, medians, tapers, turnouts <300’ and shoulders 4’ paved with the
roadway. (For < 250 tons, PE decides.)
Minor mix without density requirements is accepted based on contractor plant
testing data.
Core Sampling
See the “Core Handling Flow Chart” protocol and time lines for testing, reporting,
challenges and resolution of acceptance cores.
Upon completion of compaction procedures, cores shall be taken in accordance with Section
502.11 and its subsections. Sampling shall be performed using the random number tables
found in the Appendix titled - Generating and Using Random Numbers for Sampling Purposes
or the random number generator in MS Excel
®
2010 or later.
Coring operation:
Within 24 hours after the sublot is placed closes
o If the 24 hours falls on a holiday or weekend, the next business day
If a random number places a core with 18 inches of a none supported edge, the
inspector will use another random number
The Certified Roadway Inspector shall list the generated random numbers on the Roadway
Report.
The Certified Roadway Inspector shall mark core locations on the pavement. Coring shall be
performed in the presence of the DOTD Inspector within 18 in. up or down station of the marked
location. Transverse location shall be the same distance from the pavement edge as marked.
When the Project Engineer or DLE request investigative coring, the coring shall be performed at
the marked location or as directed by the engineer. Core barrels for investigative and forensic
analysis shall have an internal diameter of 6 in. or as directed by the DLE. Normal coring may
use a 6 in. O.D. coring barrel.
If the sample obtained from the pavement is less than 1-3/8 in. (1.375 in.) thick, the Department’s
Certified Paving Inspector will reject the core and select another sampling location for that section
by reapplication of the Random Number Tables. Asphalt mixes placed in design lifts less than 1-
3/8 in. (1.375 in.) thick shall be compacted by approved methods to the satisfaction of the Project
Engineer and shall not require coring for pay. Informational cores may be taken when the design
thickness is less than 1-3/8 in.
Contractor QC cores shall be cut within 12” of acceptance cores in the direction of travel from
acceptance cores.
SECTION 502 – ASPHALT (Cores)
88
Acceptance cores other than patching and widening shall be cut with a core barrel with either an
inside diameter or outside diameter of 6 inches. The diameter of the core shall be approximately
6 inches.
Minor mix use for patching and widening with density requirements may use 4-in. diameter
cores. The top 6-inch of patching and widening cores are tested for density.
The DOTD Paving Inspector, along with the Contractor/Producer coring representative, will
inspect the cores for damage and acceptability and label them for identification. The DOTD
Inspector and the Contractor Technician in the field, upon inspection and mutual agreement,
reserve the right to reject damaged or under thickness core(s).
The core sample’s official thickness measurement will be obtained by taking 3 measurements
spaced uniformly around the circumference of the core before trimming and then averaged. The
measurements will be taken and recorded to the nearest 1/16 in. on the Superpave Asphalt
Concrete Roadway Report by the technician.
How to measure:
Measure cores to the nearest 1/16 inch
Cores shall be measured before trimming
Cores with multiple lifts shall be measured at/to the lift lines
Cores taken from cold planed surfaces shall be measured at approximately the midpoint
of visible ridges
Patching and widening cores:
Record the core length to the nearest 1/16 inch
Trim and keep the top 6 inches
Send the top 6 inches to the district lab for density testing
Patching and widening cores may be 4 inch diameter
When a specimen is damaged during coring operations, the recut core shall be taken from a
position longitudinally up or down the pavement within 5 ft.
The Contractor shall trim roadway cores on the project at the time coring is performed. This may
be done after all cores are cut per lane closure and away from traffic.
The contractor is responsible for providing proper traffic control and lane closures for safe coring
operations.
Cores shall be trimmed at the lift line, but shall not trimmed cut into the tested lift any more than
necessary to remove:
Tack
Base material
o Soil Cement
o Aggregate
o Soil
The preceeding or subsequent lift
Ridges and valleys from a milled surface
SECTION 502 – ASPHALT (Cores)
89
Lifts placed over milled surfaces, tested for density, shall have enough material removed to
eliminate “milling ridges and valleys.” Core thickness measurements shall be taken before
trimming.
All acceptance and quality control cores shall be clearly marked for identification with a permanent
marker or paint stick. See Table-10 for core identification.
Information written on each core:
Project number
Lot number
Core identification
The acceptance cores shall be delivered to the District Lab. The Contractor’s Quality Control
cores shall be delivered to the plant lab. Deliver all cores the same day they are cut, so results
for acceptance and Quality Control are available in a timely manner. Cores shall be delivered no
later than the next business day. The district lab and contractor’s lab shall dry the cores for testing
according to DOTD TR 304 (AASHTO T 166).
Roadway cores that cannot be delivered the same day they are cut shall not be left in a vehicle.
Cores are to be stored in a climate controlled environment in an approved transport container or
flat with the top surface down. I.e., Air conditioned office.
Contractors may request to transport roadway cores to the district lab. The request shall be in
writing and approved by the DLE.
With approval of the DLE for contractor transport of roadway cores, the following requirements
must be met:
The contractor shall supply sufficient clean paper or paper bags and clear packing tape
to wrap the cores. The paper shall not be newspaper or other paper with print, writing or
graphics that interfere with signature recognition.
Cores that are to be delivered to the district lab by the contractor or courier shall be
wrapped with the roadway inspector placing their signature on the wrapping paper.
The core will be wrapped across the inspector signature with clear wide packing tape.
The core shall be sealed with a second strip of tape 90° to the first.
The contractor shall deliver the cores to the district lab the same work shift they are cut.
The contractor and roadway inspector shall coordinate delivery with the ADI, lab staff
and DLE. The contractor will not take possession of the cores until it is confirmed a
district lab employee will be available to accept the cores.
The DLE may require a contractor supplied lockbox for core transport by the contractor
or courier.
The contractor may make a written request at the pre-construction conference to waive their core
trimming responsibility. It shall be at the DLE discretion to grant such requests.
Density
District Laboratory Acceptance
SECTION 502 – ASPHALT (Cores)
90
Cores shall be inspected by district lab personnel upon receipt for damage and minimum
thickness in the presence of the technician delivering the cores. The technician delivering the
roadway cores shall sign the chain of custody for the roadway cores.
If the contractor does not trim the cores in the field, the core sample’s official thickness
measurement will be obtained by taking 3 measurements spaced uniformly around the
circumference of the core and then averaged. The measurements will be taken and recorded to
the nearest 1/16 in. on the Superpave Asphalt Concrete Roadway Report by the technician.
All laboratories shall be equipped with a saw suitable for sawing asphalt pavement cores. This
saw may be used to remove base course material (e.g., soil cement and/or curing membrane),
different lifts and/or tack. Care must be taken to minimize the amount of material cut and
discarded, especially from the upper surface. Cores shall be cut at the lift line to remove tack,
but shall not cut into the tested lift. Lifts placed over milled surfaces, tested for density, shall have
enough material removed to eliminate “milling ridges and valleys.”
The Department will determine the G
mb
and report G
mb
results in LaPave with preliminary
percent density. The Contractor and the Department shall report core G
mb
results within 3
business days.
The Contractor will evaluate the pavement QC cores for roadway density, which shall be
computed by comparing bulk specific gravity (G
mb
) of the roadway core to the corresponding
sublot theoretical maximum specific gravity (G
mm
) as tested by the producer The contractor shall
enter G
mb
data for all QC cores into LaPave. The Contractor shall test and report a G
mm
from one
randomly selected QC roadway core from the lot into LaPave. The contractor shall follow the
same procedures as the district lab for G
mm
verification. If the first randomly chosen core does
not verify for the corresponding sublot G
mm
, the contractor shall test one core from each sublot in
the lot for G
mm
.
DOTD reserves the right to test remaining QC cores for verification. The contractor shall retain
all cores not used for G
mm
verification for a minimum of 10 business days after all testing,
challenges and/or resolutions are finalized for the lot.
Core handling flow:
Plant production data entered into LaPave
10 Acceptance cores cut 2 per sublot
10 Quality Control cores cut 2 per sublot
Cores accepted or rejected on the roadway by the Contractor’s technician and
DOTD inspector
Cores properly labeled
NOTE
To ensure that the cores are sufficiently free from moisture, they shall be
placed in a force draft oven at 125° F until a constant mass is achieved in
accordance with DOTD TR 304 (AASHTO T 166).
SECTION 502 – ASPHALT (Cores)
91
Cores are trimmed by the contractor in the field
Cores transported to the DOTD district lab and Contractor’s lab
Cores are dried to constant weight
Core G
mb
is measured and reported by both parties into LaPave
Results are revealed after both parties results are entered into LaPave
After all cores in the lot are tested, the lot is complete
The contractor has one business day to question DOTD G
mb
results after the lot
is complete. The contractor may also question G
mb
results on a sublot before the
lot is complete
The contractor shall put in writing (email or LaPave) the reason and cause for
questioning results. This is sent to the DLE.
If disputed, the cores are transferred to the Asphalt Technology Lab (ATL) at
Materials Lab for G
mb
retesting if G
mb
results are questioned
o If G
mb
of the district lab is verified, the contractor pays a testing fee and lot
pay is calculated based on the verified G
mb
.
o If G
mb
changes in favor of the contractor, no testing fee is incurred and the
reworked G
mb
is used to calculate pay.
After G
mb
of cores for the lot are finalized, one core from the lot is randomly
chosen for G
mm
verification by the district lab. If the core verifies within ±0.024 of
the average lot G
mm
, use the reported G
mm
of each sublot reported by QC testing
to calculate pay for the corresponding core sublot.
It the first selected core does not verify, the district lab will select one core from
the remaining sublots and test G
mm
. If the average G
mm
of all the cores tested for
G
mm
in the lot are within ±0.024 of the average plant lot G
mm
, calculate the pay of
the cores in each sublot using the corresponding QC reported G
mm
for each
sublot.
If the averaged G
mm
of all the sublots do not verify, the Contractor has one
business day to dispute the results. (DOTD and Contractor G
mm
results from
cores will be compared)
If the dispute proceeds, the district lab will transfer custody of the remaining
roadway cores with the ATL lab for G
mm
testing.
If the district lab G
mm
is verified, the contractor pays a testing fee and pay for the
lot is calculated based on the G
mm
from the roadway cores. If results change in
the contractor’s favor, no testing fee is incurred and pay for the lot is calculated.
When the core verification average G
mm
of all sublots is not within ±0.024 of the
average lot plant reported G
mm
, and any resolution if pursued verifies such, the
average G
mm
from the cores shall be used to calculate density of all sublots in the
lot.
In cases that do not verify, the ATL in conjunction with the district lab will
investigate the cause of the core G
mm
being out of tolerance.
If a cause cannot be determined or the core G
mm
from three lots fail to verify without
just cause, the JMF will be terminated.
Approximately 20 grams of No. 4 and +No. 8 asphalt coated aggregate from the G
mm
verification
core will be sent to the Materials Lab for GPC analysis.
GPC sample submittal is a minimum of 1 per project and 1 per 20,000 tons per project
thereafter.
SECTION 502 – ASPHALT (Cores)
92
See the Core Handling Flow Chart for a graphical representation of the above description:
SECTION 502 – ASPHALT (Cores)
93
Contractor cuts 10 QA and
10 QC cores per lot in
presence of DOTD
Contractor transports QC
specimens to Contractor Lab
and tests
QA cores transported to
DOTD District Lab
District Lab performs Gmb
testing on all cores
LOT CLOSED and
final core (Gmb) results
submitted to contractor,
Pay calculated using
contractor Gmm for each
sublot
District Lab waits 1 business
day to allow time for dispute
Contractor has one business
day to dispute (Gmb) results
Cores of disputed sublots
tested by ATL for Gmb
Contractor notifies DLE and
ATL
Yes
Gmb Dispute
District Lab transfers
custody of disputed QA
cores with ATL
Window for dispute closes
or Gmb dispute resolved
ATL reported values used in
place of District Lab
Pay Change
District Lab values remain,
contractor billed for $1,000
per sublot disputed
No Pay Change
ATL transfers custody of
disputed QA cores with
District Lab
Contractor Tasks District Lab Tasks
Asphalt Technology
Lab Tasks
To next
page
SECTION 502 – ASPHALT (Cores)
94
District Lab randomly selects
1 QA core to break for Gmm
verification
Pay calculation remains
using contractor Gmm for
each sublot
Within ± 0.024 of
average plant Gmm
District Lab notifies
contractor
Outside ± 0.024 of
average plant Gmm
District Lab selects
additional core from each
other sublot and breaks for
Gmm testing
Average within ±
0.024 of average
plant Gmm
Pay calculated using average
verification Gmm,
District Lab notifies
contractor
Average outside ±
0.024 of average
plant Gmm
Contractor has one business
day to dispute (Gmm)
results
Yes
Gmm Dispute
Remaining cores broken for
Gmm testing
Contractor notifies DLE and
DLE notifies ATL
District Lab transfers
custody of remaining QA
cores with ATL
ATL reported values used in
place of District Lab
Pay Change
District Lab values remain,
contractor billed for $1,000
No Pay Change
SECTION 502 – ASPHALT (NDT)
95
Weighing an object (as we do with an asphalt core) to determine its mass in air and its mass
in a fluid (as we do in water) whose specific gravity is known yields sufficient data to determine
its weight (mass), volume, and specific gravity. Specific gravity is defined as the ratio of the
weight of a unit volume of the sample to the weight of an equal volume of water at
approximately 25° ±1° C, (77 ±1.8° F).
DOTD specifies that the G
mb
be determined by TR 304. The equation from the test method for
calculating G
mb
is as follows:
Water) inWeight Weight(SSD
AirinWeight
G
mb
Note for Specimens with Obvious Surface Voids:
As the size of the external voids in the specimen increase, it becomes difficult to determine an
accurate SSD mass, because the diameter of the voids are of such size that the water will run
out of them before an accurate SSD mass can be determined. If air pockets are observed on
the core surface, there may be a problem with calculation of voids.
To account for this, alternate test procedures may be used with approval of the DLE. One
alternate test procedure is AASHTO T 275 Bulk Specific Gravity of Compacted Bituminous
Mixtures Using Paraffin, used for determining G
mb
when the percent water absorbed by the
specimen exceeds 2.0% as determined by the following equation:
Percent H
2
O Absorbed (by Volume) =
Water) in WeightWeight(SSD
Air)inWeightWeight(SSD
In addition to DOTD TR 304 and AASHTO T 275, an alternative method to determine G
mb
of a
cored pavement specimen is the Pure Volume method. It is performed by measuring the
thickness and diameter of the cylindrical specimen in numerous locations to calculate average
values and then using the following formula to determine its volume:
Heightx
2
Diameter
xVolume
2
This volume is used in the denominator with dry weight in air in the numerator to determine the
G
mb
.
In summary, if the Contractor or the DOTD Inspector suspects that G
mb
values determined via
TR 304 are yielding erroneous values, the DLE is to be notified and may approve use of these
alternate methods.
SECTION 502 - ASPHALT (NDT)
96
Density by Non-Destructive Technologies (NDT):
The Department is evaluating the use of NDT for density determination for pay.
In addition to all required quality control testing, contractors may submit quality control density
measurements collected using DOTD approved non-destructive technologies (NDT). Density
measurements reported by NDT devices will be for informational purposes only, such as, to
provide supporting documentation for a dispute claim. Density measurements reported by
NDT devices will not be used in place of any required quality control or quality assurance
testing.
Use a non-destructive technologies (NDT) device meeting requirements of AASHTO T-343
or AASHTO T-355.
When performing NDT tests, set the device in the single reading and shallow penetration
modes. A density measurement will consist of the average of five readings taken in
accordance with the reading pattern described by the manufacturers procedure manual.
Take readings where the pavement surface is flat and no surface moisture is evident. Use a
brush to clear loose particles from contact area.
Verify the NDT device operation daily using the standardization plate issued with the gauge.
Follow the Manufacturer’s instructions for performing the standardization. Ensure each day’s
standardization result is within the limits established by the manufacture.
Device Off-set Procedure
Prior to using NDT device measurements, an offset will be determined for each JMF, for
each project on a control strip, which is defined as the first 2000 tons of production on a
roadway. Without sufficient tonnage, as determined by the Project Engineer, this procedure
will not be allowed.
On days when a control strip is being placed, the DOTD personnel must witness the
contractor’s personnel standard count procedure and the establishment of the offset. The
NDT device will be used to determine an average density from 20 random locations
determined by the DOTD personnel within the validation lot/control strip. The center location
of the device readings will be marked. Core specimens will be extruded from marked location
within 24 hours from when NDT readings are conducted at that location.
The device readings will be compared with the core densities in order to establish a working
offset.
The offset will be specific to that device, for that JMF, for that project. In the event that the
JMF changes, or a new device is used, a new offset must be established.
Offset procedures should be followed as listed below:
1. Contractor and DOTD technicians should jointly verify all NDT parameters for each
device:
a. Successful self-test at start up
b. Daily G
mm
SECTION 502 - ASPHALT (NDT)
97
c. Lift thickness
d. Test mode
e. Target density
f. Correct any issue(s) prior to proceeding with field confirmation
2. DOTD personnel will select a random site on the mat:
a. Location of random spots will be recorded
3. NDT readings should be taken in single mode and reading pattern should follow
the 5-point star method as seen below for each core location.
4. The QA gauge operator will conduct 100 NDT density tests, 5 readings at each of
the 20 random core locations within the validation lot/control strip. The 5 readings
from each location will be averaged into a single density measurement for that
location.
5. Density gauge readings will be recorded by the contractor and in the density gauge
if possible.
6. Follow core sampling, trimming, handling and transport procedures outlined in
section 502.11.1.
7. The offset will be determined by subtracting the average device density from the
core density for each location. An average offset is determined using the 20 location
offsets. The offset will be applied on subsequent lots of the same JMF, with the
same device, during the construction of the project.
SECTION 502 – ASPHALT (NDT)
98
Offset computation example
Non-Destructive Testing (NDT) Offset Procedures
Project:
H.999999
QC
Technician:
Date:
Location:
QA
Technician:
NDT
Type/Model
Mix Type:
Wearing
Plant:
Gmm:
2.533
Location
Station
R/C/L
Non-Destructive Gauge Denisty (pcf)
avg.
Core
Density
(pcf)
center
2 o'clock
4 o'clock
8 o'clock
10 o'clock
1
2+83
R
143.6
141.4
144.8
141.8
139.2
142.2
146.6
2
3+35
R
144.8
139.5
140.5
143.9
142.1
142.1
151.2
3
3+57
C
143.2
139.9
143.9
144.5
143.5
143
146.9
4
4+24
L
144.2
144.4
144
145.1
144.4
144.4
146.7
5
4+89
R
144.2
142.3
142.1
143.7
139.9
142.4
145.7
6
5+23
R
144.3
142
141.3
143.4
139.7
142.2
147
7
5+55
R
141.8
140.4
141.4
140
141
140.9
150.8
8
5+96
C
139.7
142
143.6
144.2
143.3
142.6
146.2
9
6+54
L
141.6
145.2
143.8
144.5
139.6
142.9
146.1
10
6+94
R
142.4
144.1
140.7
142.8
144.6
142.9
147
11
7+21
R
143.1
143.5
141.8
144.5
143
143.2
148.6
12
7+60
R
139.2
141.9
141.7
139.8
139.9
140.5
147
13
7+82
C
139.1
139.7
140.8
143.1
139.1
140.4
151.4
14
8+42
L
143.1
141.6
140.5
142.1
139.6
141.4
148.1
15
8+88
R
144
139.2
144.2
145.4
143.1
143.2
151.3
16
9+13
L
144.5
142.2
141.7
145.3
140
142.7
148.1
17
9+45
R
142.7
143.7
144.9
145
139.2
143.1
145.8
18
10+05
C
142.4
145.2
145.4
139.3
140.6
142.6
151.3
19
10+55
L
142.5
144.4
144.4
140.1
145.4
143.4
149.9
20
10+90
R
140
144.4
143
140.8
144.9
142.6
147
NDT overall avg.
