CSU SEISMIC REQUIREMENTS
Rev. February 2024
CSU Seismic Requirements Quick Start Guide
Scope: These California State University (CSU) Seismic Requirements were established to implement
the Seismic Policy set by the Board of Trustees. The CSU Seismic Policies apply to all structures
within the bounds of a CSU physical master plan. To accomplish its seismic purpose, it requires
considerations of gravity loadings and response.
Applicability: If a University seeks to conduct operations at an off-campus location, the facility must
be evaluated according to theStandards for Acquiring Buildings and Space” (Lease/Acquisition
Policy). Project funding source has no effect on peer review needs. CSU use is the determining
factor. (Sec. 3.2, 3.4, 8.0)
Planning for all Capital Projects: Planning for all projects shall address the options considered to
improve seismic performance beyond minimally required code conformance. The basis for
determination of the selected option shall be documented to Capital Planning, Design and
Construction (CPDC). (Sec. 8.0)
What Needs Seismic Peer Review: All major capital building projects require seismic peer review.
All minor capital building projects shall be seismically assessed; however, a Campus Deputy Building
Official (CDBO) may issue a written waiver for individual minor capital infrastructure and capital
projects that do not have material seismic issues. If there is any doubt, contact the campus Seismic
Peer Reviewer to assess a project’s peer review need. (Sec. 3.7, 4.0, 5.5)
Early Notice to Design Team of Seismic Design Coefficients and Risk Category: The CSU has
established campus-specific seismic ground motion parameters that supersede California Building
Code (CBC) values and implements a conservative evaluation on CBC Structural Risk Category
assignments. As these can have a substantial effect on project costs, it is imperative that
Universities inform the Contractor and Design team proposer of these CSU seismic requirements at
the solicitation stage of a project. (Sec. 3.1, 3.3)
Peer Review: Peer review starts at project inception and continues until construction completion.
Peer review concurrence letters are issued at the completion of the Schematic Preliminary Design
and Construction Documents Phases, and during the course of construction on deferred submittals
that have a seismic component. (Sec. 4.0) All Seismic Review Board (SRB) peer review comments
require resolution. SRB construction phase submittals must be resolved prior to an occupancy permit
being issued. Engage the SRB peer review of the Owner Program Requirements (OPR) and/or
Feasibility Study (FS) concurrent with Project Request for Proposal (RFP) development for Design
Build (DB) or Collaborative Design Build (CDB) Deliveries. Secure Seismic Peer Reviewer’s
concurrence letters for the OPRs and/or FSs in advance of advertisement for DB or CDB proposals
and deliveries. (Sec. 3.8, 4.4, 5.18)
Purchase, Lease: The CSU Seismic Requirements have standards for the purchase, lease, license,
and another form of acquisition or occupancy of buildings or portions thereof. Compliance is
required before actual occupancy begins. (Sec. 1.0, 8.0)
Special Conditions: The CSU Seismic Requirements address many special conditions including
Geotechnical Investigations, Modular Buildings, Pre-engineered Structures, Temporary Use of
Buildings, Voluntary Retrofits, Use of Engineered Wood Products, and Designated Seismic Systems.
(Sec. 5.0)
Phased Retrofit: If the CSU Building Official approved retrofit completion date is not met, then at
their discretion, the CSU Building Official can direct the building to be vacated until such work is
completed and a certificate of occupancy issued. (Sec 5. 16)
Change of Use: Temporary use changes (<14 days) require a Special Event Permit. Coordinate with
CDBO. Renovations that alter an existing CBC Use and Occupancy require CDBO and SRB review.
Early concept review by SRB can readily provide an informal advisory assessment.
