ENERGY STAR Single-Family New Homes
California Program Requirements, Version 3.4 (Rev. 12)
Revised 05/01/2023 Page 1 of 3
Eligibility Requirements
Site-built or modular
1
Dwellings
2
(e.g., single-family homes, duplexes) and Townhouses
3
are eligible to participate in the ENERGY STAR
Single-Family New Homes (SFNH) program.
While primarily intended for new construction, existing homes (e.g., undergoing a gut rehabilitation) are also eligible to participate in the
ENERGY STAR SFNH program, with guidance available at: www.energystar.gov/GutRehabGuidance.
For information about other ENERGY STAR residential new construction programs, visit www.energystar.gov/newhomesrequirements.
Note that compliance with these requirements is not intended to imply compliance with all local code requirements.
4
Partnership, Training, and Credentialing Requirements
The following requirements must be met prior to certifying homes:
Builders are required to sign an ENERGY STAR Partnership Agreement and complete the online Version 3 Builder Orientation,
which can be found at www.energystar.gov/homesPA.
HVAC installing contractors are required to be credentialed by an EPA-recognized HVAC Quality Installation Training and Oversight
Organization (H-QUITO) for homes certified using Track B in Exhibit 1. An explanation of this process can be found at
www.energystar.gov/newhomesHVAC.
Energy Rating Companies (e.g., rater companies and Providers
5
) are required to sign an ENERGY STAR Partnership Agreement,
which can be found at www.energystar.gov/homesPA, and operate under a Home Certification Organization (HCO). Learn more and
find a current list of HCOs at www.energystar.gov/hco.
Raters
6
are required to complete EPA-recognized training, which can be found at www.energystar.gov/newhomestraining.
ENERGY STAR Certification Process
1. The certification process provides flexibility to select a custom combination of measures for each home that meets one of two
performance targets, as assessed through energy modeling. Select one of the two following performance targets:
a. An Efficiency Energy Design Rating (EDR2 Efficiency) that is ≥ 5 points better than that of the Standard Design corresponding to
the home, as defined by the 2022 Building Energy Efficiency Standards and determined by a CEC-approved software program.
7
b. A Compliance Margin (EDR2) ≥ 10% compared to the Compliance Total of the Standard Design TDV Energy corresponding to the
home, as defined by the 2022 Building Energy Efficiency Standards and determined by a CEC-approved software program.
7
2. Configure the preferred set of efficiency measures for the home to be certified and verify that the resulting performance meets or exceeds
the applicable performance target using the applicable software program, as determined in Step 1.
Note that, regardless of the measures selected, the Mandatory Requirements for All Certified Homes in Exhibit 1 are also required and
impose certain constraints on the efficiency measures selected (e.g., insulation levels, insulation installation quality, window
performance, duct leakage).
3. Construct the home using the measures selected in Step 2 and the Mandatory Requirements for All Certified Homes, Exhibit 1.
4. Using a Rater, verify that all requirements have been met in accordance with the Mandatory Requirements for All Certified Homes and
with Data Input requirements and On-Site Inspection Procedures for California HERS Ratings.
6, 8
For modular homes, a Rater must
verify any requirement in the plant not able to be verified on-site because a feature will be concealed prior to shipment. Finally, submit
the home to the HCO for final certification and follow the HCO’s certification and oversight procedure (e.g., quality assurance,
recordkeeping, and reporting). The Rater is required to keep electronic or hard copies of the completed and signed National Rater
checklists and either an HVAC design report compliant with ANSI / RESNET / ACCA / ICC 310, and the National HVAC Design
Supplement to Std. 310 for Dwellings & Units, for homes using Track A, or the National HVAC Design Report for homes using Track B.
The Rater must review all items on the National Rater checklists. Raters are expected to use their experience and discretion to verify
that the overall intent of each inspection checklist item has been met (i.e., identifying major defects that undermine the intent of the
checklist item versus identifying minor defects that the Rater may deem acceptable).
In the event that a Rater finds an item that is inconsistent with the intent of the checklists, the home cannot earn the ENERGY STAR
until the item is corrected. If correction of the item is not possible, the home cannot earn the ENERGY STAR. In the event that an item
on a National Rater checklist cannot be inspected by the Rater, the home cannot earn the ENERGY STAR. The only exceptions to this
rule are in the Thermal Enclosure System Section of the National Rater Field Checklist, where the builder may assume responsibility for
verifying a maximum of eight items. This option shall only be used at the discretion of the Rater. When exercised, the builder’s
responsibility will be formally acknowledged by the builder signing the checklist for the item(s) they verified.
In the event that a Rater is not able to determine whether an item is consistent with the intent (e.g., an alternative method of meeting a
checklist requirement has been proposed), then the Rater shall consult their Provider. If the Provider also cannot make this determination,
then the Rater or Provider shall report the issue to EPA prior to project completion at: energystarhomes@energystar.gov and will receive
an initial response within 5 business days. If EPA believes the current program requirements are sufficiently clear to determine whether
the intent has been met, then this guidance will be provided to the partner and enforced beginning with the house in question. In contrast,
if EPA believes the program requirements require revisions to make the intent clear, then this guidance will be provided to the partner
but only enforced for homes permitted after a specified transition period after the release of the revised program requirements, typically
60 days in length.
This will allow EPA to make formal policy decisions as partner questions arise and to disseminate these policy decisions through the
Policy Record and the periodic release of revised program documents to ensure consistent application of the program requirements.