142.4
Core
avg.
148.1
Offset is the difference between the core avg. and NDT overall avg. (value can be negative)
Offset (pcf):
Core avg.
-
NDT
overall avg.
=
5.7
148.1
142.4
Input offset into NDT - *Important* - If core avg. is greater than NDT overall avg., then a positive offset is inputted into the NDT, and
vice versa
Offset (Gmb):
Core avg.
-
NDT
overall avg.
=
0.091
2.373
2.282
Offset
(Density,%):
Core avg.
-
NDT
overall avg.
=
3.6
93.7
90.1
SECTION 502 - ASPHALT (NDT)
99
Roadway Testing Procedures
This procedure is in addition to any and all acceptance testing done on cores for pay. It is to
be done after offset establishment, during production.
There are typically five sublots for each lot.
Mainline and minor mixes may be in the same lot/sublot. Divide each of the sublots into two
segments of approximately equal tonnage each.
For each sublot segment, the Department will determine sample locations using random
sampling approach.
The department will obtain one quality assurance device density reading (average of 5 spot
readings), using the contractor’s device when requested by the Project Engineer, at the
designated sample location. The contractor will obtain one quality control device density
reading (average of 5 spot readings) approximately 12 inches in the direction of travel from the
quality assurance reading.
If the sublot segment has mainline mix uses, the quality assurance reading will be taken from
the mainline portion. A typical lot will have 25 quality assurance readings and 25 quality control
readings. Record the location and mix use of each reading taken.
The NDT density readings will be entered into an approved DOTD software within 1 calendar
day. The offset value determined during validation will be applied in the software and reported.
Differences between the Contractor's quality control and the Department's quality assurance
density results will be considered acceptable if within ± 1.3%.
One destructive field core will be cut from the roadway every lot for offset and G
mm
verification.
The location will be determined randomly by DOTD.
Disputed NDT Device Readings
In the event of a questionable NDT device reading, a core will be extracted from the center
location of the 5 readings.
The core density will replace that NDT device reading for determination of density.
If the core density is found to be unacceptable, the roadway inspector will isolate the
questionable section with the NDT device.
SECTION 502 - ASPHALT (NDT)
100
Roadway Measurement Example
Non-Destructive Testing (NDT) Roadway QA/QC
Date
Project:
H.999999
QC
Technician:
NDT
Type/Model
Offset From
Validation
5.7
Location:
QA
Technician:
NDT
Type/Model
Offset From
Validation
6.8
Mix
Type:
Wearing
Plant:
Gmm:
2.533
Lot-
Sublot
Station
R/C/L
Reading
Type
(QC/QA)
Non-Destructive Gauge Denisty (pcf) Not offset
avg.
Density
with
Offset
Difference
(QA-QC)
center
2 o'clock
4 o'clock
8 o'clock
10 o'clock
1-1
2+83
R
QC
143.6
141.4
144.8
141.8
139.2
142.16
147.86
1.08
QA
140
142
143
140.8
144.9
142.14
148.94
1-2
3+35
R
QC
144.8
143
145
143.9
142.1
143.76
149.46
0.7
QA
142.5
144.4
144.4
140.1
145.4
143.36
150.16
1-3
3+57
C
QC
143.2
139.9
143.9
144.5
143.5
143
148.7
0.68
QA
142.4
145.2
145.4
139.3
140.6
142.58
149.38
1-4
4+24
L
QC
144.2
144.4
144
145.1
144.4
144.42
150.12
-0.22
QA
142.7
143.7
144.9
145
139.2
143.1
149.9
1-5
4+89
R
QC
144.2
142.3
142.1
143.7
141
142.66
148.36
0.92
QA
144.5
142.2
141.7
144
140
142.48
149.28
2-1
5+23
R
QC
145
144
141.3
143.4
142
143.14
148.84
1.14
QA
144
139.2
144.2
145.4
143.1
143.18
149.98
2-2
5+55
R
QC
141.8
140.4
141.4
142
141
141.32
147.02
1.16
QA
143.1
141.6
140.5
142.1
139.6
141.38
148.18
2-3
5+96
C
QC
139.7
142
143.6
144.2
143.3
142.56
148.26
-0.72
QA
141
139.7
140.8
143.1
139.1
140.74
147.54
2-4
6+54
L
QC
141.6
145.2
143.8
144.5
139.6
142.94
148.64
-0.92
QA
139.2
141.9
141.7
139.8
142
140.92
147.72
2-5
6+94
R
QC
142.4
144.1
140.7
142.8
144.6
142.92
148.62
-0.9
QA
141.8
140.4
141.4
140
141
140.92
147.72
3-1
7+21
R
QC
143.1
143.5
141.8
144.5
143
143.18
148.88
0.84
QA
142.4
144.1
140.7
142.8
144.6
142.92
149.72
3-2
7+60
R
QC
142
141.9
141.7
140
145
142.12
147.82
0.96
QA
142.4
142
140.7
142.8
142
141.98
148.78
3-3
7+82
C
QC
141
142
140.8
143.1
145
142.38
148.08
1.22
QA
141.6
143
143.8
144.5
139.6
142.5
149.3
3-4
8+42
L
QC
143.1
141.6
140.5
142.1
142
141.86
147.56
1.16
QA
139.7
142
143.6
141
143.3
141.92
148.72
3-5
8+88
R
QC
144
139.2
144.2
145.4
143.1
143.18
148.88
-1.16
QA
141.8
140.4
141.4
140
141
140.92
147.72
4-1
9+13
L
QC
144.5
142.2
141.7
145.3
140
142.74
148.44
0.5
QA
144.3
142
141.3
143.4
139.7
142.14
148.94
4-2
9+45
R
QC
142.7
143.7
144.9
145
139.2
143.1
148.8
2.42
QA
144.2
144.4
144
145.1
144.4
144.42
151.22
4-3
10+05
C
QC
142.4
145.2
145.4
139.3
140.6
142.58
148.28
1.52
QA
143.2
139.9
143.9
144.5
143.5
143
149.8
4-4
10+55
L
QC
142.5
144.4
144.4
140.1
145.4
143.36
149.06
-0.1
QA
144.8
139.5
140.5
143.9
142.1
142.16
148.96
4-5
10+90
R
QC
140
144.4
143
140.8
144.9
142.62
148.32
0.64
QA
143.6
141.4
144.8
141.8
139.2
142.16
148.96
5-1
11+40
C
QC
144.8
145
140.5
143.9
142.1
143.26
148.96
0.84
QA
143.2
139.9
143.9
144.5
143.5
143
149.8
SECTION 502 - ASPHALT (NDT)
101
5-2
11+88
L
QC
144.2
144.4
144
145.1
144.4
144.42
150.12
-0.88
QA
144.2
142.3
142.1
143.7
139.9
142.44
149.24
5-3
12+33
L
QC
144.3
142
141.3
143.4
139.7
142.14
147.84
-0.12
QA
141.8
140.4
141.4
140
141
140.92
147.72
5-4
12+74
R
QC
139.7
142
143.6
144.2
143.3
142.56
148.26
0.84
QA
141.6
142
143.8
144.5
139.6
142.3
149.1
5-5
13+20
C
QC
142.4
144.1
144
142.8
144.6
143.58
149.28
0.7
QA
143.1
143.5
141.8
144.5
143
143.18
149.98
SECTION 502 - ASPHALT (Pay)
102
Measurement and Payment
Measurement
Refer to 502.14 of the Standard Specifications
Payment
Refer to 502.15 of the Standard Specifications
If the Engineer adjusts the application rate of tack coat from that specified by the contract
document or Standard Specifications, payment for asphalt mixture will be increased or
decreased based on the difference in applied quantity of asphalt emulsion shown on paid
invoices (total charges). The contractor shall provide copies of paid invoices for this
determination.
Density
Mainline Payment
>1000 current plan ADT
After test results have been determined, use Quality Level Analysis in accordance with Tables
502-9 and 502-10 of the specifications to determine percent within limits (PWL), see Appendix
and Section 502.15 to determine pay. For an example on calculating PWL, refer to page 67.
NOTE for roadway densities there is only Q
L
. Q
U
does not apply to roadway density.
1000 current plan ADT (When declared at the Pre-construction Conference)
After test results have been determined, average the densities of each sublot and pay using
Table 502-7 with density requirements of Table 502-5
Payment for Mainline Small Quantities
Mainline mixtures:
>1000 current plan ADT
Ensure a minimum of three cores per sublot for pay calculations. For project lots less than
1000 tons, a minimum of three cores for density will be taken. Cores for projects with less than
250 tons per JMF may be waived or modified by the Project Engineer. Pay on density PWL.
1000 current plan ADT
Ensure a minimum of two cores per sublot for pay calculations. Cores for projects with less
than 250 tons per JMF may be waived or modified by the Project Engineer
Payment for Minor Mix Quantities
Two cores per 1000 tons with a minimum of 2 cores. This applies to minor mix with density.
Minor mix without density will be accepted on Contractor QC plant testing.
SECTION 502 - ASPHALT (Surface Tolerance)
103
Section 502.12 – Surface Tolerance
Surface Tolerance
See Table 502-8 Standard Specifications, Section 502.12 of the Standard Specifications
Profiler Certification
The Materials and Testing Section (MATLAB) certifies Inertial Profilers annually. The Materials
Section will contact Contractors whose Profilers have an established history with DOTD for
scheduling the annual certification. Any new Contractors shall call the Materials Section at
(225) 248-4168 to schedule an appointment for certification. ProVAL software is required to
analyze data. ProVAL is available free of charge at www.roadprofile.com. During certification,
the Contractor is required to provide all data collected from the test track to the Materials
Section representative. Data is provided to DOTD on a Contractor supplied USB storage
device and shall contain the following formats: raw data, header file, .ERD, and
.PRO. Contractors are encouraged to have their equipment (lasers and accelerometer)
calibrated by the Profiler manufacturer prior to attending the certification.
The DOTD Roadway Inspector shall check cross slope, grade and transverse surface
tolerance in accordance with Table 502-5.
Longitudinal Surface Tolerance Testing
Longitudinal quality control testing shall be in accordance with Subsection 502.12. The
Contractor shall furnish a DOTD Certified Inertial Profiler and measure both wheel paths
simultaneously. A wheel path is defined as 3 ft. (±½ ft.) on either side of the longitudinal
centerline of the lane being tested. The project, lane, and/or segment must meet the
requirements of Table 502-8 (depending on Category). Categories are defined in Table 502-
8. Individual deficiencies (bumps) greater than - the longitudinal value specified in Table 502-
5 when tested with a 10-foot metal static straightedge are to be corrected in accordance with
502.12.2.
How to Identify a Bump
The Rolling Straightedge Simulation in ProVAL may be used to help identify bumps.
ProVAL settings for the Rolling Strainedge Simulation are:
o Straightedge Length (ft) 10.00
o Deviation Threshold (in) 0.25
o Filter - Butterworth Low-pass (1.97 ft)
Field verify all deficiencies located with ProVAL to determine if a bump exists.
o Use distance measuring equipment to locate the possible bump. For example,
ProVAL identified a ¼ in. event at Station 102+00.
o Utilizing a 10-foot static straight edge, start at Station 101+75 and investigate
the horizontal surface of the wheel path in question of the roadway to station
102+10 looking for a bump according to Table 502-5.
o If no bump is found, the DOTD roadway inspector will note this in their field
book, and no further work investigation is required.
SECTION 502 - ASPHALT (Surface Tolerance)
104
o If a bump according to Table 502-5 is found, the Contractor must remove the
bump by diamond grinding or In lieu of grinding, the Project Engineer may
penalize the contractor $1000 per individual bump or ripple
After removal, the DOTD roadway inspector will re-evaluate to
determine that the bump is removed and note the removal in the field
book.
DOTD and contractor will repeat this process until the roadway is in
compliance.
Pre-op Tests and Observations
The DOTD Roadway Inspector shall ensure that the Contractor is using a DOTD Certified
Inertial Profiler for quality control and quality acceptance. Profilers must be certified and
operated in accordance with DOTD TR 644 and Section 502.12. To verify that the profiler to
be used to be used on a job is certified, the DOTD Roadway Inspector will check the calibration
decal or certificate (DOTD Profiler Inspection and Certification). The certification sticker will
display the date of certification, expiration date, high pass and low pass filter settings, collection
filter, and the DOTD Technician certifying the equipment. Inertial Profilers are certified for IRI.
When QC testing establishes that the cross slope is deficient, the Contractor shall immediately
suspend paving operations
The profiler settings shall match the certification settings during profiler operation on
DOTD projects. Since the settings on the profilers can be changed by the operator, it is
imperative that the certification settings be verified before accepting data from the
Contractor. The settings directly affect the data collected. By changing the settings,
the data collected can be manipulated.
Before a profiler is used, the following pre-operation tests shall be performed by the
Contractor, witnessed by the DOTD Inspector, each day of testing:
1. Tire Pressure CheckThe distance measuring system of the profiler is based on
revolutions of the wheel and the rolling radius of the tire. The rolling radius of a tire is
dependent upon the air pressure. A tire that is fully inflated has a larger rolling radius
than one that is not fully inflated. Tire pressure affects the number of revolutions made
in a given distance. The tire pressure shall be checked each morning on the cold
tires and adjusted if necessary. The correct tire pressure at which each profiler is to
be run may be found on the DOTD Profiler Inspection and Certification form. The tires
must be inflated to the specified pressure used on the day of certification.
If using a lightweight profiler, it should be driven for 15 minutes to warm the tires prior
to testing.
2. Vertical CalibrationThis test is performed on a stationary profiler by placing various
plates under the lasers and taking readings at each block height. Blocks shall
have a thickness of 0.25 in., 0.50 in., and 1.00 in. or 1.00 in., 2.00 in., and 3.00 in.,
depending on make of the profiler. The vertical calibration check ensures that the
height sensor is performing properly. The height sensor measures vertical distance
from the sensor to the roadway. For a profiler to pass the vertical calibration check,
the average difference must be 0.01 or less. The operator should not be in the unit
during this test.
SECTION 502 - ASPHALT (Surface Tolerance)
105
3. Bounce TestIt is performed on a stationary profiler while the operator bounces
the unit (according to manufacturer’s recommendation). This test is performed in
order to check that the accelerometers and height sensors are functioning properly.
Accelerometers measure vertical acceleration and are mounted above the height
sensor. If the sensors are working properly, the unit will filter out any bouncing or
excess movement of the unit itself during the actual surface roughness testing. The
display of the results will differ by profiler make. Some profilers will display
“pass” or “fail.” Other profilers will show an accelerometer graph. The rise and
fall of the graph lines above and below the zero mark must be symmetrical for
the test to pass
4. Horizontal CalibrationThis procedure calibrates the horizontal measuring system of
the profiler. This calibration is performed by running the profiler over a measured
distance of a minimum of 528 ft. The longer the calibration distance, the more
accurate the distance measurement will be over the project length. Whoever is going
to be in the profiler during the testing process must be in the profiler during the
horizontal calibration. The calibration adjusts for weight distribution. The profiler will
display, “calibration successful” or “calibration unsuccessful.” Other
manufacturers of profiler simply display the distance traveled. Profilers with a
GPS DMI are not required to calibrate the GPS. (See Odometer Check)
5. Odometer CheckThis check measures the distance traveled by the profiler and
verifies the horizontal calibration. This test needs to be performed by running the
same measured distance used with the horizontal calibration. Distance is usually
measured by a pulsar attached to a wheels. Rotation of the wheel is measured by
detection of pulses as the wheel rotates and the notches pass. Each pulse is directly
associated with a fixed travel distance through the rolling radius of the tire. The results
of the odometer check must be within ±0.1% of the distance measured. Profilers with
a GPS DMI will verify a minimum 528 ft distance to comply with the odometer check
requirement. GPS units do not have to be calibrated unless the odometer check fails
to meet the ±0.1% of the distance measured requirement.
Surface tolerance quality is determined by an International Roughness Index, (IRI) and is
measured in units of inches per mile.
Longitudinal Quality Assurance Testing
Once Pre-op Tests and setting verification are complete, the Contractor shall measure the
mainline wearing course continuously from start to finish in the direction of travel with the
DOTD Inspector present. At the completion of the quality assurance run for pay, the
NOTE:
All results of the pre-ops shall be printed (or clearly displayed in data on the
USB storage device) and turned in to the DOTD Inspector with the data.
The date and time of the test will be indicated with the pre-op results.
SECTION 502 - ASPHALT (Surface Tolerance)
106
Contractor’s Technician will provide the DOTD Certified Inspector a copy of the results on a
USB flash drive and a paper copy of the IRI report.
Surface Tolerance Pay
Report one IRI measurement in inches/mile for the entire project or an approved portion of the
project. The IRI values for the inside and outside wheel paths shall be averaged and reported
as the lane average and the mean of each lane average shall be reported as the project
average. Pay adjustment for the project is determined in accordance with Table 502-8 using
the average IRI.
SECTION 503 – PLANTS & EQUIPMENT
107
Section 503 – Asphalt Concrete Equipment and Processes
This section describes the equipment and processes used in producing asphalt concrete
mixture for a DOTD project under Standard Specifications, Section 501 (Thin Asphalt Concrete
Applications), Section 502, (Asphalt Concrete Mixtures), and in conjunction with Section 503,
(Asphalt Concrete Equipment and Processes).
This section shall be used along with Section 501, Section 502, and Section 503 of the
Standard Specifications. This section also applies to subsections of Section 1002 (Asphalt
Materials and Additives) and Section 1003 (Aggregates).
Plant Certification
Initial Plant Certification
Plants furnishing asphalt concrete mixtures in accordance with Sections 501 and 502 shall be
certified at least every two years pending inspection and approval by the DLE. The district
laboratory in the district in which the plant is located will certify the plant. Material shall not be
produced or accepted on any DOTD project from an asphalt plant that does not possess a
valid certification. Certified plants will have a Plant Inspection Certification sticker placed in an
obvious location in the plant control house.
Following is a list of steps required to certify a plant and on-site laboratory:
1. The plant shall be operational with approved materials on-site and be capable of
producing mixtures that are correctly proportioned and mixed. The plant shall
consistently produce specified materials in accordance with Sections 501 or 502.
2. In accordance with Section 503, the plant and laboratory equipment, meters, scales,
measuring devices and plant mixture-weighing device shall be tested, inspected, and
certified by the Weights and Measures Division of the LA Department of Agriculture
and Forestry or by an independent scale service, licensed by Louisiana and approved
by the certifying DLE. The certifications shall be maintained in the Plant Certification
File for access by district laboratory personnel with a copy emailed to the district lab.