(Sec. 5.20)
CSU Seismic Priority Lists: Buildings on the CSU Priority Lists require seismic assessments to be
included as a part of the project scope of any renovation work. (Sec. 7.0)
CSU Seismic Emergency Response: In the event of a seismic or structural emergency, contact any
Seismic Peer Reviewer to assess the need for a mobilization response. If a mobilization response is
warranted, the CDBO functions will be temporarily assumed by the SRB to rapidly assess which
buildings are safe for use. (Sec. 6.0)
Responsibility of Design Professionals During Construction: Design professionals are expected to
directly notify the CSU construction manager and Seismic Peer Reviewer of potential construction
changes or modifications to the approved design documents that can substantively impact expected
structural performance and, where appropriate, directly contact the Seismic Peer Reviewer for
consideration of and concurrence with the changes as specific conditions warrant. (Sec. 3.10)
Table of Contents
1. CSU SEISMIC REQUIREMENTS .............................................................................................................. 1
2. SEISMIC REVIEW BOARD ..................................................................................................................... 3
3. CODES AND STANDARDS APPLICABLE TO CSU CONSTRUCTION ACTIVITY ................................................. 3
3.1 Minimum Requirements .......................................................................................................................... 3
3.2 Application to New Buildings .................................................................................................................. 5
3.3 Campus Seismic Coefficients ................................................................................................................... 5
3.4 Applications to Existing Buildings ............................................................................................................ 6
3.5 Code Enforcement ................................................................................................................................... 9
3.6 Active Faults .......................................................................................................................................... 10
3.7 Peer Review for Small Projects .............................................................................................................. 11
3.8 Peer Review Verification........................................................................................................................ 11
3.9 Engineer-of-Record................................................................................................................................ 12
3.10 Responsibility of Design Professionals during Construction .................................................................. 12
3.11 Special Inspections ................................................................................................................................ 13
3.12 Structural Observations ......................................................................................................................... 13
4. PEER REVIEW .................................................................................................................................. 13
4.1 Scope of Review ..................................................................................................................................... 14
4.2 Timing of Peer Review ........................................................................................................................... 15
4.3 Reports .................................................................................................................................................. 15
4.4 Responses and Corrective Actions ......................................................................................................... 16
4.5 Distribution of Reports .......................................................................................................................... 16
4.6 Design Professional Responsibility ........................................................................................................ 16
4.7 Resolution of Differences....................................................................................................................... 16
4.8 Peer Review Contract and Cost ............................................................................................................. 17
5. SPECIAL CONSIDERATION ................................................................................................................. 17
5.1 Private Buildings Constructed on CSU Land........................................................................................... 17
5.2 Geotechnical Investigations .................................................................................................................. 17
5.3 EOR References to Geotechnical Investigation...................................................................................... 17
5.4 Changes and Additions to Published SRB Requirements ....................................................................... 18
5.5 Projects Not Warranting Peer Review ................................................................................................... 18
5.6 Demolition Projects ............................................................................................................................... 18
5.7 Material Properties of Existing Buildings .............................................................................................. 19
5.8 Design Build and CM at Risk Projects .................................................................................................... 19
5.9 Moment Frame Structural Systems ....................................................................................................... 20
5.10 Post-tensioned Structural Elements ...................................................................................................... 20
5.11 Alternate Methods of Construction ....................................................................................................... 20
5.12 Use of Engineered Wood Products ........................................................................................................ 21
5.13 Delegated Design and/or Deferred Approvals ...................................................................................... 21
5.14 Pre-engineered Structures ..................................................................................................................... 22
5.15 Designated Seismic Systems .................................................................................................................. 24
5.16 Phased and Voluntary Retrofit .............................................................................................................. 24
5.17 Final Approval ....................................................................................................................................... 25
5.18 Earthquake Soil Pressures ..................................................................................................................... 25
5.19 Temporary Use of Buildings and Structures .......................................................................................... 26
5.20 Suspended Ceilings ................................................................................................................................ 26
6. POST-EARTHQUAKE REVIEWS ........................................................................................................... 27
7. CSU SEISMIC BUILDING ASSESSMENT PROCEDURES ............................................................................. 28
8. PROJECT PLANNING ......................................................................................................................... 30
8.1 Priority Lists ........................................................................................................................................... 30
8.2 Project Considerations........................................................................................................................... 32
9. SEISMIC SAFETY STANDARDS FOR ACQUIRING BUILDING AND SPACE .................................................... 33
9.1 Types of Acquisitions ............................................................................................................................. 33
9.2 Acceptable Evaluation Documents ........................................................................................................ 35
Attachment A ....................................................................................................................................... 38
California State University Seismic Review Board ............................................................................ 38
ATTACHMENT B ...................................................................................................................................... 39
CSU Seismic Requirements values for use on all projects subject to the 2022 edition of the California Building
Code ...................................................................................................................................................... 39
Table 1 - CSU Campus Seismic Ground Motion Horizontal Response Spectral Acceleration Parameters ............. 40
ATTACHMENT C....................................................................................................................................... 49
California State University Campus Assignments of Seismic Peer Reviewers .................................................. 49
ATTACHMENT D ...................................................................................................................................... 50
Seismic Performance Levels for Existing Buildings ....................................................................................... 50
ATTACHMENT E ....................................................................................................................................... 52
Technical Guidelines ................................................................................................................................ 52
A. American Concrete Institute 318 Requirements .................................................................................. 52
B. Post-Tensioning Institute Recommendations ...................................................................................... 52
C. California Building Standards Code .................................................................................................... 53
D. Recommended Standards of Care & Practice ...................................................................................... 53
ATTACHMENT F ....................................................................................................................................... 55
References.............................................................................................................................................. 55
CSU Seismic Requirements
February 15, 2024
Page 1
CSU Seismic Requirements
Originally Adopted December 8, 2000; revised July 1, 2023
1. CSU SEISMIC REQUIREMENTS
The California State University (CSU) Board of Trustees adopted the following policy to apply to
all CSU construction projects:
RESOLVED, by the Trustees of the California State University, that the
following policy is adopted:
It is the policy of the Trustees of the California State University that to the
maximum extent feasible by present earthquake engineering practice to
acquire, build, maintain, and rehabilitate buildings and other facilities that
provide an acceptable level of earthquake safety for students, employees,
and the public who occupy these buildings and other facilities at all
locations where University operations and activities occur. The standard for
new construction is that it meets the life safety and damageability
objectives of Title 24 provisions; the standard for existing construction is
that it provides reasonable life safety protection, consistent with that for
typical new buildings. The California State University shall cause to be
performed independent technical peer reviews of the seismic aspects of all
construction projects from their design initiation, including both new
construction and remodeling, for conformance to good seismic resistant
practices consistent with this policy. The feasibility of all construction
projects shall include seismic safety implications and shall be determined by
weighing the practicality and cost of protective measures against the
severity and probability of injury resulting from seismic occurrences.
[Approved by the Trustees of California State University at its May 18-19, 1993
meeting (RTCPBG 05-93-13).]
These CSU requirements are the basis for CSU seismic actions. CSU undertook the assessment of
the seismic hazard posed by the University’s building stock at the direction of Governor
Deukmejian in 1992 with resources provided by the Legislature in 1993. Since then, CSU has had
a vigorous program of reducing the unacceptable seismic risk of its owned, constructed,
acquired, and leased buildings based on these CSU requirements’ enforcement to acceptable
levels. Assessment of seismic issues also entails gravity and other environmental loads as
necessary companions, which are included in the assessment.
The CSU Seismic Requirements describe the CSU framework used to implement the Trustees’
Seismic Requirements. Key objectives and requirements are excerpted below.
Additional background information and direction to the related policy requirements are
provided for each.
1. The goal is, to the maximum extent feasible by present earthquake
engineering practice, to provide an acceptable level of earthquake
safety when acquiring, building, maintaining, and rehabilitating
buildings and other facilities.
CSU Seismic Requirements
February 15, 2024
Page 2
Discussion: Actions necessary to accomplish this goal were initiated in
1992 for existing buildings and will continue until all CSU existing
buildings meet the seismic safety objective of the Trustees and all new
construction meets this goal. Each year capital expenditures are
recommended until the unacceptable safety hazard buildings are
seismically retrofitted or removed from service. The Seismic Review
Board is responsible to the Chancellor for review of expected seismic
performance characteristics of all CSU buildings and advises the
Chancellor of actions necessary to achieve an acceptable level of seismic
risk for CSU buildings. The SRB is addressed in Section 2. Safe use of
buildings subjected to possible earthquake damage is addressed in
Section 6. Other special issues are addressed in Section 5. Standards for
the acquisition and lease of buildings are given in Section 9.
2. The standard for:
New construction is that it meets the life safety and damageability
objectives of Title 24 applicable provisions.
Renovation and maintenance construction is that it provides
reasonable life safety protection consistent with that for typical new
buildings.