The Service Technician will place a signed sticker in an obvious location in the plant
control house. Scales shall be checked in a conventional manner using known weights
of sufficient size to check the scale system in its upper ranges with a minimum number
of loadings, to the satisfaction of the Department
3. The Producer shall notify the district laboratory that the plant is ready for certification.
4. The DLE will send qualified personnel to certify the plant using the DOTD Asphalt
Concrete Plant Certification Report. This form documents the inspection of materials,
crushing apparatus, individual plant components, storage/surge silos, testing, and
laboratory. The DLE must sign and date the form.
5. Upon satisfactory completion of the Asphalt Concrete Plant Certification Report, plant
certification will be granted for a two-year period, provided the plant is maintained in
accordance with the conditions under which certification was issued.
SECTION 503 – PLANTS & EQUIPMENT
108
Random Conformance Inspections
The plant will be inspected randomly, a minimum of once per quarter, for conformance to
certification requirements by the ADI for the DLE. Upon completion of the conformance
inspection, the ADI will report findings to the DLE and Contractor. If deficiencies are identified,
the Contractor will need to correct these deficiencies within the agreed upon timeframe with
the DLE. Failure to correct these deficiencies may result in a suspension to continue to provide
mix to Department projects as determined by DLE.
During these inspections, the ADI will be in charge of reviewing the following:
Inspect Plant Operations within Certification
Plant Equipment Inspection
Lab Equipment
Lab Technician’s Certifications
Observe Technician’s Test Procedures
Materials
Re-Certification Deadline
Testing Frequency Compliance
All these items will be documented in the report.
Re-Certification
Before the two-year certification period expires, the Producer shall notify the district laboratory
that the plant is ready for re-certification within 60 days of certification expiration.
The Producer shall also notify the DLE of any major change in the manufacturing process at
the plant because a new certification inspection will be required. This would include the
installation of a new dryer/drum, RAP system, baghouse, storage/surge system, proportioning
system, crumb rubber system, chemical additive system (warm mix), or latex system.
Revoked Certification
NOTE:
When a calibration Service Technician located outside of Louisiana must
be used to calibrate a scale or metering device, the Service Technician
shall be licensed by the state where the Service Technician is located under
standards similar to those required by Louisiana and approved by the
DOTD Materials Engineer Administrator.
SECTION 503 – PLANTS & EQUIPMENT
109
If a plant fails to conform to the DOTD standards under which certification was issued, the DLE
will revoke the plant certification. The certifying DLE may also revoke or suspend plant
certification when the mixture demonstrates continued non-conformance to specifications due
to plant operations.
Once certification has been revoked, the plant will be prohibited from supplying mix for any
Department project until all deficiencies have been corrected and certification is reinstated by
the DLE.
Plant Laboratory Equipment and Documentation
The plant shall be equipped with a quality control laboratory. The plant laboratory shall contain
equipment to meet the requirements of the specifications and as referenced in applicable test
procedures.
The contractor’s plant laboratory shall contain equipment to meet the requirements of the
specifications for acceptance testing by DOTD personnel for 501 production.
Production and Design Laboratory Equipment Requirements
At the time of this printing, the following equipment is required, but not limited to:
Constant Temperature Oven [100°F (38°C) to 400°F (204°C)] A 350°F (177°C)
capability oven is for heating loose mix. It should be of adequate size to hold 3
gyratory molds.
An oven of 125°F (52°C) capability is required for moisture content determination
and for drying cores
Oven for conditioning SCB specimens
Fume hood(s)
Specimen Ejector
Shakers, splitters, scales
Approved SHRP Gyratory Compactor, and extra molds (4 recommended)
Maximum Specific Gravity (G
mm
) apparatus, including vibrating table, pycnometer,
vacuum pump and drier apparatus, and residual pressure manometer
Bulk Specific Gravity (G
mb
) apparatus, including balance, temperature controlled
water bath equipped with overflow spigot
Equipment to perform G
sb
Saw(s), suitable for cutting pavement cores and gyratory specimens (wet saw
preferred) including SCB specimens
Automated Ignition Furnace
Freezer for TR 322, Tensile Strength Ratio
Breaking heads for Lottman test
Water baths, at 77°F (25°C) and at 140°F (60°C)
Draindown test apparatus
Computer and adequate connection for internet connectivity (for data tracking
software and online reference manuals)
Laboratory Equipment Manual which documents equipment calibrations R18
requirements
Void content apparatus (FAA) and a Flat & Elongated (F&E) Gauge are required
SECTION 503 – PLANTS & EQUIPMENT
110
Approved Loaded Wheel Tracker (LWT) System
Semi Circular Bend (SCB)
Sand Equivalent equipment
Other laboratory equipment used to perform Quality Control Testing
Additional equipment that may be required based on mix design submitted. The following is a
list of equipment, but not limited to: DSR
The Contractor shall supply all of this equipment. In addition, the Contractor shall provide
sufficient 6-in. diameter molds and auxiliary equipment necessary for the gyratory compactor
and its calibration. A loading scoop (chute) for transferring material to gyratory molds is
recommended to minimize segregation and temperature loss and help in attaining consistency.
All equipment supplied by the Contractor/Producer (including electronic scales) shall be
maintained, serviced and calibrated in accordance with the manufacturers’ recommendations
and Subsection 503.02.2.
The DLE or their representative will inspect and approve all laboratory equipment supplied by
the Contractor/Producer at the time of initial plant certification and during all subsequent
inspections.
All laboratory equipment shall be calibrated and verified by the procedures in AASHTO R 18,
the appropriate test methods, and by the frequency directed in R 18.
The Contractor shall maintain a Laboratory Equipment Manual containing all records for
calibration of plant equipment. See the Preface and website for information and worksheets.
Scales and Meters Certification
In accordance with Subsection 503.02.2, every 90 days (or more frequently, if directed by the
DLE), the plant shall have its meters, scales, and measuring devices tested, inspected, and
recertified by the Weights and Measures Division of the LA Department of Agriculture and
Forestry or by an independent scale service approved by the certifying DLE. The required
DOTD Certification Report for Scales and Meters shall be completed and sent to the DLE each
90 days.
There must be a calibration sticker on each scale and meter. If the DOTD ADI has reason to
question the calibration of any scale or meter, the Inspector will contact the DLE. The DLE
has the authority to require the recalibration of scales or meters even though the ninety-day
calibration sticker has not expired. Meters must properly display flow rate and total amount of
material and liquid dispensed.
Roadway Equipment Approval
Primary roadway equipment shall be approved on a project by project basis. This equipment
includes asphalt distributors, pavers, rollers, hauling, and MTV equipment. A DOTD
representative will inspect and complete the Asphalt Concrete Paving Equipment Paving
Approval Form. This approval signifies that the equipment is in satisfactory condition and is
SECTION 503 – PLANTS & EQUIPMENT
111
capable of performing its function as related to proper paving practices and in accordance with
Department standards. Final approval will be granted following an evaluation of the
equipment’s performance on the project.
For haul trucks, separate tractor/trailer- trucks require certification together as a unit so that an
accurate total tare weight may be determined. The DOTD number on separate tractor/trailers
must match, showing that they were originally certified together. A new trailer shall require a
new certification. Prior to certification, a truck or tractor/trailer shall have its tare weight
determined on a truck scale certified by the Weights and Measures Division of the Louisiana
Department of Agriculture and Forestry. This tare weight shall be determined with the fuel tank
at least three quarters full. The tare weight is used to calculate the maximum payload the truck
or tractor/trailer is permitted to legally haul according to its axle size. DOTD Engineering
Directives and Standards (EDSM) Number III.1.1.12 outlines the Enforcement of Legal Load
Requirements on Construction and Maintenance Construction Projects (See LA DOTD
website.). A sample copy of the DOTD truck (and trailer, if applicable) Weight Certification Tag
is shown in the Appendix.
Transport and roadway paving equipment shall perform to the satisfaction of the Project
Engineer. If equipment fails to perform satisfactorily or is not maintained in acceptable
condition the Inspector is to notify the Project Engineer. If an equipment malfunction is
detrimental to the project, the roadway Inspector has the authority to require the removal of
the equipment.
Inspection of Plant and Roadway Equipment
The ADI and the Certified Paving Inspector are the official representatives of the Department
through the authority of the DLE and Project Engineer, respectively.
The concept of applying a payment adjustment to certain acceptance tests does not imply that
the role of the DOTD Inspector is limited to performing or monitoring these tests. Increased
dependence on Contractor/Producer quality control programs has extended the need for
DOTD inspectors to be knowledgeable and vigilant concerning the design, production,
transport, placement and compaction of hot-mix asphalt materials. It is intended that all
requirements of the specifications shall be adhered to, not merely those to which payment
adjustments are applied.
If problems arise in the production, transport or paving operations, it is the Inspector’s
responsibility to notify the Contractor/Producer’s representatives that the product is not
meeting Department standards. The DOTD Inspector will tell the Contractor/Producer what is
wrong, however, the inspector will not under no circumstances order a solution to the
problem by word or action. Correcting the problem so that the product meets all
requirements of the specifications is the responsibility of the Contractor/Producer. If corrective
actions are not made, the Inspector is to notify the Project Engineer and DLE and make a
subsequent investigation to ensure that corrective action has been taken. The Inspector will
document all actions, discussions with other Department personnel and Contractor/Producer
NOTE:
The Contractor will not be allowed to certify more than
3 tractor and trailer combinations
SECTION 503 – PLANTS & EQUIPMENT
112
personnel, any other information relevant to the situation and will take measurements or
samples, as necessary, to identify the problem.
When deficiencies occur in any area of the production, transport or paving processes, the
Contractor/Producer must take immediate action to correct the problem. Failure to do so can
result in the discontinuance of operations for DOTD projects. Quality control shall be
accomplished by a program independent of, but correlated with, the Department’s acceptance
testing and shall verify that all requirements of the JMF are being achieved, and that necessary
adjustments provide specification compliance. It is the intent of the specifications that mixtures
provided meet 100% for all production. Whenever the mixture produced falls into areas under
which payment adjustment schedules must be applied, the Contractor/Producer shall make
immediate adjustments or the DOTD Inspector will require the discontinuance of operations
for DOTD projects.
Plant Inspection
The Department’s ADI must continually observe the entire manufacturing process when at the
plant. The Inspector is to make a minimum of once per quarter inspection of the plant to ensure
that it is in conformance with the standards under which certification was granted. The
Inspector must be familiar with Section 503 of the Standard Specifications, Asphalt Concrete
Equipment and Processes, and the certification standards for plants. It is also the Inspector’s
responsibility to observe the Contractor/Producer’s testing, monitor the results, and perform
any sampling and testing operations assigned to Department personnel. The plant equipment
and operations are to be inspected continually during production to ensure that no malfunctions
have occurred that will have a detrimental effect on the mixture.
The following headings indicate areas of the plant in which routine inspection is considered
essential. These lists are not intended to be comprehensive or to exclude other areas from
regular inspection. They are merely intended to serve as a guide to the Inspector in the
performance of this responsibility.
Plant Equipment
Stockpiles and HandlingAny new materials delivered to the plant are to be inspected,
sampled, and tested in a timely manner so that production is not disrupted.
Aggregates must be handled in a manner that will not be detrimental to the final mixture.
Stockpiles shall be built without causing segregation. Segregation can be minimized if
stockpiles are constructed in successive layers, not in a conical shape. Stockpiles shall be
located on a clean, stable, well-drained surface to ensure uniform moisture content throughout
the stockpile. The area in which the stockpiles are located shall be large enough for the
stockpiles to be separated, so that no intermixing of materials will occur. Stockpiles shall not
become contaminated with deleterious materials such as clay balls, leaves, sticks or non-
specification aggregates.
SECTION 503 – PLANTS & EQUIPMENT
113
Material ProportioningAll materials used, such as aggregates, asphalt cement, mineral
filler, hydrated lime, fibers, and RAP shall be proportioned by fully integrated measuring
systems that maintain the required proportions in conformance with the approved mix design.
Cold BinsCold feed apparatus shall conform to Subsection 503.03.2 and shall be inspected
routinely. Bins shall be of the proper size to accommodate loader bucket size and plant
production. They shall also be of a configuration that will not contribute to segregation and be
in good condition. There shall be no holes in any bin. The bin separating partitions shall not
be worn or broken. If a partition is damaged to the point that this specification is not met, the
Contractor/Producer shall replace the damaged part. Cold feed bins shall be loaded in a
manner that will not contribute to segregation. Aggregates shall be dumped into the center of
each bin. Bins shall be kept adequately filled with a relatively constant level of material with
uniform moisture content.
Belt feeders shall be in good condition, not worn or broken. Gate openings and belt speeds
shall be set to distribute the appropriate gradation for the job mix formula being produced. The
gate openings and belt speeds shall be periodically inspected to ensure that they remain
properly set. Aggregates shall flow uniformly onto the belt. Clogged gates, bridging or
excessive moisture can cause non-uniform flow.
Truck LoadingThe loading of trucks will be observed to ensure that loading techniques or
discharge equipment is not contributing to mixture segregation. Equipment that drops a large
amount of mixture at a time into the truck will tend to generate less segregation than compared
to equipment that discharges a small flow/stream. The material dropped into the front and
back should be placed as close as possible to the front and back of the bed to minimize
segregation caused by the rolling of large aggregates. The intent of this truck loading
procedure is to minimize the roll down of coarse aggregate at the front and back of the truck
and to concentrate any roll down in the center of the load, where it will be more readily mixed
with the mass of material during discharge into the paver or MTV. When equipment
necessitates deviating from this procedure, the Producer may modify this procedure as long
as segregation does not occur.
Drum mix plants will be checked for satisfactory performance by inspecting the material
exiting the drum mixer. It will be checked for temperature, coating [Ross Count, (AASHTO T
195), if questionable], moisture, and segregation. If segregation is occurring during the mixing
process, one side of the material coming out of the dryer/drum will usually be fine and the other
coarse. Such segregation is often caused by improper drum operation.
Material produced at the beginning or termination of production periods shall be diverted
from DOTD projects. During startup, the Contractor shall observe the mixture coming out of
the diversion chute during these periods to determine that proper mixing and coating are being
achieved before allowing the asphalt mixture to enter the surge or storage silos.
The surge or storage silos in use at all plants are components that must be carefully and
routinely inspected. The batcher on the top of the silo must operate properly and at all times.
The gates must close tightly so that material cannot dribble through. The storage silo or surge
silo should maintain the proper cone shape of the material in storage to reduce the height of
mix drop, thereby helping to prevent segregation.
SECTION 503 – PLANTS & EQUIPMENT
114
On a quarterly basis, when the plant is in production, the ADI will, as a part of continuous
quality assurance efforts, inspect the plant and its individual components. Section 503 (Asphalt
Concrete Equipment and Process) outlines requirements for the inspection of the following
items:
Asphalt cement tanks (storage and working)
Anti-strip additive equipment
Cold aggregate feeders (bins)
Hydrated lime/mineral filler equipment (if used)
Screening systems
Dryer/drums
Thermometers (including thermocouples)
Dust collection systems (baghouses)
Asphalt measuring equipment
Weigh hoppers (if used)
Scales and printer systems
Storage and Surge silos
Mix Release agent dispenser systems
Not only shall proper functioning of these individual components be inspected, their combined
operation is to be continually monitored for proper quality assurance.
SECTION 503 – PLANTS & EQUIPMENT
115
Inspection of Mixture at Plant
Temperature of the Asphalt MixtureThe temperature is to be checked a minimum of 2
trucks per lot by the Contractor and reported in the DOTD tracking software. For each
temperature determination, the temperature shall be checked in more than one location per
truck.
SegregationAsphalt mixtures that exhibit obvious segregation when loaded at the plant shall
not be issued a haul ticket. The material shall not be transported to a DOTD project. If there
is plant segregation, the loading procedure, stockpile construction, cold feed bin operation,
mixing process, and surge/storage bin operations should immediately be inspected for proper
function.
UniformityThe asphalt mixture should be uniform in appearance in all aspects from batch to
batch and from one area of the truckload to another. There should be no lumps, areas of
differing color, segregation or wet/dry areas. Inconsistent color throughout a truckload may
also be the result of excessive dryer/drum flight wear, low or excessive asphalt cement content
or inadequate drying/heating. If the mixture does not exhibit acceptable uniform color, the
Contractor is to identify and correct the problem.
OdorBurned or unusual odor may be indicative of oxidized asphalt cement.
Asphalt CoatingAsphalt mixtures that exhibits obvious coating deficiencies shall not be
transported to a DOTD project. If the Certified Technician suspects that the mixture is
improperly coated, A Ross Count may (AASHTO T 195) be performed. Reference section
502.11 of the Standard Specifications.
MoistureExcess moisture in asphalt mixtures may cause the mixture to appear to have
excessive asphalt cement. Hence, the material will appear to be wet and shiny and slump in
the truck. This is because, prior to moisture evaporation, the saturated steam is acting like
excess asphalt cement. If the Certified Inspector(s) suspects moisture problems, then the
asphalt mixture shall be analyzed for moisture content (DOTD TR 319). The maximum
moisture content allowed by specifications is 0.3%.
SECTION 503 – PLANTS & EQUIPMENT
116
Haul Ticket
All truckloads of asphalt mix shall be accompanied by a properly completed haul ticket. Haul
tickets show the exact quantity, by weight, of material in the haul truck. This quantity, in tons,
is used to determine pay. No material shall be placed from a truck without a properly completed
haul ticket.
The Lot number shall be indicated on each haul ticket. The Lot number may be either
printed on the ticket via the printer system or written on the DOTD stamped form on the back
of the ticket.
The Contractor shall keep a running total of production to ensure that all lots are terminated at
proper tonnage and that the succeeding lot number is placed on the next haul ticket. Lot
numbers will be assigned based on the next sequential lot number. Lot numbers will be
sequential to plant production for DOTD without regard to delivery points, individual projects,
or mix types.
The Contractor shall also maintain a log of the distribution of hot-mix production for DOTD
projects from a plant’s operation. This log shall contain, as a minimum, the following data:
Date
State project mix shipped to
Sequential lot number
Tons shipped
Accumulated tons of the lot
Remarks
Initials of the technician making the entry
AC type
This log is to remain at the plant as a continuing record of plant production and distribution. It
is to be maintained separately from all other Department documentation.
Roadway Equipment
Haul TrucksTrucks are to be routinely inspected to ensure they are clean and that there are
no holes in the trailer/truck beds with the exception of a ¼” hole midway of the dump body on
the driver’s side for thermometer insertion to check mix temperature. Materials shall not be
allowed to build up in truck beds. Truck beds must be coated with an approved mix release
agent, as needed. Diesel or any other petroleum-based product shall not be used as a mix
release agent. Each truck shall have an adequate cover and tie downs. The cover must be in
good condition with no holes or tears and must cover the complete bed. Covers shall be used
to protect the material from rain and excessive temperature loss. All haul trucks shall have
silver weight certification stickers attached to the cab and the trailer unit. These two stickers
must match to be valid. If the weight certification stickers are not valid, the haul truck shall be
removed from the project.
PaversThe paver shall be operated at a consistent speed that will produce a smooth,
uniformly textured pavement surface and create a continuous operation in conjunction with
plant production and hauling capacity. Use a paver insert hopper in conjunction with the MTV
SECTION 503 – PLANTS & EQUIPMENT
117
with a minimum capacity of 5 tons. The hopper is to be kept reasonably full at all times; the
slat conveyors should never be uncovered. Cold, segregated material in the hopper wings
shall not be dumped into the paver. The paving Inspector will check the sensitivity of the
paver’s electronic controls to ensure they are working properly.
If screed extensions are used, they must be heated and meet all screed requirements and
produce the same quality surface as the screed. When auger extensions are required, they
must extend to within 1 ft. of the end of the screed. With approval, the use of an auger
extension with screed extensions in excess of 1 ft. on one side may be waived for transitions,
taper sections and similar short sections or when hydraulically extended screeds, which trail
the main screed assembly, are used, provided required density and surface texture are
obtained.
MTVThe MTV shall comply with Section 503.14 of the Standard Specifications. If Lightweight
MTV (503.14.1) and/or Windrow Paving (503.14.2) are used, then a Thermal Profile System
(503.14.3) will be required to be attached to the paver. The DOTD Inspector will check for
thermal segregation of the mix. If thermal segregation is found, the operation should be
discontinued and changes made to allow continuation of the laydown operation.
Asphalt DistributorThe Asphalt Distributor shall comply with Section 503.13 of the Standard
Specifications. The Inspector should check to ensure that the Distributor meets the
requirements in Section 503.13.1 and note this on the Asphalt Concrete Paving Equipment
Project Approval form.
Within 12 months prior to use, calibrate the asphalt distributor in accordance with ASTM
D2995. Provide the ASTM calibration record to the Project Engineer prior to beginning work.
At any time, the Engineer may require verification of calibration accuracy of the asphalt
distributor in accordance with ASTM D 2995.
RollersIt is critical to the life of an asphalt pavement that it be properly compacted to develop
the strength and proper aggregate interlock intended for the mixture. Sufficient compactive
energy should be applied as necessary for adequate design density. A properly compacted
pavement will provide a smooth, sealed riding surface.
A best practice is for the breakdown roller to follow closely behind the paver.
It is the Contractor’s responsibility to establish a rolling pattern that will ensure optimum and
consistent density. Almost every project or mixture type requires a varied rolling pattern. The
ability of a mixture to be compacted will be affected by variables such as mixture temperature,
aggregate gradation, type of aggregate and asphalt, ambient temperature, moisture content,
and condition of the foundation on which the asphalt mixture is being placed and compacted.
Section 503.16 of the Standard Specifications states that all compaction equipment must be
self-propelled and be capable of reversing without backlash. It is the Contractor’s responsibility
to provide the number, type and size of rollers sufficient to compact the mixture to the specified
density and surface smoothness. The Contractor shall establish the number, type, size and
rolling pattern on the first day of production for a particular mix design. Once established, the
same protocol shall be maintained throughout production. If the pavement or mixture
characteristics are changed during the project, the Project Engineer may require a revised
SECTION 503 – PLANTS & EQUIPMENT
118
protocol deemed appropriate for those changes. Compaction equipment shall comply in
accordance with Subsection 503.16.
Steel wheel rollers may be either vibratory or non-vibratory. The wheels shall be true to round
and equipped with suitable scraper and watering devices. If used, vibratory rollers shall be
designed for asphalt mixture compaction and shall have separate controls for
frequency, amplitude and forward speed. Non-vibrating steel wheel rollers shall be
operated with drive wheels toward the paver. Vibratory rollers shall not be used on the first lift
of asphalt pavement placed over asphalt treated drainage blanket. When asphalt mix is placed
on newly constructed cement or lime stabilized or treated layers, vibratory rollers shall not be
used for at least 5 days after such stabilization or treatment. Steel wheels shall be checked
for flat spots.
Drawbar Pull is defined as the horizontal force required to move the roller forward. The most
efficient roller is that with the smallest drawbar pull. Rollers with large diameter drums have
lower drawbar pull (rolling resistance), because they do not penetrate as far into the mix to
develop a contact area as a roller with smaller diameter drums.
All tires for pneumatic tire rollers shall have smooth tread, shall be the same size and ply rating,
and shall be inflated to a uniform pressure not varying more than ±5 psi between tires. Wheels
shall not wobble and shall be aligned so that tires of the other axle cover gaps between tires
on one axle. Tires shall be equipped with scrapers to prevent adhesion to the asphalt mix.
The pneumatic tire roller shall be kept 6 in from unsupported edges of the paving strip;
however, when an adjacent paving strip is down, the roller shall overlap the adjacent paving
strip approximately 6 in. All scrapers and watering systems shall be in good condition and
functioning properly.
Rollers shall be operated at uniform speeds that will coordinate with paver speed and within
the frequency setting so as to allow for proper drum impacts per linear foot. The more quickly
a roller passes over a particular point in the new asphalt pavement surface, the less time the
weight of the roller rests on that point. This in turn means that less compactive effort is applied
to the mixture. As roller speed increases, the amount of density gain achieved with each roller
pass decreases. The roller speed selected is dependent on a combination of the following
factors:
Paver speed
Layer thickness
Position of the roller in the roller train.
Typically static steel wheel rollers can operate at speeds of 2 to 5 miles per hour; pneumatic
tire rollers typically run 2 to 7 miles per hour; a vibratory roller can operate at speeds of 2 to
miles per hour. Roller speed is also governed by the lateral displacement or tenderness
of the asphalt mix. If the mixture moves excessively under the roller, the speed of the
compaction equipment should be reduced. As discussed earlier, roller speed affects the
impact spacing for vibratory rollers. This spacing is important for controlling the amount of
dynamic compaction energy applied to the pavement, as well as for obtaining the proper
surface smoothness. In general, at least 10 to 12 impacts per foot are needed to obtain
adequate density and layer smoothness.
SECTION 503 – PLANTS & EQUIPMENT
119
Rollers are not to reverse in the same location on subsequent passes. Reversal points of
continuous passes should be skewed at an angle of approximately 45 degrees across the mat.
Rollers should cross their reversal points when moving across the mat surface in order to
smooth any dips or bumps caused by changing direction. When a vibratory roller is used for
breakdown rolling, the vibrators must be turned off to compact joints or whenever the roller
stops or changes direction.
The Paving Inspector will inspect the mat during compaction after the rollers have passed. If
the mat tears, blisters, shoves, leaves indelible marks or displaces in any way beneath the
roller, the Paving Inspector will require the Contractor to adjust the operation so that the mat
is not damaged. Deficiencies shall be corrected.
Rollers for SMA shall be steel wheel weighing a minimum of 10 tons operated at high frequency
and low amplitude. SMA mix shall be rolled immediately after placement. The mastic shall
not be allowed to migrate to the surface. Rolling shall continue until all roller marks are
eliminated and minimum density is obtained, but not after the mat has cooled below 220°F.
Traffic will not be allowed on the newly compacted SMA until the mat has cooled to 140°F or
lower.
Tender ZoneA mid-temperature tender zone has been identified for some Superpave mixes.
The tender zone has been identified in temperature ranges of approximately 200°F to 240°F.
The mixture can be satisfactorily compacted above this range or below this range, but the
mixture is tender within the temperature range and cannot be adequately compacted. This is
not true for all mixtures, but it has been observed for some Superpave designed mixtures.
When a mixture is tender within the mid-temperature range, the preferred compaction method
is to obtain density prior to cooling to the point of the tender zone. This may require an
additional breakdown roller or other changes in rolling techniques, but obtaining density prior
to reaching the tender zone is preferable. In some cases, the mixture temperature may be
increased slightly to provide more compaction time. However, excessive temperatures will
magnify the problem. Another alternative is to use a vibratory steel wheel breakdown roller
above the tender zone, followed by a rubber tire roller, which can be operated in the tender
zone. The finish roller should be used after the mixture has cooled below the tender zone.
This second method may not be satisfactory if the rubber tire roller picks up excessively.
Another possibility is to breakdown with a steel wheel roller above the tender zone, then
complete the rolling process after the asphalt mixture has cooled to below the tender zone.
This has been used on a number of projects, but problems may occur due to differential cooling
of the mixture and due to excessive aggregate breakdown when rolling in the vibratory mode
after the mixture has cooled to below 200°F. Therefore, vibratory rolling should not be used
below 200°F.
If the tenderness problem yields a pavement with poor in-place density, or if the paving train
length is excessively long due to the time required for the mixture to cool, adjustments to the
mixture design must be made to eliminate, or at least reduce, the temperature tenderness
zone. It is important that the paving crew working at the laydown site communicate with the
plant personnel.
SECTION 503 – PLANTS & EQUIPMENT
120
Surface PreparationThe requirement to use tack coat, prime coat or curing membrane
depends on the type of surface material upon which it is being placed. The different types of
asphalt materials, along with their applicable sections in the Standard Specifications, are as
follows:
1. Tack Coat - (Section 504) is applied to existing hot-mix asphalt, Asphalt Surface
Treatment, or Portland cement concrete pavement surface. The distributor used to
apply the tack coat shall be certified.
2. Prime Coat (Section 505), is applied to untreated base course such as crushed
aggregate, stone and concrete base courses. The distributor that is used to apply
the prime coat shall be certified.
Curing Membrane (Section 506), is applied to treated base courses such as on
the surface of cement or lime-treated/stabilized materials. The distributor used to
apply the curing membrane does not have to be certified, but shall be approved by
the Engineer.
SECTION 504 - TACK
121
Section 504 – Asphalt Tack Coats
Record the temperature of the tack truck for information. Tack coat rate and quantity as
measured by the calibrated tack coat distributer will be recorded and used for verification.
Shipments of tack coat emulsion must be accompanied with a Certificate of Delivery collected
by the Contractor and then delivered to the DOTD Inspector.
If the tack coat distributer has to leave the project, the operator shall inform the DOTD
Inspector. The DOTD Inspector will take a gallons reading of the distributor for verification
calculations. If the distributor has to refill, the Inspector will take a reading upon the return of
the distributor. The quantity reading will be from calibrated measuring devices for the
distributer being measured.
Within 12 months prior to use, calibrate the asphalt distributor in accordance with ASTM D
2995. Provide the ASTM calibration record to the Project Engineer prior to beginning work. At
any time, the Engineer may require verification of calibration accuracy of the asphalt distributor
in accordance with ASTM D 2995.
Measurement will be by the in place gallon per square yard. The DOTD Certified Paving
Inspector will compute the square yards covered and gallons placed to calculate application
rates.
Tack coat will not be paid for separately but will be incidental to asphalt mixtures.
When questionable, tack coat will be sampled in plastic one-gallon containers as stated in the
sampling plan or MSM.
If the Engineer adjusts the application rate of tack coat from that specified by the contract
document or Standard Specifications, payment for asphalt mixture will be increased or
decreased based on the difference in applied quantity of asphalt emulsion shown on paid
invoices (total charges). The contractor shall provide copies of paid invoices for this
determination.
Application Rate Calculation
Application rate is based on gallons per square yard and is indicated in the equation following:


= application rate
yd
2
= area covered = length in feet x width in feet ÷ 9
Example: Station 10+00 to 56+80 = 4680 ft. length, paving width = 12.5 ft.
Area Covered = 4680 ft. x 12.5 ft. ÷ 9 ft.
2
/sq yd = 58500 ft
2
÷ 9 ft.
2
/sq yd = 6500 yd
2
260 gallons of tack used as measured from Tack Distributor
SECTION 503 – PLANTS & EQUIPMENT
122


= 0.04 gal/yd
2
application rate
APPENDIX
APPENDIX
A-2
For move to appendices:
Mineral aggregate is porous and can absorb water and asphalt to a variable degree.
The ratio of water to asphalt absorption varies with each aggregate. Three methods
of measuring aggregate specific gravity consider these variations. The methods are
bulk, apparent, and effective specific gravities. Differences among the specific
gravities come from the different definitions of aggregate volume. The Department,
for use when analyzing and documenting Superpave hot-mix asphalt mixtures, adopts
the following definitions and nomenclature:
Figure 2-3 Illustrating Bulk, Effective, and Apparent Specific Gravities, Air
Voids, and Effective Asphalt Content in Compacted Asphalt Paving Mixture
Bulk Specific Gravity, G
sb
The ratio of the weight in air of a unit volume of a
permeable material (including both permeable and impermeable voids normal for the
material) at a stated temperature to the weight in air of equal density of an equal
volume of gas-free distilled water at a stated temperature. See Figure 2-3.
Apparent Specific Gravity, G
sa
The ratio of the weight in air of a unit volume on
an impermeable material at a stated temperature to the weight in air of equal density
of an equal volume of gas-free distilled water at a stated temperature. See Figure 2-
3.
Effective Specific Gravity, G
se
The ratio of the weight in air of a unit volume of a
permeable material (excluding voids permeable to asphalt) at a stated temperature to
the weight in air of equal density of an equal volume of gas-free distilled water at a
stated temperature. See Figure 2-3.
APPENDIX
A-3
Voids in Mineral Aggregate, VMA The volume of inter-granular void space
between the aggregate particles of a compacted paving mixture including air voids
and effective asphalt content, expressed as a percent of total sample volume. See
Figure 2-4.
Air Voids, V
a
The total volume of the small pockets of air between the coated
aggregate particles throughout a compacted paving mixture, expressed as a
percentage of the bulk volume of the compacted paving mixture. See Figure 2-4.
Voids Filled with Asphalt, VFA The portion of the volume of inter-granular void
space between the aggregate particles (VMA) occupied by the effective asphalt. See
Figure 2-4.
Effective Asphalt Content, P
be
The total asphalt content of a paving mixture minus
the portion of asphalt lost by absorption into the aggregate particles. See Figure 2-4.
Absorbed Asphalt, P
ba
The absorbed asphalt, percent by mass of aggregate. See
Figure 2-4.
When evaluating a JMF, the Apparent Gravity is greater than the Effective Gravity is
greater than the Bulk Gravity of the aggregates.
G
sa
> G
se
> G
sb
Asphalt absorption generally falls somewhere in the middle two thirds of water
absorption. If asphalt absorption approaches zero or a negative asphalt absorption
(mix makes asphalt) is indicated, the gravity and absorption of the aggregates needs
to be reviewed.
Due to the washing of fine aggregates over the 200 sieve for T 84, large aggregate
mixes and mixes not containing RAP (SMA), may approach zero absorption. JMFs
submitted with negative asphalt absorptions shall not be approved.
JMFs with low composite absorption values, using low water absorption aggregates,
are more sensitive to the asphalt aborption to water absorption ratio than higher water
absorption composites.
APPENDIX
A-4
Figure 2-4 Representation of Volumes in a Compacted Asphalt Specimen
(Phase Diagram)
Asphalt Cement Specific Gravity, G
b
The ratio of the mass in air of a given volume
of asphalt cement to the mass of an equal volume of water, both at the same
temperature. (Assumed to be 1.03)
Mixture Bulk Specific Gravity, G
mb
The ratio of the mass in air of a given volume
of compacted asphalt mixture to the mass of an equal volume of water, both at the
same temperature.
Theoretical Maximum Specific Gravity, G
mm
(Rice Gravity) The ratio of the mass
of a given volume of asphalt mixture with no air voids to the mass of an equal volume
of water, both at the same temperature.
Initial Number of Gyrations, N
initial
The number of gyrations (7 gyrations) that
represents a measure of mixture compactability. Mixtures that compact too quickly
may be tender during construction and unstable when subjected to traffic.
Design Number of Gyrations, N
design
The number of gyrations required to produce
a density in the mix equivalent to the expected density in the field after traffic. In the
mix design process, an asphalt content is selected that will provide 3.5% air voids
when the mix is compacted to N
design
gyrations.
Maximum Number of Gyrations, N
max
The number of gyrations required to
produce a density in the laboratory that should never be exceeded in the field. N
design
provides an estimate of ultimate field density. N
max
provides a compacted density with
some safety factor to ensure the mixture does not densify too much, which would
result in low in-place air voids, which can cause rutting. The air voids at N
max
are
required to be at least 2%. Mixtures that have less than 2% air voids at N
max
are
susceptible to possible rutting.
APPENDIX
A-5
The VMA values for compacted asphalt paving mixtures are calculated using
the G
sb
of the combined aggregate.
VMA and air voids (V
a
) are expressed as percentage by volume of the paving mixture.
VFA is the percentage of VMA filled by the effective asphalt cement, (P
be
). The
effective asphalt cement content shall be expressed as a percentage by weight of the
total weight of the mixture.
The following equations are used to compute volumetric properties of compacted hot-
mix asphalt specimens:
Bulk Specific Gravity of Compacted Asphalt Mixture Specimen G
mb
:
Water in WeightWeight SSD
Airin Weight
G
mb
Air Voids, V
a
:
mm
mbmm
a
G
G-G
x100V
Voids in Mineral Aggregate, VMA:
sb
smb
G
PG
100VMA
Voids Filled with Asphalt, VFA:
VMA
VVMA
100VFA
a
Effective Specific Gravity, G
se
:
b
b
mm
b
se
G
P
G
100
P100
G
APPENDIX
A-6
Percent Absorbed Asphalt, P
ba
:
sesb
sbseb
ba
GG
GGG100
P
Percent Effective Asphalt Cement, P
be
:
100
PxP
PP
sba
bbe
Dust to Asphalt Ratio, D/P or P
200
/P
be
:
be
200
P
P
Ratio Dust
Asphalt mixture volumetric analysis results for trial blends shall be documented in
LaPave.
The following relationships, as determined from these equations, are plotted in
LaPave to show the Optimum Asphalt Cement Content - Summary of Test Properties.
1. Air Void (V
a
) versus asphalt content
2. Voids in Mineral Aggregate (VMA) versus asphalt content
3. Voids Filled with Asphalt (VFA) versus asphalt content
Selection of Optimum Asphalt Cement Content
Examining test property curves reveals information about sensitivity of the mixture to
asphalt content. Trends generally noted are:
Percent Air Voids (V
a
) decreases with increasing asphalt cement content,
ultimately approaching a minimum void content.
Percent VMA generally decreases to a minimum value then increases with
increasing asphalt cement content.
Percent VFA steadily increase with increasing asphalt cement content
because VMA is being filled with asphalt cement.
Dust to Effective Asphalt Cement Ratio Evaluation
Another mixture requirement, as per Tables 502-6 and 502-6b, is the dust ratio.
Computed as the ratio of the percentage by weight of aggregate finer than the No.
APPENDIX
A-7
200 sieve to effective asphalt content (P
be
) expressed as a percentage by weight of
total mixture. Effective asphalt content is the total asphalt used in the mixture less
the percentage of absorbed asphalt.
Dust to Asphalt Ratio, D/P or P
200
/P
be
:
be
200
P
P
Ratio Dust
The dust ratio, P
200
/P
be
, tolerance for all 502 asphalt mixtures is 0.6 to 1.6 unless
otherwise stated.
Moisture Susceptibility Analysis
Subsection 502.02.2.1 requires that a minimum of 0.6% anti-strip be used or a rate
approved by the DLE.