Discussion: The California Building Code (CBC) and the California Existing
Building Code (CEBC) provide construction standards for new
construction and renovation of existing buildings, respectively.
(The implementation of these standards is addressed in Section 3.)
3. Independent technical peer reviews shall be conducted concerning the
seismic aspects of all construction projects from their design initiation,
including new construction, maintenance, and remodeling, for
conformance to good seismic-resistant practices consistent with these
CSU requirements.
Discussion: The SRB is delegated responsibility to conduct independent
technical peer reviews of all CSU construction projects. The conduct of
seismic peer reviews is addressed in Section 4.
4. The feasibility of all construction projects shall include seismic safety
implications and shall be determined by weighing the practicality and
cost of protective measures against the severity and probability of injury
resulting from seismic occurrences.
Discussion: The CBC establishes minimum standards for building safety.
The CSU Standard may require more demanding considerations than
what current CBC and referenced technical standards require where the
SRB review indicates it is necessary to achieve the Trusteesstandard of
seismic performance. Section 9 of the CSU Seismic Requirements
addresses the incorporation of seismic design and review into facilities
planning and campus development.
CSU Seismic Requirements
February 15, 2024
Page 3
2. SEISMIC REVIEW BOARD
The SRB was established in 1992. It is charged with implementing the independent peer review
requirements of the Trustees Seismic Requirements later adopted. The Board of Trustees also
advises CSU on structural engineering issues for specific projects. Membership is comprised of
professionals not otherwise affiliated with the University system. Board members are appointed
by and serve at the discretion of the Chancellor. The Board’s current membership is listed in
Attachment A.
3. CODES AND STANDARDS APPLICABLE TO CSU CONSTRUCTION ACTIVITY
By law, California State University is required to enforce the current edition of the adopted
applicable elements of the California Code of Regulations, Title 24 in its entirety as adopted by
the California Building Standards Commission (CBSC), henceforth known as the CBSC unless
specifically noted otherwise. To facilitate this legal requirement, the CSU has adopted, as policy,
selected additional sections of Chapter 1 Scope and Administration of the CBC related to code
administration, code enforcement, and code interpretation, see California State Policy
PolicyStatfor listing of sections adopted as policy. These Seismic Requirements supplement
the requirements of the Code (Parts 1 through 12). Where requirements differ, the more
restrictive shall apply.
The CBSC applies to all construction activity undertaken by CSU and applies to both seismic and
non-seismic requirements for construction. The two sections address the seismic design of
structures: the requirements for new buildings are found in Chapter 16 of Part 2, Volume 2 of
the California Code of Regulations, known as the California Building Code (CBC); and the
requirements for existing retrofit/renovation and repair to campus buildings are found in
Part 10 of the California Code of Regulations, termed the California Existing Building Code
(CEBC).
The CSU Building Official (known hereafter as the Building Official) is based in the Chancellor’s
Office and is responsible for the enforcement of the Code and these CSU Seismic Requirements.
A Campus Deputy Building Official (CDBO) is designated on each campus and has the delegated
responsibility under the direction of the Building Official to enforce the code at the associated
campus and those additional sites under campus jurisdiction. When an emergency occurs at the
campus resulting in earthquake damage, an SRB member serves as Emergency Designated
Building Official (EDBO) to assure the independence of judgment on safety-related issues.
Designated historic structures may be subject to the State Historic Building Code; these
requirements are in addition to the same life safety objectives as provided in CBC and CEBC.
3.1 Minimum Requirements
The current edition of the CBC provides the minimum requirements for the regulation of
all California State University construction activity. It has 12 sections, including those for
new (Part 2), existing (Part 10), and historic buildings (Part 8). By common practice, the
CBSC Code refers to the entirety of the 12 Parts. It applies to all construction, whether it
is new, or an addition, modification, or alteration of an existing structure, including both
permitted and non-permit-requiring actions.
CSU Seismic Requirements
February 15, 2024
Page 4
The seismic requirements of CEBC for existing buildings are less stringent than CBC
Requirements for new buildings. The intent of CEBC is to retrofit and repair existing
structures that will yield an essential life-safety level of performance. Essential life
safety seeks to provide design performance that will allow building occupants in a
seismic event to exit the structure safely. CBC Part 2, Chapter 16 may be used for
modifications of the International Building Code (IBC) existing building, if so desired.