Loaded Wheel Tester, LWT Testing
Perform (AASHTO T 312) Preparing and Determining the Density of Asphalt
Specimens by Means of the Superpave Gyratory Compactor and (AASHTO T 324)
Hamburg Wheel-Track Testing of Compacted Hot Mix Asphalt (LWT) tests.
Specimens shall be prepared and tested according to T 312 and T 324. Testing
tolerances are listed in Tables 502-6 and 502-6b of the Standard Specifications.
Report values will be included in the LaPave JMF submittal. The LWT Excel file data
shall be submitted to the Department with the JMF submittal.
LWT testing of plant produced mix is required to complete the JMF validation process.
If LWT testing was used for minor mix submittal, LWT testing will be done on plant
produced mix when the JMF starts production.
4 60mm gyratory specimens are used for LWT.
Semi Circular Bend Test (SCB)
Perform according to ASTM D8044. The Contractor shall perform SCB testing for
design. SCB test for design submittal may be witnessed by a DOTD employee at the
request of the DLE. The Contractor will coordinate with the DLE for an employee to
be present for testing. The Contractor will submit the required Excel data file with the
JMF proposal.
SCB will not be required for base, PG67-22 leveling or minor mixes. Any mix that is
under traffic will be subject to SCB testing.
1” binders used on mainline require SCB testing.
Mixes using polymer asphalt binders are subject to SCB testing (including
leveling with PG70-22 and PG76-22)
APPENDIX
A-8
Perform long term aging of SCB samples in accordance to AASHTO R 30, 7.3.4 (85
± 3°C for 120 ± 0.5 h), 7.3.5, and 7.3.6.
Laboratory testing temperature for SCB specimens is 25° C.
Upon request by DOTD, the contractor will be required to perform SCB testing on
plant produced mix.
Tensile Strength Ratio, (TSR), (Lottman) (Minor Mixes) (Optional)
To complete the design process for minor mixes, at the Contractor’s option , in lieu
of LWT, may perform moisture sensitivity test (DOTD TR 322) to evaluate the
proposed hot-mix asphalt blend for stripping. This test identifies whether a
combination of asphalt cement and aggregate is moisture susceptible.
Report results in LaPave and submit with the JMF proposal. Minimum TSR results of
80% are required for approval of a design. TSR testing is required on the first lot of
plant produced mix once a JMF is approved. TSR results are entered in LaPave.
Alternate Method for Calculating Roadway Yield Correction Factors
Calculating an adjustment factor for high void mixes (OGFC) and/or low G
mm
(Rice Gravity) mixes
OGFC and sometimes SMA and 501 Coarse Mix do not follow typical yield.
Below are two methods of calculating theoretical yield factors.
Yield correction factor
PCF = Pounds per cubic foot
PCF = G
mm
(Rice Gravity) from plant x 62.4 (weight of one cubic foot of water)


 
Volume of lift x PCF = weight of mix in pounds at zero voids.
Weight of mix in pounds at zero voids x inverse of design voids = adjusted yield
(pounds per square yard)
Example for OGFC:
OGFC design voids = 20% 0.80 (inverse of design voids) will be used in calculating
the adjusted yield.
Lift thickness = 0.75”
G
mm
= 2.400
PCF = 2.400 x 62.4
PCF = 149.76
APPENDIX
A-9


  ft
3
. This is the volume of one square yard of OGFC at 0.75” lift
thickness
Weight of mix at zero percent voids = 149.76 x 0.5625 = 84.24 pounds per square
yard
Weight per square yard using design voids 84.24 x 0.80 = 67.392 pounds per
square yard at 0.75 lift thickness.
High AC content mixes such as SMA may need an adjustment factor for
calculating yield.
Calculating a roadway yield “adjustment factor” for high AC content and/or low
G
mm
(Rice Gravity) mixes such as SMA
Yield correction factor
PCF = Pounds per cubic foot
PCF = G
mm
(Rice Gravity) from plant x 62.4 (weight of one cubic foot of water)


 
Volume of lift x PCF = weight of mix in pounds at zero voids.
Weight of mix in pounds at zero voids x average roadway core density = adjusted
yield (pounds per square yard)
Example for SMA:
Average SMA roadway core density = 95% 0.95 will be used in calculating the
adjusted yield.
Lift thickness = 2.00”
G
mm
= 2.395
PCF = 2.395 x 62.4
PCF = 149.45


  ft
3
. This is the volume of one square yard of SMA at 2.00” lift
thickness
Weight of mix at zero percent voids = 149.49 x 1.499 = 224.09 pounds per square
yard
Weight per square yard using average density of roadway cores from validation or
previous production lot.
224.09 x 0.95 = 212.9 pounds per square yard at 2.00” lift thickness.
106.5 lbs per inch per square yard.
APPENDIX
A-10
Example of core sampling determination
when there are different mix uses in the same sublot.
Assume lot has 5000 tons of continuous mixture production.
Sublot A
800 Tons
Roadway
Wearing
Sublot B
500 Tons
Roadway
Binder
Sublot C
200 Tons
Rdwy
Wear
Sublot D
600 Tons
Roadway
Wearing
Sublot E
1000 Tons
Driveways
3
800 Tons
Shoulder
500 Tons
Roadway
Wearing
400 Tons
Shoulder
200 Tons
Shoulder
Using random number tables, core locations may occur as follows (select mainline if
there are mixed uses in the sublot):
800 Tons
Roadway
Wearing
2
acceptance
cores
2 QC cores
500 Tons
Roadway
Binder
1
acceptance
& 1 QC Core
200 Tons
Rdwy
Wearing
1
acceptance
& 1 QC Core
2
600 Tons
Roadway
Wearing
2
acceptance
& 2 QC
cores
1000 Tons
Driveways
0 cores
800 Tons
Shoulder
1
acceptance
& 1 QC
cores
500 Tons
Roadway
Wearing
1
acceptance
& 1 QC core
400 Tons
Shoulder
0 cores
(from
random
number
results)
1
acceptance
core & 1 QC
core
1
200 Tons
Shoulder
0 cores
(from
random
number
results)
1
acceptance
core & 1 QC
core
1
1
Sublot A Shoulder is a mix use that is not represented, so take an additional
acceptance and additional QC core from the shoulder
2
Sublot C Choose wearing for first segment location and choose shoulder for
second segment location.
APPENDIX
A-11
Sublots B, D and E All mix uses are represented.
3
Sublot E compaction shall be to the satisfaction of the Project Engineer (100%
pay).
For projects greater than >1000 current plan ADT:
Mainline core density results are used to calculate PWL for pay. Minor core density
results are used to calculate average density for pay.
Mainline mix use requires a minimum of three cores for lots >250 tons to calculate
PWL.
For projects ≤ 1000 current plan ADT:
Mainline mix pay may be calculated by averaging or by PWL, as designated in the
preconstruction conference. When averaging is chosen, the average of each sublot
will be used to determine pay. The average core density per sublot is 92.0% with an
individual minimum core density of 90.5
Example PWL Calculation
Assume 5 samples taken from 5 consecutive sublots of continuous production of the
same mix from a plant.
5000 TONS
¾” NMS Wearing
Category B Roadway
AIR VOIDS Spec Limits are 2.5% to 4.5%.
Test results for air voids are:
2.3%
2.2%
3.0%
2.9%
3.0%
AIR VOIDS Compute PWL for 5 air voids results.
1. Compute the mean and the standard deviation. The formula used to
determine the mean is:
n
X
=
n
X
+...+
X
+
X
+
X
= X =
i
n
1=i
n321
Mean
APPENDIX
A-12
Using the example,
2.68
5
13.4
=
5
3.0
+2.9+
3.0
+
2.2
+
2.3
= X = Mean
2. Compute standard deviation. The formula to determine standard deviation
is:
1 - n
)
X-
X
(
=
1 - n
)
X -
X
(++....
)
X-
X
( +
)
X-
X
(
2
i
n
1 = i
2
i
2
2
2
1
= s = Deviation Standard
0.3962 s
0.396232 s
0.1570 s
4
0.6280
s
1 - 5
0.6280
s
1 - 5
0.1024 0.0484 0.1024 0.2304 0.1444
s
1 - 5
0.32 0.22 0.32 0.48 0.38
s
1 - 5
2.68) - (3.0 2.68) - (2.9 2.68) - (3.0 2.68) - (2.2 2.68) - (2.3
s
22222
22222
Standard Deviation = 0.3962
APPENDIX
A-13
*Software carries indefinite places for intermediate calculations. Results from
“hand” calculations and LaPave may differ.
3. Compute the Upper Quality Index, Q
u
, and Lower Quality Index, Q
L
, using
these formulas:
Example: If the Upper Spec Limit, USL, is 4.5 and the Lower Spec Limit, LSL, is 2.5, then:
0.45
0.3962
0.18
0.3962
2.5 - 2.68
=
Q
=Index Quality Lower
4.59
0.3962
1.82
0.3962
2.68 - 4.5
=
Q
=Index Quality Upper
L
U
4. Compute PWL.
Use Table 502-9 to convert the Quality Index into the PWL value. PWL is
calculated for each Quality Index (upper and lower) and combined for a total
PWL calculated in accordance with the formula:
PWL = PWL
L
+ PWL
U
- 100
Where:
PWL
L
= lower percent within limits
PWL
U
= upper percent within limits
PWL, for the five void results previously shown, calculates as follows:
From Table 502-9, using n = 5
PWL
U
corresponds to 4.59 is 100.
s
LSL - X
=
Q
=Index Quality Lower
s
X - USL
=
Q
=Index Quality Upper
LU
*NOTE: For hand calculations
When performing computations, please note that the significant digits for the
average will be one more place than the significant digits for the value. In
addition, the significant digits for the standard deviation will be two more than
the significant digits for the average. For Example:
Voids is x.x Density is xx.x
Voids Average is x.xx Density Average is xx.xx
Voids Standard Deviation is x.xxxx Density Standard Deviation is xx.xxxx
APPENDIX
A-14
PWL
L
corresponds to 0.45 is 66.
Total PWL = PWL
U
+ PWL
L
100 = 100 + 66 100 = 66
APPENDIX
A-5
Table 502-9
Quality Index Values for Estimating Percent Within Limits
(PWL)
PWL
n = 3
n = 4
n = 5 - 6
n = 7 - 9
n = 10 - 12
n = 13 - 15
99
98
97
96
95
94
93
92
91
90
89
88
87
86
85
84
83
82
81
80
79
78
77
76
75
74
73
72
71
70
69
68
67
66
65
64
63
62
61
60
59
58
57
56
55
54
53
52
51
50
1.16
1.15
1.15
1.15
1.14
1.13
1.12
1.11
1.10
1.09
1.08
1.07
1.06
1.05
1.03
1.02
1.00
0.98
0.96
0.94
0.92
0.89
0.87
0.84
0.82
0.79
0.77
0.74
0.71
0.68
0.65
0.62
0.59
0.56
0.53
0.49
0.46
0.43
0.39
0.36
0.32
0.29
0.25
0.22
0.18
0.14
0.11
0.07
0.03
0.00
1.47
1.44
1.41
1.38
1.35
1.32
1.29
1.26
1.23
1.20
1.17
1.14
1.11
1.08
1.05
1.02
0.99
0.96
0.93
0.90
0.87
0.84
0.81
0.78
0.75
0.72
0.69
0.66
0.63
0.60
0.57
0.54
0.51
0.48
0.45
0.42
0.39
0.36
0.33
0.30
0.27
0.24
0.21
0.18
0.15
0.12
0.09
0.06
0.03
0.00
1.68
1.61
1.55
1.49
1.45
1.40
1.36
1.31
1.27
1.23
1.20
1.16
1.12
1.08
1.05
1.02
0.98
0.95
0.92
0.88
0.85
0.82
0.79
0.76
0.73
0.70
0.67
0.64
0.60
0.58
0.55
0.52
0.49
0.46
0.43
0.40
0.37
0.34
0.31
0.28
0.25
0.23
0.20
0.17
0.14
0.11
0.08
0.06
0.03
0.00
1.89
1.77
1.67
1.59
1.52
1.46
1.40
1.35
1.30
1.25
1.21
1.17
1.12
1.08
1.05
1.01
0.97
0.94
0.90
0.87
0.83
0.80
0.77
0.74
0.71
0.67
0.64
0.61
0.58
0.55
0.53
0.50
0.47
0.44
0.41
0.38
0.35
0.33
0.30
0.27
0.24
0.21
0.19
0.16
0.13
0.11
0.08
0.05
0.03
0.00
2.04
1.86
1.74
1.64
1.56
1.49
1.43
1.37
1.32
1.26
1.21
1.17
1.13
1.08
1.04
1.00
0.96
0.93
0.89
0.85
0.82
0.79
0.76
0.72
0.69
0.66
0.63
0.60
0.57
0.54
0.51
0.48
0.46
0.43
0.40
0.37
0.35
0.32
0.30
0.26
0.24
0.21
0.18
0.16
0.13
0.10
0.08
0.05
0.03
0.00
2.14
1.93
1.80
1.69
1.59
1.51
1.44
1.38
1.32
1.27
1.22
1.17
1.13
1.08
1.04
1.00
0.96
0.92
0.89
0.85
0.82
0.78
0.75
0.72
0.69
0.66
0.62
0.59
0.56
0.54
0.51
0.48
0.45
0.42
0.40
0.37
0.34
0.31
0.29
0.26
0.23
0.21
0.18
0.15
0.13
0.10
0.08
0.05
0.03
0.00
Note 1: For negative values of Q
u
or Q
L
. PWL
U
or PWL
L
is equal to 100 minus the tabular PWL
U
or PWL
L.
Note 2: If the value of Q
U
or Q
L
does not correspond exactly to a value in the table, use the next higher value.
APPENDIX
A-6
Generating and Using Random Numbers for Sampling Purposes
Generating random numbers for determining sampling is covered in this section. This
section is how to generate the number(s). Applying the number is addressed in another
section.
The practice of riding a project and just picking a spot to choose a sample location may seem
random, but statistical analysis of this has proven that a pattern emerges. There are multiple
ways to utilize random numbers. One way is the use of random number tables covered here.
Statistical analysis used in this specification necessitates the use of random numbers that
are just that, random.
The following tables have groups of numbers that are 10 across and 5 down. This grouping
is used to generate random numbers.
The Inspector can generate numbers on a per lot basis or calculate the number of samples
for a project and generate all the numbers for a project. Whichever method started should
be used for the whole project.
Random numbers for longitudinal distance will be 10, along with 10 random numbers for
transverse distance for a total of 20 required random numbers per lot.
The over and down method will be used to generate random numbers in this example.
There are eight pages with seven groups of numbers per page.
The Inspector can use down and then across or across and down. The selection can start
left to right or right to left and then up or down depending on the starting point. The
limitations are 10 horizontally and five vertically. Choose a pattern and use that pattern until
all numbers are chosen or all sections are used. If more numbers are needed, pick another
pattern and proceed until enough numbers are generated.
On the first page, the pattern will be three down (vertical) and seven across (horizontal). In
each group of 50 numbers, go down three rows and across seven columns. Going down the
first page, the seven numbers generated are: 0.133, 0.954, 0.371, 0.393, 0.825, 0.416, and
0.608. The Inspector will use this pattern through the eight pages of random numbers.
Once all the pages and groups are utilized, another pattern will be used to generate numbers
if more are needed.
This pattern will be three across and five down generating 56 numbers for later use.
The following numbers were generated from the eight pages of random numbers.
1
st
page:
0.034, 0.802, 0.474, 0.652, 0.211, 0.203, and 0.522.
2
nd
page:
APPENDIX
A-7
0.649, 0.398, 0.229, 0.605, 0.811, 0.094, and 0.690
3
rd
page:
0.844, 0.701, 0.413, 0.996, 0.994, 0.810, and 0.231
4
th
page:
0.455, 0.606, 0.751, 0.658, 0.360, 0.814, and 0.073
5
th
page:
0.138, 0.573, 0.741, 0.705, 0.170, 0.792, and 0.534
6
th
page:
0.019, 0.656, 0.425, 0.031, 0.525, 0.874, and 0.099
7
th
page:
0.037, 0.185, 0.074, 0.786, 0.240, 0.355, and 0.703
8
th
page:
0.555, 0.746, 0.352, 0.251, 0.955, 0.234, and 0.645
APPENDIX
A-8
Application of Random Numbers for Roadway Core Location
The example lot will use ideal conditions of consistent yield. Each 1000 ton sublot illustrated
is 6800 feet with each section of the sublot 3400 feet.
Total lot is 5000 tons.
For simplicity, the paving width is 12 feet.
Cores cannot be within 18 inches of an unsupported edge.
Transverse core locations are measured from an established alignment (for example,
centerline or edgeline) left to right in the direction of travel.
QC cores are cut within 12 inches of the acceptance cores in the direction of travel.
Random numbers for the lot: 0.034, 0.802, 0.474, 0.652, 0.211, 0.208, 0.522, 0.649, 0.398,
0.229, 0.605, 0.811, 0.094, 0.690, 0.844, 0.701, 0.413, 0.996, 0.994, 0.810 - Alternatives:
0.231, 0.455, 0.606, 0.751
Sublot A
Section 1 of sublot A has random numbers of 0.034 and 0.802.
The longitudinal random number 0.034 multiplied by the section length of 3400 feet would
place the core 115.6 feet from the beginning of the section of the sublot at station 11+15.6
rounded to 11+16. 10+00 (beginning of section) plus 115.6 feet equals station 11+16.
The transverse location measured from the left edge is 0.802 multiplied by the lane width of
12 feet equals 9.6 feet. The transverse location should be marked to the nearest tenth of a
foot. The core would be marked at station 11+16, 9.6 feet from the left edge.
To simplify:
Paving from down station to up station
Sublot A: 10+00 78+00
Section 1: 10+00 44+00
Random #s: 0.034, 0.802
Section length 3400 feet: 3400’ x 0.034 = 115.6’
10+00 + 115.6’ = 11+15.6 = 11+16
Paving width 12 feet: 12’ x 0.802 = 9.6’ from left edge
Core location: Longitudinal = 11+16, Transverse = 9.6’ measured from left edge
Section 2: 44+00 78+00
Random #s: 0.474, 0.652
APPENDIX
A-9
Section length 3400 feet: 3400’ x 0.474 = 1611.6’
44+00 + 1611.6’ = 60+11.6 = 60+12
Paving width 12 feet: 12’ x 0.652 = 7.8’ from left edge
Core location: 60+12, 7.8’ measured from left edge
Sublot B: 78+00 146+00
Section 1: 78+00 112+00
Random #s: 0.211, 0.203
Section length 3400 feet: 3400’ x 0.211 = 717.4’
78+00 + 717.4’ = 85+17.4 = 85+17
Paving width 12 feet: 12’ x 0.203 = 2.4’ from left edge
Core location: 85+17, 2.4’ from left edge
Section 2: 112+00 146+00
Random #s: 0.522, 0.649
Section length 3400 feet: 3400’ x 0.522 = 1774.8’
112+00 + 1774.8’ = 129+74.8 = 129+75
Paving width 12 feet: 12’ x 0.649 = 7.8’ from left edge
Core location: 129+75, 7.8’ from left edge
Sublot C: 146+00 214+00
Section 1: 146+00 180+00
Random #s: 0.398, 0.229
Section length 3400 feet: 3400’ x 0.398 = 1353.2’
146+00 + 1353.2’ = 159+53.2 = 159+53
Paving width 12 feet: 12’ x 0.229 = 2.7’ from left edge
Core location: 159+53, 2.7’ from left edge
Section 2: 180+00 214+00
Random #s: 0.605, 0.811
Section length 3400 feet: 3400’ x 0.605 = 2057’
180+00 + 2057 = 200+57
APPENDIX
A-10
Paving width 12 feet: 12’ x 0.811 = 9.7’ from left edge
Core location: 200+57, 9.7’ from left edge
Paving changes to pave the travel lane in the opposite direction
Paving from up station to down station.
Subtract the distance calculated from the random number from the beginning station of the
section in the sublot.
Paving is now against the previous paving strip. The left edge is supported and the 18” rule
does not apply on the left edge.
Sublot D: 214+00 146+00
Section 1: 214+00 180+00
Random #s: 0.094, 0.690
Section length 3400 feet: 3400’ x 0.094 = 319.6’
214+00: 319.6 = 210+80.4 = 210+80
Paving width 12 feet: 12’ x 0.690 = 8.3’ from the left edge
Core location: 210+80, 8.3’ from the left edge
Section 2: 180+00 146+00
Random #s: 0.844, 0.701
Section length 3400 feet: 3400’ x 0.844 = 2869.6’
180+00 2869.6 = 151+30.4 = 151+30
Paving width 12 feet: 12’ x 0.701 = 8.4’ from left edge
Core location: 151+30, 8.4’ from left edge
Sublot E: 146+00 78+00
Section 1: 146+00 112+00
Random #s: 0.413, 0.996
Section length 3400 feet: 3400’ x 0.413 = 1404.2
146+00 1404.2 = 131+95.8 = 131+96
Paving width 12 feet: 12’ x 0.996 = 11.95 from left edge
Another random number will need to be used because this location is on the
pavement edge.
APPENDIX
A-11
The next random number from the alternates = 0.231
12’ x 0.231 = 2.8’ from left edge
Core location: 131+96, 2.8’ from left edge
Section 2: 112+00 78+00
Random #s: 0.994, 0.810
Section length 3400 feet: 3400’ x 0.994 = 3379.6’
112+00 3379.6’ = 78+20
Paving width 12 feet: 12’ x 0.810 = 9.7’ from left edge
Core location: 78+20, 9.7’ from left edge
APPENDIX
A-12
Roadway Lot Core Layout
Sublot A
Sublot B
Sublot C
Sublot D
Sublot E
Cores are shown in approximate location
Section 2 Random #s, 0.474, 0.652
Section 1 Random #s, 0.034, 0.802
Section 2 Random #s, 0.605, 0.811
Section 1 Random #s, 0.398, 0.229
Section 1 Random #s, 0.094, 0.690
Section 2 Random #s, 0.844, 0.701
Section 1 Random #s, 0.413, 0.996
Section 2 Random #s, 0.994, 0.810
Section 2 Random #s, 0.522, 0.649
Section 1 Random #s, 0.211, 0.203
44+00
112+00
180+00
78+00
10+00
146+00
78+00
146+00
214+00
214+00
180+00
146+00
146+00
112+00
78+00
cores∞
cores∞
cores∞
cores∞
cores∞
cores∞
cores∞
cores∞
cores
cores∞
APPENDIX
A-13
0.002
0.876
0.374
0.746
0.844
0.959
0.730
0.539
0.838
0.996
0.156
0.864
0.413
0.533
0.013
0.131
0.365
0.614
0.371
0.038
0.382
0.335
0.952
0.861
0.792
0.728
0.133
0.582
0.822
0.096
0.533
0.243
0.151
0.492
0.221
0.446
0.034
0.473
0.079
0.404
0.775
0.794
0.334
0.445
0.840
0.199
0.820
0.379
0.386
0.965
0.967
0.629
0.485
0.350
0.080
0.540
0.826
0.610
0.916
0.767
0.180
0.738
0.099
0.147
0.401
0.568
0.409
0.964
0.256
0.432
0.467
0.019
0.853
0.988
0.856
0.396
0.954
0.404
0.198
0.344
0.960
0.541
0.232
0.176
0.833
0.296
0.416
0.593
0.757
0.753
0.079
0.338
0.802
0.315
0.673
0.582
0.383
0.455
0.133
0.958
0.787
0.254
0.893
0.640
0.558
0.375
0.582
0.383
0.011
0.636
0.935
0.914
0.673
0.835
0.942
0.601
0.906
0.981
0.784
0.791
0.521
0.591
0.561
0.727
0.646
0.206
0.371
0.454
0.638
0.786
0.749
0.616
0.312
0.138
0.012
0.553
0.280
0.032
0.532
0.601
0.671
0.163
0.474
0.008
0.018
0.618
0.029
0.359
0.592
0.996
0.668
0.935
0.963
0.844
0.459
0.895
0.075
0.570
0.964
0.696
0.610
0.473
0.766
0.658
0.919
0.063
0.134
0.075
0.316
0.318
0.878
0.780
1.000
0.037
0.916
0.578
0.393
0.945
0.580
0.436
0.183
0.709
0.207
0.860
0.832
0.510
0.024
0.336
0.860
0.348
0.881
0.276
0.652
0.711
0.851
0.336
0.107
0.790
0.226
0.555
0.871
0.872
0.951
0.177
0.471
0.087
0.016
0.604
0.104
0.151
0.841
0.348
0.379
0.273
0.196
0.428
0.786
0.871
0.664
0.075
0.175
0.261
0.205
0.189
0.022
0.976
0.825
0.433
0.776
0.862
0.912
0.374
0.053
0.616
0.238
0.584
0.963
0.927
0.186
0.099
0.361
0.852
0.211
0.144
0.286
0.621
0.086
0.537
0.388
0.487
0.946
0.667
0.603
0.813
0.677
0.465
0.883
0.025
0.668
0.260
0.237
0.601
0.471
0.942
0.878
0.753
0.382
0.321
0.762
0.950
0.496
0.108
0.282
0.946
0.248
0.403
0.416
0.466
0.985
0.113
0.105
0.202
0.589
0.200
0.133
0.289
0.693
0.164
0.307
0.897
0.515
0.665
0.203
0.113
0.839
0.703
0.269
0.765
0.181
0.242
0.559
0.332
0.670
0.707
0.890
0.612
0.665
0.235
0.687
0.304
0.657
0.114
0.314
0.141
0.471
0.293
0.160
0.753
0.307
0.376
0.270
0.910
0.657
0.023
0.797
0.284
0.608
0.130
0.053
0.419
0.592
0.730
0.453
0.028
0.089
0.001
0.117
0.311
0.331
0.282
0.424
0.412
0.522
0.531
0.295
0.708
0.625
0.093
0.484
0.054
APPENDIX
A-14
0.229
0.224
0.656
0.666
0.541
0.241
0.546
0.781
0.026
0.728
0.967
0.759
0.724
0.702
0.947
0.777
0.791
0.129
0.796
0.782
0.272
0.718
0.356
0.847
0.657
0.383
0.238
0.590
0.241
0.284
0.313
0.818
0.822
0.862
0.253
0.047
0.772
0.758
0.384
0.052
0.997
0.034
0.649
0.113
0.847
0.602
0.952
0.097
0.470
0.260
0.672
0.051
0.670
0.247
0.622
0.449
0.794
0.722
0.235
0.756
0.665
0.076
0.260
0.456
0.110
0.474
0.758
0.216
0.108
0.544
0.651
0.328
0.084
0.615
0.648
0.090
0.385
0.410
0.784
0.288
0.474
0.594
0.393
0.419
0.862
0.104
0.764
0.838
0.322
0.633
0.286
0.455
0.398
0.214
0.346
0.158
0.770
0.276
0.771
0.618
0.468
0.100
0.093
0.618
0.502
0.071
0.416
0.580
0.917
0.633
0.167
0.431
0.810
0.364
0.514
0.473
0.344
0.056
0.732
0.416
0.286
0.229
0.299
0.216
0.101
0.971
0.996
0.896
0.136
0.516
0.801
0.978
0.922
0.460
0.863
0.716
0.125
0.031
0.315
0.754
0.181
0.314
0.229
0.389
0.141
0.831
0.495
0.079
0.766
0.401
0.882
0.365
0.388
0.656
0.086
0.853
0.586
0.155
0.042
0.423
0.199
0.472
0.263
0.304
0.700
0.186
0.520
0.194
0.483
0.157
0.608
0.065
0.069
0.022
0.506
0.806
0.785
0.291
0.705
0.385
0.934
0.969
0.975
0.649
0.985
0.091
0.367
0.458
0.826
0.101
0.723
0.274
0.605
0.455
0.477
0.884
0.187
0.373
0.029
0.409
0.760
0.141
0.469
0.245
0.629
0.861
0.940
0.107
0.717
0.069
0.417
0.819
0.813
0.120
0.179
0.014
0.091
0.743
0.765
0.405
0.947
0.678
0.683
0.764
0.658
0.804
0.670
0.287
0.924
0.648
0.761
0.494
0.800
0.708
0.975
0.310
0.069
0.464
0.878
0.498
0.569
0.521
0.811
0.092
0.520
0.746
0.070
0.987
0.377
0.850
0.813
0.350
0.233
0.287
0.975
0.990
0.317
0.893
0.974
0.365
0.609
0.169
0.493
0.369
0.101
0.611
0.112
0.557
0.749
0.998
0.075
0.967
0.626
0.035
0.973
0.195
0.333
0.270
0.628
0.876
0.168
0.684
0.949
0.230
0.123
0.858
0.055
0.831
0.197
0.125
0.429
0.249
0.094
0.623
0.410
0.731
0.817
0.639
0.771
0.561
0.186
0.158
0.691
0.282
0.834
0.030
0.896
0.401
0.682
0.647
0.240
0.768
0.449
0.547
0.517
0.262
0.214
0.852
0.786
0.945
0.570
0.934
0.982
0.353
0.392
0.231
0.102
0.059
0.758
0.608
0.747
0.183
0.056
0.173
0.292
0.994
0.791
0.958
0.478
0.264
0.156
0.362
0.698
0.536
0.856
0.772
0.766
0.946
0.257
0.264
APPENDIX
A-15
0.438
0.774
0.364
0.788
0.482
0.372
0.666
0.745
0.565
0.616
0.393
0.367
0.746
0.562
0.187
0.801
0.852
0.433
0.755
0.299
0.524
0.619
0.499
0.432
0.203
0.830
0.686
0.723
0.854
0.062
0.162
0.619
0.688
0.540
0.163
0.182
0.689
0.280
0.241
0.445
0.201
0.443
0.844
0.797
0.376
0.119
0.568
0.333
0.750
0.713
0.637
0.567
0.746
0.583
0.613
0.404
0.361
0.083
0.890
0.797
0.842
0.673
0.992
0.971
0.617
0.245
0.207
0.647
0.267
0.336
0.595
0.148
0.820
0.364
0.890
0.808
0.153
0.556
0.341
0.590
0.771
0.727
0.006
0.305
0.760
0.553
0.553
0.360
0.182
0.510
0.076
0.419
0.701
0.120
0.969
0.909
0.715
0.674
0.394
0.741
0.786
0.078
0.363
0.196
0.637
0.983
0.969
0.344
0.499
0.858
0.804
0.926
0.106
0.150
0.087
0.090
0.091
0.209
0.534
0.908
0.086
0.106
0.507
0.050
0.305
0.029
0.470
0.550
0.876
0.393
0.276
0.055
0.724
0.325
0.336
0.467
0.272
0.687
0.170
0.378
0.743
0.288
0.413
0.223
0.355
0.439
0.760
0.528
0.168
0.510
0.923
0.191
0.897
0.647
0.104
0.176
0.435
0.305
0.028
0.544
0.400
0.749
0.063
0.213
0.463
0.177
0.461
0.368
0.753
0.642
0.244
0.916
0.120
0.394
0.780
0.897
0.520
0.831
0.564
0.256
0.328
0.697
0.248
0.882
0.845
0.691
0.443
0.321
0.781
0.135
0.333
0.073
0.996
0.869
0.620
0.867
0.292
0.018
0.843
0.837
0.515
0.798
0.594
0.993
0.770
0.002
0.673
0.896
0.012
0.345
0.692
0.945
0.813
0.295
0.189
0.185
0.568
0.578
0.757
0.036
0.934
0.987
0.232
0.848
0.777
0.663
0.469
0.702
0.407
0.511
0.741
0.346
0.398
0.883
0.282
0.678
0.740
0.222
0.015
0.696
0.648
0.780
0.994
0.293
0.772
0.106
0.586
0.836
0.109
0.427
0.935
0.903
0.397
0.609
0.725
0.113
0.262
0.823
0.787
0.435
0.911
0.599
0.572
0.894
0.647
0.410
0.024
0.069
0.984
0.442
0.887
0.306
0.651
0.719
0.975
0.034
0.259
0.215
0.432
0.102
0.917
0.141
0.521
0.538
0.575
0.033
0.972
0.642
0.377
0.819
0.410
0.813
0.810
0.509
0.908
0.014
0.915
0.669
0.193
0.296
0.361
0.335
0.525
0.268
0.650
0.523
0.798
0.930
0.237
0.990
0.878
0.780
0.848
0.402
0.718
0.586
0.780
0.570
0.288
0.742
0.456
0.905
0.827
0.613
0.020
0.748
0.478
0.771
0.261
0.735
0.819
0.522
0.638
0.853
0.323
0.652
0.680
0.337
0.283
0.776
0.571
0.078
0.231
0.201
0.164
0.674
0.383
0.724
0.233
0.814
APPENDIX
A-16
0.143
0.249
0.236
0.116
0.185
0.647
0.360
0.104
0.167
0.758
0.151
0.462
0.589
0.937
0.485
0.228
0.829
0.062
0.183
0.086
0.903
0.396
0.037
0.408
0.953
0.224
0.533
0.203
0.030
0.660
0.058
0.638
0.164
0.532
0.862
0.267
0.287
0.755
0.558
0.648
0.016
0.103
0.455
0.487
0.843
0.767
0.483
0.977
0.749
0.631
0.007
0.476
0.789
0.647
0.313
0.189
0.666
0.242
0.029
0.016
0.829
0.135
0.287
0.198
0.135
0.490
0.885
0.955
0.592
0.810
0.247
0.728
0.223
0.462
0.452
0.226
0.581
0.267
0.115
0.896
0.944
0.024
0.407
0.994
0.730
0.418
0.987
0.915
0.143
0.178
0.134
0.919
0.606
0.918
0.857
0.931
0.996
0.555
0.262
0.558
0.217
0.714
0.966
0.979
0.141
0.025
0.824
0.879
0.456
0.722
0.772
0.060
0.433
0.439
0.041
0.909
0.169
0.627
0.550
0.356
0.318
0.486
0.734
0.503
0.845
0.812
0.612
0.555
0.843
0.689
0.358
0.235
0.932
0.403
0.160
0.312
0.281
0.512
0.663
0.424
0.780
0.450
0.751
0.831
0.388
0.602
0.978
0.272
0.205
0.226
0.401
0.568
0.277
0.151
0.122
0.137
0.683
0.650
0.304
0.069
0.927
0.384
0.941
0.928
0.166
0.843
0.182
0.924
0.309
0.173
0.463
0.623
0.519
0.801
0.256
0.846
0.141
0.773
0.689
0.913
0.595
0.195
0.845
0.885
0.266
0.691
0.999
0.974
0.917
0.296
0.587
0.754
0.658
0.666
0.188
0.358
0.002
0.032
0.289
0.288
0.047
0.791
0.129
0.018
0.298
0.154
0.396
0.028
0.178
0.743
0.055
0.445
0.751
0.547
0.094
0.924
0.685
0.153
0.469
0.945
0.997
0.647
0.026
0.171
0.599
0.091
0.681
0.029
0.182
0.997
0.646
0.164
0.474
0.680
0.969
0.932
0.394
0.922
0.188
0.579
0.141
0.833
0.360
0.262
0.741
0.327
0.264
0.583
0.091
0.118
0.044
0.766
0.032
0.629
0.088
0.164
0.472
0.746
0.409
0.224
0.102
0.799
0.323
0.588
0.725
0.685
0.698
0.471
0.746
0.545
0.552
0.982
0.831
0.895
0.296
0.540
0.291
0.611
0.380
0.040
0.197
0.694
0.644
0.932
0.785
0.200
0.150
0.856
0.155
0.249
0.766
0.010
0.814
0.528
0.297
0.881
0.091
0.181
0.436
0.520
0.943
0.499
0.319
0.002
0.202
0.313
0.962
0.233
0.781
0.504
0.371
0.756
0.873
0.526
0.591
0.718
0.677
0.350
0.492
0.654
0.680
0.749
0.553
0.233
0.029
0.308
0.452
0.643
0.020
0.078
0.713
0.746
0.235
0.288
0.221
0.686
0.366
0.003
0.860
0.081
0.250
0.146
0.073
0.472
0.144
0.784
0.618
0.184
0.783
0.100
APPENDIX
A-17
0.303
0.243
0.237
0.929
0.978
0.522
0.112
0.290
0.576
0.756
0.116
0.812
0.462
0.598
0.526
0.449
0.901
0.361
0.590
0.412
0.903
0.601
0.389
0.704
0.230
0.211
0.192
0.175
0.861
0.168
0.836
0.502
0.676
0.593
0.172
0.999
0.654
0.286
0.084
0.662
0.364
0.384
0.138
0.355
0.022
0.306
0.377
0.550
0.905
0.635
0.300
0.517
0.405
0.093
0.551
0.380
0.489
0.277
0.355
0.932
0.863
0.290
0.226
0.638
0.612
0.952
0.988
0.704
0.602
0.715
0.624
0.637
0.420
0.971
0.003
0.207
0.140
0.881
0.005
0.189
0.687
0.399
0.074
0.828
0.091
0.640
0.740
0.405
0.406
0.255
0.127
0.824
0.573
0.953
0.998
0.624
0.017
0.850
0.342
0.317
0.246
0.782
0.065
0.465
0.251
0.244
0.783
0.401
0.969
0.115
0.283
0.996
0.606
0.823
0.650
0.383
0.089
0.103
0.618
0.042
0.441
0.011
0.160
0.149
0.348
0.338
0.852
0.606
0.703
0.100
0.050
0.645
0.419
0.240
0.398
0.423
0.271
0.208
0.707
0.500
0.068
0.581
0.741
0.633
0.928
0.360
0.920
0.756
0.935
0.127
0.505
0.585
0.963
0.694
0.260
0.735
0.949
0.411
0.148
0.759
0.391
0.795
0.083
0.026
0.360
0.623
0.270
0.821
0.800
0.154
0.161
0.600
0.401
0.634
0.564
0.793
0.825
0.743
0.934
0.049
0.570
0.136
0.376
0.360
0.245
0.731
0.390
0.943
0.545
0.916
0.897
0.293
0.705
0.309
0.567
0.327
0.714
0.247
0.984
1.000
0.066
0.649
0.685
0.327
0.340
0.410
0.595
0.199
0.376
0.988
0.897
0.895
0.342
0.337
0.860
0.724
0.466
0.834
0.669
0.665
0.709
0.380
0.772
0.447
0.176
0.297
0.786
0.948
0.531
0.209
0.499
0.332
0.202
0.545
0.977
0.839
0.663
0.827
0.332
0.606
0.565
0.391
0.170
0.461
0.006
0.717
0.247
0.064
0.713
0.994
0.374
0.325
0.423
0.111
0.097
0.492
0.243
0.696
0.180
0.819
0.269
0.387
0.430
0.222
0.246
0.974
0.890
0.823
0.553
0.582
0.929
0.801
0.283
0.529
0.271
0.442
0.722
0.044
0.479
0.799
0.979
0.484
0.936
0.876
0.074
0.198
0.857
0.730
0.250
0.724
0.345
0.404
0.792
0.440
0.050
0.103
0.146
0.350
0.435
0.500
0.600
0.156
0.198
0.602
0.327
0.260
0.875
0.066
0.056
0.870
0.156
0.380
0.162
0.857
0.944
0.804
0.455
0.512
0.689
0.493
0.445
0.881
0.033
0.696
0.368
0.809
0.286
0.442
0.751
0.367
0.778
0.621
0.802
0.809
0.605
0.857
0.401
0.725
0.811
0.094
0.982
0.526
0.534
0.290
0.067
0.948
0.140
0.127
0.765
0.703
APPENDIX
A-18
0.889
0.147
0.987
0.946
0.152
0.219
0.675
0.716
0.723
0.737
0.821
1.000
0.242
0.469
0.559
0.585
0.273
0.446
0.115
0.344
0.067
0.814
0.878
0.123
0.527
0.039
0.405
0.875
0.428
0.391
0.610
0.206
0.408
0.087
0.938
0.983
0.767
0.029
0.794
0.164
0.600
0.516
0.019
0.507
0.304
0.857
0.682
0.305
0.983
0.281
0.983
0.821
0.785
0.048
0.530
0.556
0.701
0.174
0.794
0.035
0.862
0.677
0.003
0.233
0.854
0.741
0.267
0.333
0.099
0.713
0.214
0.938
0.815
0.338
0.917
0.426
0.601
0.131
0.386
0.576
0.169
0.305
0.428
0.138
0.263
0.149
0.129
0.500
0.282
0.269
0.757
0.106
0.656
0.595
0.360
0.781
0.491
0.566
0.849
0.621
0.526
0.390
0.830
0.604
0.921
0.794
0.990
0.578
0.923
0.166
0.291
0.783
0.925
0.491
0.779
0.561
0.958
0.002
0.274
0.411
0.152
0.931
0.724
0.050
0.181
0.287
0.507
0.626
0.240
0.052
0.465
0.752
0.580
0.709
0.943
0.507
0.127
0.508
0.623
0.061
0.218
0.370
0.425
0.093
0.997
0.845
0.270
0.635
0.482
0.020
0.969
0.526
0.848
0.797
0.032
0.107
0.960
0.425
0.675
0.326
0.675
0.719
0.804
0.914
0.952
0.852
0.260
0.777
0.297
0.132
0.104
0.260
0.590
0.682
0.223
0.454
0.792
0.402
0.043
0.189
0.600
0.152
0.624
0.865
0.562
0.538
0.922
0.800
0.677
0.215
0.499
0.219
0.031
0.121
0.459
0.574
0.486
0.530
0.894
0.322
0.956
0.352
0.629
0.836
0.299
0.572
0.523
0.597
0.369
0.231
0.143
0.330
0.239
0.875
0.055
0.228
0.146
0.853
0.545
0.933
0.169
0.392
0.025
0.427
0.196
0.839
0.930
0.482
0.187
0.986
0.366
0.834
0.279
0.883
0.299
0.735
0.760
0.040
0.573
0.033
0.445
0.430
0.525
0.449
0.478
0.197
0.486
0.195
0.104
0.475
0.953
0.591
0.431
0.223
0.700
0.851
0.715
0.489
0.625
0.668
0.211
0.997
0.601
0.785
0.101
0.473
0.124
0.182
0.547
0.620
0.025
0.053
0.395
0.130
0.048
0.217
0.554
0.659
0.546
0.129
0.601
0.165
0.109
0.142
0.613
0.506
0.381
0.173
0.790
0.716
0.855
0.443
0.874
0.866
0.932
0.427
0.913
0.900
0.016
0.685
0.389
0.375
0.939
0.731
0.246
0.491
0.478
0.586
0.860
0.333
0.270
0.175
0.453
0.719
0.881
0.232
0.022
0.569
0.330
0.859
0.278
0.198
0.841
0.402
0.647
0.432
0.097
0.795
0.862
0.975
0.797
0.031
0.169
0.900
0.778
0.923
0.686
0.707
0.487
0.790
0.944
0.821
0.099
0.257
0.136
0.962
0.041
0.790
0.122
0.275
APPENDIX
A-19
0.215
0.152
0.693
0.642
0.706
0.418
0.156
0.064
0.241
0.704
0.750
0.537
0.194
0.292
0.930
0.322
0.414
0.263
0.057
0.001
0.654
0.344
0.512
0.258
0.883
0.081
0.782
0.750
0.270
0.027
0.531
0.014
0.110
0.081
0.205
0.788
0.483
0.646
0.186
0.659
0.914
0.753
0.037
0.461
0.839
0.816
0.869
0.297
0.126
0.169
0.356
0.629
0.463
0.043
0.425
0.308
0.874
0.135
0.176
0.971
0.154
0.434
0.026
0.710
0.497
0.452
0.642
0.407
0.109
0.523
0.675
0.651
0.075
0.317
0.838
0.648
0.272
0.236
0.340
0.015
0.596
0.840
0.238
0.877
0.305
0.966
0.703
0.168
0.733
0.688
0.764
0.545
0.185
0.784
0.538
0.817
0.261
0.855
0.484
0.300
0.428
0.769
0.721
1.000
0.087
0.559
0.925
0.034
0.938
0.466
0.853
0.195
0.915
0.256
0.013
0.062
0.477
0.471
0.517
0.567
0.528
0.790
0.645
0.423
0.762
0.130
0.155
0.321
0.697
0.661
0.872
0.302
0.191
0.380
0.575
0.200
0.720
0.417
0.726
0.585
0.190
0.701
0.074
0.089
0.580
0.176
0.650
0.534
0.182
0.197
0.199
0.762
0.730
0.272
0.574
0.584
0.190
0.809
0.123
0.739
0.503
0.020
0.601
0.276
0.054
0.639
0.645
0.275
0.149
0.613
0.325
0.298
0.285
0.415
0.825
0.479
0.492
0.145
0.771
0.672
0.531
0.067
0.236
0.545
0.219
0.747
0.965
0.044
0.680
0.436
0.840
0.117
0.786
0.866
0.122
0.118
0.580
0.107
0.496
0.783
0.957
0.652
0.462
0.203
0.387
0.367
0.086
0.679
0.961
0.484
0.656
0.888
0.538
0.282
0.270
0.236
0.280
0.608
0.886
0.845
0.349
0.909
0.865
0.037
0.057
0.912
0.542
0.756
0.237
0.627
0.850
0.809
0.132
0.817
0.535
0.357
0.567
0.594
0.991
0.534
0.702
0.299
0.240
0.624
0.127
0.325
0.100
0.689
0.605
0.031
0.062
0.064
0.222
0.407
0.911
0.609
0.235
0.655
0.626
0.147
0.402
0.324
0.583
0.973
0.069
0.174
0.596
0.854
0.803
0.416
0.832
0.420
0.835
0.476
0.116
0.355
0.125
0.963
0.682
0.288
0.293
0.972
0.873
0.806
0.228
0.391
0.846
0.474
0.644
0.370
0.793
0.281
0.355
0.602
0.729
0.423
0.570
0.570
0.355
0.815
0.976
0.434
0.056
0.245
0.890
0.682
0.532
0.585
0.267
0.241
0.127
0.948
0.846
0.168
0.358
0.211
0.204
0.601
0.697
0.805
0.015
0.116
0.121
0.179
0.284
0.148
0.477
0.841
0.841
0.634
0.177
0.393
0.876
0.529
0.266
0.447
0.799
0.365
0.392
0.851
0.194
0.486
0.703
0.115
0.176
0.138
0.210
0.447
0.891
0.061
APPENDIX
A-20
0.645
0.307
0.484
0.732
0.342
0.893
0.283
0.932
0.174
0.439
0.496
0.774
0.083
0.773
0.200
0.867
0.224
0.996
0.902
0.756
0.257
0.721
0.454
0.307
0.834
0.768
0.598
0.183
0.778
0.714
0.938
0.074
0.028
0.216
0.596
0.838
0.844
0.505
0.353
0.201
0.322
0.961
0.555
0.181
0.753
0.173
0.548
0.889
0.844
0.393
0.946
0.865
0.345
0.793
0.498
0.594
0.100
0.414
0.837
0.383
0.069
0.244
0.901
0.226
0.342
0.298
0.299
0.835
0.673
0.132
0.400
0.486
0.578
0.680
0.443
0.827
0.519
0.837
0.429
0.324
0.201
0.672
0.084
0.484
0.528
0.697
0.688
0.518
0.238
0.096
0.021
0.601
0.746
0.301
0.241
0.382
0.236
0.851
0.949
0.907
0.530
0.917
0.236
0.599
0.759
0.404
0.994
0.465
0.372
0.047
0.256
0.177
0.521
0.395
0.875
0.187
0.337
0.096
0.288
0.532
0.141
0.383
0.685
0.481
0.126
0.178
0.324
0.692
0.517
0.706
0.308
0.018
0.773
0.039
0.582
0.634
0.834
0.468
0.445
0.631
0.960
0.110
0.352
0.738
0.192
0.658
0.282
0.330
0.956
0.681
0.472
0.369
0.858
0.379
0.772
0.448
0.184
0.200
0.426
0.583
0.149
0.221
0.544
0.913
0.416
0.705
0.061
0.964
0.931
0.742
0.442
0.639
0.585
0.369
0.941
0.575
0.752
0.086
0.679
0.046
0.228
0.176
0.317
0.043
0.594
0.718
0.629
0.708
0.553
0.726
0.724
0.766
0.251
0.290
0.233
0.118
0.129
0.156
0.205
0.245
0.334
0.626
0.034
0.586
0.206
0.195
0.158
0.540
0.901
0.838
0.842
0.255
0.651
0.337
0.808
0.852
0.711
0.566
0.010
0.249
0.518
0.141
0.307
0.233
0.098
0.335
0.354
0.942
0.239
0.661
0.453
0.414
0.482
0.049
0.681
0.351
0.439
0.992
0.042
0.764
0.492
0.602
0.955
0.654
0.380
0.949
0.837
0.373
0.726
0.618
0.075
0.840
0.024
0.866
0.166
0.256
0.123
0.310
0.294
0.474
0.728
0.523
0.148
0.688
0.970
0.474
0.245
0.592
0.556
0.196
0.538
0.661
0.535
0.598
0.608
0.723
0.226
0.832
0.199
0.463
0.314
0.102
0.392
0.030
0.671
0.352
0.200
0.389
0.913
0.702
0.847
0.583
0.234
0.075
0.541
0.568
0.552
0.895
0.996
0.751
0.484
0.271
0.498
0.926
0.196
0.577
0.798
0.723
0.655
0.832
0.598
0.264
0.305
0.779
0.933
0.152
0.714
0.079
0.213
0.467
0.213
0.527
0.212
0.923
0.054
0.682
0.787
0.833
0.136
0.837
0.609
0.050
0.808
0.716
0.681
0.534
0.798
0.822
0.927
0.697
0.791
0.831
0.645
0.196
0.685
0.937
0.078
0.316
0.067
0.561
APPENDIX
A-21
Levels and Requirements for Asphalt Plant Qualified Tester and Certification
Qualified Aggregate Tester
Introduction to Standard Specifications
Math for Construction Personnel
Sampling of Aggregate and Aggregate Mixtures
Sampling of Asphalt Materials
Determination of Moisture Content of Aggregates
Sieve Analysis of Fine and Coarse Aggregates
Amount of Material Finer than No. 200 Sieve in Aggregate by Wash
Splitting and Quartering Samples
Standard Method of Test for Bulk Density (Unit Weight) and Voids in Aggregate
Aggregate Specialty Area Examination
Technician must begin Asphalt Mixture Level 1 Qualified Technician Training within 1 year of
Proficiency Sample Program Participation.
Qualified Asphalt Concrete Plant Level I
Must participate in Proficiency Sample Program
No experience required
Must have completed Qualified Aggregate Tester
Basic Asphalt Concrete Plant Inspection
Lecture:
Superpave Materials
Asphalt Mixture Volumetrics
Gyratory Compaction
Quality Control and Acceptance
Basic Asphalt Mixture Plant Operations
Performance:
Specific Gravity and Density of Compressed Asphalt Mixtures
Mechanical Analysis of Extracted Aggregate
Determination of the Moisture Content of Asphalt Concrete
Determination of the Asphalt Content of Asphalt Mixtures by the Ignition Method
Theoretical Maximum Specific Gravity of Asphalt Concrete Mixtures
Preparing and Determining the Density of Hot Mix Asphalt Specimens by
Means of the Superpave Gyratory Compactor
Asphalt Mixture Level I Specialty Area Examination
Certified Asphalt Concrete Plant Level II
6 months experience required
Must participate in Proficiency Sample Program
Required for QC Plant Technicians and DOTD Asphalt District Inspectors
May review and verify Job Mix Formula (JMFs) and perform asphalt tests for record.
Math for Construction Personnel Vol. 2
Lecture:
Asphalt Mixture Superpave Aggregate Properties
Water Susceptibility of Asphalt Mixtures
Review of JMF Submittals
Performance:
Sand Equivalent of Soils and Fine Aggregate
APPENDIX
A-22
Fine Aggregate Angularity
Coarse Aggregate Angularity
Specific Gravity and Absorption of Fine Aggregates
Specific Gravity and Absorption of Coarse Aggregates
Flat and Elongated Particles
Test for Hamburg Wheel Track Testing of Compacted Asphalt Mixtures
Loose Mix and Compressed Mix Testing and Analysis
Asphalt Mixtures Level II Specialty Area Examination
Certified Asphalt Concrete Plant Level III
Authorized to submit JMF proposals for record
QC Mix Designer requirement and Asphalt District Inspector DCL requirement
12 months experience in asphalt QC or QA
Lecture:
Mix Design Steps and Approval
Performance:
Batching Aggregates and Asphalt Cement for Producing Trial Blends
Asphalt Mixtures Level III Specialty Area Examination
A-23
Asphalt Concrete Plant Certification DOTD 03-22-3075 (Rev. 10/15)
DOTD 03-22-3075
Rev. 10/15
A-24
DOTD 03-22-3075
Rev. 10/15
Page 1 of 8
Material
Approved
Source
Satisfactory
Drainage
Separation
Contamination
Segregation
Adequate
Spacing
Partition
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
COLD AGGREGATE FEEDER
Virgin Aggregate Recycled Material
Type of loading………………………………………………………… Front End Loader Front End Loader
Other Other
Number of Cold Feed Systems Used…………………………………
If more than one system is used, are they integrated?.... Yes / No Yes / No
Number of Cold Bins Used……………………………………………………………
Number of bins sufficient for operations…………………………………… Yes / No Yes / No
Bins are large enough for continuous operation at rated capacity Yes / No Yes / No
Condition of bins satisfactory…………………………………………………….. Yes / No Yes / No
Partitions extend a minimum one foot above top between bins Yes / No Yes / No
Bins equipped with vibrators……………………………………………………… Yes / No Yes / No
Individual Bin Gates:
Gate rectangular……………………………………..…………………… Yes / No Yes / No
Positive mechanical adjustment………………………….…….….. Yes / No Yes / No
Locks in position……………………………………………………………. Yes / No Yes / No
Aggregate Proportioning by cold feed……………………………….. Applicable N/A Applicable N/A
Determined by……………………………………………………... Belt Speed Gate Opening
Calib. Curve / each bin per material type used……………… Yes / No Yes / No
Automatic shut off on each bin……………………………………. Yes / No Yes / No
Adjusted and operating correctly………………………………….. Yes / No Yes / No
A-25
DOTD 03-22-3075
Rev. 10/15
Page 1 of 8
Remarks:
Hydrated Lime Additive Equipment
Interlocked and synchronized with cold feed
control…………………………………… Yes / No
Positive Signal Auto shut-down….. Yes / No
Separate Bulk Storage………………… Yes / No
with approved feed……………….. Yes / No
can be readily calibrated……….. Yes / No
can be easily sampled……………. Yes / No
can be easily verified……………… Yes / No
has totalizer………………………… Yes / No
Approved spray system:
Consistently maintains aggregate in uniform
surface wet condition……………. Yes / No
Moisture content can be introduced into
automatic moisture controls….. Yes / No
Approved mixing device……………. Yes / No
coats uniformly…………….……….. Yes / No
located between additive point and dryer:
……………………………………………… Yes / No
Dispersed directly onto aggregate Yes / No
between cold feed and dryer…. Yes / No
minimum required amount added……………….
………………………………………………… Yes / No
included in belt scale weight…. Yes / No
Remarks:
Mineral Filler Equipment
Capacity (tons)
Adequate…………………………………… Yes / No
Weatherproof……………………………. Yes / No
Leakage……………………………………… Yes / No
Hopper w/adjustable feed…………. Yes / No
Can be accurately calibrated………. Yes / No
Mineral Filler Equipment (cont.)
Interlock w/aggr. & asphalt feeds Yes / No
Proportions accurately……………….. Yes / No
Constant flow of material…………… Yes / No
For Drum & Continuous Plants:
Introduced into mix in advance of asphalt for
proper drying time……………………… Yes / No
For Batch Plants:
Batched into mix w/aggregates….. Yes / No
Screens & Scalpers
Over fine sand bins ……………………. Yes / No
Size N/A
Between cold feed discharge & belt scale
Size N/A Yes / No
Vibrating .…………………….. Yes / No
Over RAP/Recycle ……………………… Yes / No
Size N/A
Batch Plant Hot Bin Screens …… Yes / No
Size N/A
Remarks:
Dust Collection
Baghouse Other
Controller type:
Collector box Surge bin Filler Silo
Collected fines returned to mix …. Yes / No
Auger/Screw Other
Material returned to approved location near
asphalt discharge ……………………… Yes / No
Uniform rate of fines return ………. Yes / No
Acceptable condition of system Yes / No
Remarks:
A-26
DOTD 03-22-3075
Rev. 10/15
Page 1 of 8
Asphalt Cement & Equipment
Number of Storage/Working tanks
Total capacity Agitators Yes / No
Circulation system …………………….. Yes / No
Method of heating Hot oil Other
Uniform Heating ………………………. Yes / No
Required temperature …. Yes / No
Under positive control …. Yes / No
Pipelines & fittings: Insulated Yes / No
Heated Yes / No
Leakage, tanks or piping …………… Yes / No
Automatic shut-off controls ……... Yes / No
Controls operable ……….. Yes / No
Calibration charts & measuring stick provided
Yes / No
Thermometers
Graduated in 5°F increments ….. Yes / No
Accurate ± 5°F ………………………… Yes / No
Located near tank discharge …… Yes / No
A/C measured by volume
Postive displacement pump ……. Yes / No
Recorded in digital form to the nearest gallon
Yes / No
Automatic temp. correction ...... Yes / No
Quantity totalized ………………….. Yes / No
1.0% accuracy of measurement Yes / No
Warm Mix capabilities ………………. Yes / No
Foaming Chemical
Latex Blending ………………………….. Yes / No
Crumb Rubber Blending ……………. Yes / No
Remarks:
Anti-Stripping Additive Storage & Equipment
Recirculating system …………………. Yes / No
Total capacity gallons
Calibration chart & measuring stick provided
Yes / No
Uniform heat ……………………………. Yes / No
Heating: Hot oil Electric Other
Dispensed directly into asphalt feed line
Yes / No
Between asphalt control valve & end of asphalt
discharge line ……………………………. Yes / No
Required quantity of anti-stripping additive
uniformly proportioned ……………. Yes / No
How is proportioning verified?
Is proportioning easily and quickly verifiable?
Yes / No
Include positive displacement accumulating
meter ……………………………………….. Yes / No
Displays accumulated anti-strip used
Yes / No
Reads to 0.25 gallons ……………….. Yes / No
Thermometer in 5°F increments Yes / No
Accurate ±5°F ………………………. Yes / No
Located near storage discharge point
Yes / No
Remarks:
A-27
DOTD 03-22-3075
Rev. 10/15
Page 1 of 8
PRODUCTION AND STORAGE OF MIX
DRUM MIXER PLANT BATCH PLANT
□ Single Drum □ Separate Mixing Drum □ Double Barrel
Rated capacity tons per hour
Mixing unit is continuously supplied with sufficient materials to operate at capacity ……….. Yes / No
Aggregates properly dried ………………………………………………………………………………………………… Yes / No
Temperature is uniform …………………………………………………………………………………………………….. Yes / No
Temperature within specification limits ……………………………………………………………………………. Yes / No
Equipped with automatic burners ……………………………………………………………………………………… Yes / No
Moisture content within specification limits ……………………………………………………………………… Yes / No
Slope of dryer within manufacturer recommended angle limits ………………………………………… Yes / No
Flights in acceptable condition ………………………………………………………………………………………….. Yes / No
Proper asphalt coating of materials …………………………………………………………………………………… Yes / No
Segregation of mix ………………………………………………………………………………………………………….... Yes / No
Mixture is uniform ……………………………………………………………………………………………………………. Yes / No
Oxidation of asphalt ………………………………………………………………………………………………………….. Yes / No
Remarks:
THERMOMETERS
Heated aggregates or asphalt mixture for drum plants the thermometer will be located at the
mix discharge from the drum or other approved location.
Graduated in maximum 10°F increments …………………………………………………. Yes / No
Accuracy of ±5°F ………………………………………………………………………………………. Yes / No
Recording thermometer ………………………………………………………………………… Yes / No
Sensitive to 10°F change in one minute ……………………………………………………. Yes / No
Registers & automatically records discharge temperature ………………………. Yes / No
Describe Location:
Storage Silo Number of Capacity each tons Applicable N/A
Airlock……………………………………………………………………………………………………… Yes / No
Surge Bin Capacity tons Applicable N/A
Heated Unheated Hot oil Other
A-28
DOTD 03-22-3075
Rev. 10/15
Page 1 of 8
Type of atmosphere Air Inert gas. Can system be purged if inert gas ……. Yes / No
Indicator(s) installed at top of slope portion …………………………………………………………. Yes / No
High silo indicator(s) …………………………………………………………………………………………….. Yes / No
Signal: Light Audible Obvious to plant operator …………………….. Yes / No
Any segregation ……………………………………………………………………………………………………. Yes / No
Automatic warning system for gate malfunction ………………………………………………….. Yes / No
Discharged mix within 15°F of plant discharge temperature ………………………………… Yes / No
Type of discharge: Clam Other
Method of conveyance to silo or surge bin: Drag Slat Bucket Other
Type of anti-segregation system:
Conveyance system works continuously ………………………………………………………………. Yes / No
Remarks:
TRUCK WASH DOWN AREA
Area for haul trucks to wash out …………………………………………………………………………… Yes / No
MIX RELEASE AGENT
Spray bar Hand sprayer Platform if hand sprayer Other
Approved source ………………………………………………………………………………………………….. Yes / No
SAMPLING PLATFORM
Sturdy construction ……………………………………………………………………………………………… Yes / No
Acceptable location ……………………………………………………………………………………………… Yes / No
Acceptable size …………………………………………………………………………………………………….. Yes / No
Truck & asphalt mix easily assessable …………………………………………………………………… Yes / No
Sufficient lighting for non-daylight hours ……………………………………………………………… Yes / No
Remarks:
PLANT LABORATORY: Length Width Square feet Minimum 160 ft
2
R18 Compliant ………………………………………………………………………………………………………………….. Yes / No
Acceptable location in relation to the asphalt plant ………………………………………………………….. Yes / No
Protected from the weather …….. Yes / No
Heated …………………………………….. Yes / No
Air Conditioned ……………………….. Yes / No
Fume hood ………………………………. Yes / No
Exhaust fan ………………………………. Yes / No
Running water ………………………….. Yes / No
Electricity …………………………………. Yes / No
Required testing equipment …….. Yes / No
A-29
DOTD 03-22-3075
Rev. 10/15
Page 1 of 8
Adequate counter space ………….. Yes / No
Sufficient chairs & desks …………… Yes / No
File storage ………………………………. Yes / No
Sample storage …………………………. Yes / No
Acceptable sanitation facilities …. Yes / No
Constant temp. ovens 100 - 400°F ±5°F ……………………………………………………………………………. Yes / No
Remarks:
SCALES & METERS
1
Asphalt
Meter/Scale
2
Aggregate Scale
Mineral Filler
Anti-Strip
3
Platform Scales
4
Silo/Bin Scales
Make
Graduation
Date Calib.
Max Error %
Type Panel
Indicator
Accurate ± 1%
Accurate ± 0.5%
1
Asphalt Meter/Scale
Material delivery diverted for checking accuracy …………………………………………………. Yes / No
Are readouts & indicators visible to the plant operator ………………………………………. Yes / No
2
Aggregate Scales
Scale interlocked with asphalt measuring equipment ………………………………………….. Yes / No
Scale wet weight corrected to dry weight …………………………………………………………….. Yes / No
Material delivery diverted for checking accuracy ………………………………………………… Yes / No
3
Platform Scales Applicable N/A
Sufficient length to weigh entire transport …………………………………………………………… Yes / No
Prints zero weight ……………………………………………………………………………………………….. Yes / No
Prints tare weight …………………………………………………………………………………………………. Yes / No
Prints transport & mix weight (gross weight) …………………………………………………….... Yes / No
Prints mix weight (net weight) …………………………………………………………………………….. Yes / No
4
Silo/Bin Scales Applicable N/A
Type: Weigh Hopper Suspended Bin
Type Scale: Springless Load Cell
Remarks:
A-30
DOTD 03-22-3075
Rev. 10/15
Page 1 of 8
BATCH PLANTS
HOT BINS Applicable N/A
Adequate size & number for continuous operation at rated capacity …………………… Yes / No
Adequate storage for individual components ……………………………………………………….. Yes / No
Provided with overflow to prevent contamination ……………………………………………….. Yes / No
Free flowing …………………………………………………………………………………………………………. Yes / No
Acceptable condition ……………………………………………………………………………………………. Yes / No
BATCH PLANT GUGMILL Applicable N/A
Twin shafts …………………………………………………………………………………………………………… Yes / No
All mixing paddles within acceptable wear limits ………………………………………………….. Yes / No
Liner condition acceptable ……………………………………………………………………………………. Yes / No
Clogged spray bars ……………………………………………………………………………………………….. Yes / No
Weigh box leaking ………………………………………………………………………………………………… Yes / No
Pugmill gate leaking ……………………………………………………………………………………………… Yes / No
Timing device operating properly …………………………………………………………………………. Yes / No
Discharge gates lock during timing cycle ………………………………………………………………. Yes / No
Additional material interlock working …………………………………………………………………… Yes / No
Asphalt bucket locked out during dry mixing ………………………………………………………… Yes / No
Signal operational …………………………………………………………………………………………………. Yes / No
Remarks:
DISTRICT LABORATORY REPRESENTATIVE DATE
APPROVED BY DISTRICT LAB ENGINEER DATE
A-31
State of Louisiana
Department of Transportation and Development
Asphalt Concrete Plant Review
Plant: Location:
Company: Arrival Time: Departure:
Date: Inspector/title:
Contractor Technician(s) & Title:
Review to be completed & maintained at the District Laboratory. Maintain separate files for each plant in
the district.
Completed minimum once every 90 days
Yes No
Lab AASHTO R18 current O O
Lab Equipment Manual current O O
Scales & Meters calibrations current O O
Stockpiles
Proper drainage O O
Comments/Findings:
Separated with partitions or space between each material O O
Comments/Findings:
Segregation O O
Comments/Findings:
Does contractor fractionate RAP O O
Stockpiled separately O O
Does contractor use 1 inch screen for RAP O O
Comments/Findings:
A-32
Yes No
Cold feeds comply with certification requirements (Bins & Belts) O O
Drum/burner comply with certification requirements O O
Mix drag/conveyor comply with certification requirements O O
Silo batchers comply with certification requirements O O
Load out gates functioning properly O O
Segregation O O
Proper aggregate coating with asphalt O O
Comments/Findings:
Yes No
Warm mix equipment &/or additives meet certification requirements O O
Lab testing equipment maintained in proper working condition O O
Lab sampling & testing equipment clean & free of residue O O
Lab technician(s) have proper certification/qualification for duties performed O O
CDs for AC up to date in storage file or binder O O
CDs for anti-strip up to date in storage file or binder O O
CAs for fibers used to control drain down up to date in storage file or binder O O
CAs for warm mix additives up to date in storage file or binder O O
Data software up to date for all JMFs O O
Contractor documentation up to date O O
Anti-strip metering verifies O O
Mix release for haul trucks operating properly O O
Dust collection system operating properly O O
Comments:
A-33
ASPHALT MIXTURE TESTING
Each JMF being produced/shipped during DOTD visit to be sampled & tested. A minimum of one
verification sample every 30 days is to be sent to the district lab & tested for G
mm
, %AC, gradation,
%crushed, V
a
, VMA, & VFA.
JMF #: Lot Date sampled: Date tested:
Sampled by: Tested by: Mix temp
Gyratory specimens @ N
design
Plant Lab District Lab
G
mm
: O O
%G
mb
: @ini @des O O
V
a
: O O
VMA: O O
VFA: O O
%AC O O
Gradation O O
% Crushed:
Mix Moisture
Yes No
Mix segregation O O
Proper aggregate coating with AC O O
Haul trucks compliant O O
Contractor Generated Data Review
Rolling five G
mm
≥71 PWL O O
Rolling five V
a
≥71 PWL O O
Rolling five average No. 8 gradation within specification limits O O
Rolling five average No. 200 gradation within specification limits O O
Is DOTD gradation within verification tolerance of Contractor results O O
Rolling five VFA average in specification O O
VMA in specification O O
Any deficiencies or discrepancies found O O
Were any concerns conveyed to plant personnel O O
A-34
Date:
Deficiencies, Comments, etc:
A-35
ASPHALT CEMENT SAMPLES
Working tank AC samples for each PG grade on site at time of visit. To be tested at the District Lab or
Materials Lab. Transport samples taken at the request of the Materials Lab
Inspector:
Date Sampled Supplier Working Tank Transport
PG 58-28 O O
PG 67-22 O O
PG 70-22 O O
PG 76-22 O O
PG 76-22rm O O
Yes No
AC tanks & heaters meet certification requirements O O
AC metering verifies O O
Comments:
Inspector: Date:
DLE: Date:
CDs from previous month attached. Date: initials:
Deficiencies Corrected. Date: initials: Comments:
A-36
A-37
Asphalt Concrete Roadway Equipment Review
State of Louisiana
Department of Transportation and Development
CONTRACTOR ASPHALT CONCRETE ROADWAY EQUIPMENT REVIEW
Date: Project No.: District: Gang:
Inspector:
Review of equipment used for Asphalt Concrete cold planning and paving. To be included in project 2059.
Asphalt Milling Machine
Make & Model:
Yes No
Sufficient power, traction, & stability to provide uniform profile grade & cross slope O O
Capable of controlling uniform profile grade & cross slope from an erected string line,
shoe device or approved traveling reference plane O O
Does method of control accurately reflect the average grade of the surface to be operated on O O
Automatic system for controlling cross slope O O
Milling drum true to round O O
Milling teeth in sufficient number & proper condition to produce a uniform surface & texture O O
Fuel or fluid leak O O
Asphalt Distributor
Make & Model:
Serial No.:
ASTM D 2995 Calibrated O O
Date Calibrated: Calibration Current O O
Copy of Calibration O O
Overall condition acceptable O O
Fluid or fuel leaks O O
Heating system capable of heating material to proper temperature & maintaining temperature O O
Thermometer easily readable O O
Acceptable accuracy O O
Location:
A-38
Yes No
Computerized controls O O
Proper function of controls O O
Does the application rate verify with the on board rate? O O
Spray Bar
Capable of a sharp line of material parallel to the direction of travel? O O
Proper operation O O
Uniform pressure & flow of material O O
Uniform coverage O O
Clogged Nozzles O O
Hand Wand capable of applying material to areas inaccessible to spray bar O O
Material Transfer Vehicle
MTV
Make & Model:
Lightweight MTV O O
Fluid or fuel leaks O O
Capable of remixing asphalt concrete? O O
Minimum 20 storage capacity? O O
Does discharge conveyor swivel to facilitate operation from adjoining lane to paving operation? O O
Tracked or high flotation tires? O O
Attachment for Windrow Paving capable of removing 95% of mixture from paving surface O O
Lightweight MTV
Counter rotating augers O O
Offset gravity transfer conveyor chute, or O O
Twin interlaced augers O O
Thermal Profile System for use with Lightweight MTV
Make & Model:
Capable of continuously recording temperature of the full width of pavement as the mixture exits
the paver O O
GPS - location & distant traveled O O
Capable of instant data review O O
A-39
Page 1 of 1
Yes No
Permanent record of temperature & location data O O
Capable of correlating thermal profile with roadway lot & roadway sublot O O
Paver
Make & Model:
Serial #:
Automatic grade & slope control used with traveling reference plane or erected string line O O
Capable of placing mixtures within specification tolerances O O
Screed or strike off the entire width of the paving strip O O
Paving strip uniform in appearance & quality O O
Capable of adjusting to changing cross slope O O
Minimum 5 ton insert hopper when used in conjunction with a MTV O O
Screed & extension heaters O O
Screed & extension vibrators O O
Augers evenly distribute mix in front of screed O O
Capable of placing mix to required thickness & width without segregation or tearing O O
Fluid or fuel leaks O O
Spray Paver
Insulated tack storage O O
Calibrated load cells O O
Evenly distributes tack O O
Variable width heated screed O O
A-40
Page 1 of 1
Compaction Equipment
#1 Make & Model:
Serial #:
Steel Wheel O Pneumatic tire O
Yes No
Capable of changing direction without distorting the paving mat O O
Equipped with scrapers and watering devices that are working properly O O
Wheels true to round O O
Vibratory O O
Separate controls for frequency, amplitude & propulsion O O
Fluid or fuel leaks O O
Treadless tires if pneumatic O O
Tires same size & ply rating if pneumatic O O
#2 Make & Model:
Serial #:
Steel Wheel O Pneumatic tire O
Capable of changing direction without distorting the paving mat O O
Equipped with scrapers and watering devices that are working properly O O
Wheels true to round O O
Vibratory O O
Separate controls for frequency, amplitude & propulsion O O
Fluid or fuel leaks O O
Treadless tires if pneumatic O O
Tires same size & ply rating if pneumatic O O
#3 Make & Model:
Serial #:
Steel Wheel O Pneumatic tire O
Capable of changing direction without distorting the paving mat O O
Equipped with scrapers and watering devices that are working properly O O
A-41
Yes No
Wheels true to round O O
Vibratory O O
Separate controls for frequency, amplitude & propulsion O O
Fluid or fuel leaks O O
Treadless tires if pneumatic O O
Tires same size & ply rating if pneumatic O O
#4 Make & Model:
Serial #:
Steel Wheel O Pneumatic tire O
Capable of changing direction without distorting the paving mat O O
Equipped with scrapers and watering devices that are working properly O O
Wheels true to round O O
Vibratory O O
Separate controls for frequency, amplitude & propulsion O O
Fluid or fuel leaks O O
Treadless tires if pneumatic O O
Tires same size & ply rating if pneumatic O O
#5 Make & Model:
Serial #:
Steel Wheel O Pneumatic tire O
Capable of changing direction without distorting the paving mat O O
Equipped with scrapers and watering devices that are working properly O O
Wheels true to round O O
Vibratory O O
Separate controls for frequency, amplitude & propulsion O O
Fluid or fuel leaks O O
Treadless tires if pneumatic O O
Tires same size & ply rating if pneumatic O O
A-42
Page 1 of 1
#6 Make & Model:
Serial #:
Steel Wheel O Pneumatic tire O
Yes No
Capable of changing direction without distorting the paving mat O O
Equipped with scrapers and watering devices that are working properly O O
Wheels true to round O O
Vibratory O O
Separate controls for frequency, amplitude & propulsion O O
Fluid or fuel leaks O O
Treadless tires if pneumatic O O
Tires same size & ply rating if pneumatic O O
Comments:
A-43
A-43
A-44
Suggested Tie-In Procedure
The first step in attaining smoothness is defining the rate of elevation change at the bridge
approach.
Here is the process for attaining smoothness in final surface elevation:
1. Start with a string line attached to the approach slab or bridge end (or use rod
readings.) Use the string to project the slope until the pavement is touched (there
may be occasions when the string does not touch pavement)
2. Attach a second string line to the approach slab (or use rod readings) to find the
suggested elevation change using the ratio: 1” rise : (1 linear foot x speed limit).
Again, projecting the slope until the pavement is touched
For example:
If the speed limit is 60 mph, the suggested elevation change should
be 1” per 60 linear feet.
3. If the speed limit is 70 mph, the maximum change in elevation is 1 inch per 70 feet.
4. Select the shorter of items 1 or 2 (above) for the tie-in point.
5. Measure the distance under the string line from the bridge end (0”) to the tie-in
point (0”) and mark the pavement for the required fill depth at 5 or 10 ft. intervals.
This will be the fill thickness (or in some cases a cut) to get to final surface
elevation.
6. Draw plan and profile views with the information then submit them to the PE for
review with the estimated asphalt quantity for leveling.
If there is a drastic elevation difference, the 1” per 70 ft. for 70 mph can be modified as
necessary, but no greater than 2” per 70 ft. @ 70 mph.
Note: See 502.09 and 502.15.6 for information concerning the “string line.
Weight Certification Tag (example)