Essential life safety does not necessarily mean that the occupants will be uninjured or
not need medical attention. A structure is presumed to achieve this level of performance
where: although significant damage to the structure may have occurred, some margin
against total collapse remains, even though damage may not be economical to repair;
major structural elements have not become dislodged or fallen to pose a life-safety
threat; and, non-structural systems or elements, which are heavy enough to cause
severe injuries either within or outside the building, have not become dislodged so as to
pose a life-safety threat. Window glass, roofing tile, and elements of non-structural
cladding systems are not generally considered to be a falling hazard to be included
within this category of concern, except over primary entrances and exits. Very heavy
cladding, such as precast concrete or prefabricated scrim panels, should be considered
falling hazards.
The CBC-required seismic provisions can be modified by the University to provide a
higher level of seismic performance and shall be in compliance with the intent and
purpose of this code but may not be modified to provide a lower level of seismic
performance. Part 2 Division I Chapter
1 allows the Building Official to enforce other
provisions as long as they do not diminish the safety of the facility. At any time when the
Building Official chooses to exercise the authority of Section 104.10 Modifications, the
basis for the modification must be reviewed and approved by the SRB prior to the
approval of the construction plans. If any such modifications are considered, they should
be provided to the design team as soon as possible, preferably before the design begins.
Consistent with CEBC, the retrofit or repair of a structure to essential life safety as a
level of expected structural performance intends that occupants will be able to exit the
structure safely following an earthquake.
Special Note: CBC Section
1604.5 requires the [Structural] Risk Category to be
determined for every building. Table
1604.5 characterizes the nature of the Risk
Category for various occupancies and uses. Occupant load is typically calculated per CBC
Chapter 10 occupancy values based on use and square footage. Once the occupant load
is determined, Table 1604.5 is applied to assign the Risk Category for structural design
purposes.
Note that the occupant load determined by the design team (architect) is based on
fire-related considerations and confirmed by the CDBO.
CBC Table 1604.5 refers to “buildings and other structures containing educational
occupancies above 12th grade with occupancy load greater than 500.
These requirements broadly apply to all CSU buildings with educational occupancies
and/or instructional facilities, including non-state-funded buildings, dormitories (with
educational occupancies above 12th grade and occupancy load greater than 500), dining
centers, student unions, student recreation centers, student health centers, office
buildings, stadia, aquatic facilities, etc. When a building exceeds this threshold, it shall
be classified as Risk Category III, unless other designations trigger a more restrictive
designation.
CSU Seismic Requirements
February 15, 2024
Page 5
Certain CSU operations, including emergency operations centers, public safety buildings,
water storage facilities, and pump structures required to maintain water pressure for
fire suppression will trigger a Category IV use classification.
Exception: Parking Structures: The occupancy threshold trigger for Risk Category III
applied to parking structures is 5,000 occupants as calculated by CBC Chapter 10.
Requiring a Category III inclusion at 500 occupants for the inherently short-term,
transient occupancy of a parking structure use is inconsistent with the CBC intent to
provide supplemental, concentrated occupancy protection otherwise broadly afforded
to college and university adult education facilities.
Parking structures may be designed for Risk Category II provided there is no
sub-occupancy of Risk Category IV and not more than 10 percent of any other
non-parking occupancy of Risk Category III, see Section 3.1, Exception.
3.2 Application to New Buildings
These policy requirements apply to all construction, whether new or modification of an
existing building. Additions to an existing building that are seismically separated from
that existing building shall meet the requirements for a new building. An addition may
be considered seismically separated if the response of its structural elements will not be
directly impacted by those of the existing building, either because they are not
physically connected, or the physical separation is sufficient to avoid contact during an
earthquake response. The addition’s foundation systems may be in contact if they are at
or below grade and both existing and new foundations have been evaluated to avoid
surcharging each other.
3.3 Campus Seismic Coefficients
CBC Chapter 16 and CEBC Part 10 require seismic coefficients for structural calculations.
CSU has adopted specific seismic parameters (Attachment B) to be used at all sites
within the contiguous portions of a given campus that supersede those provided in the
CBC unless justified by the project geotechnical engineer and approved by the SRB.
For new buildings, the Risk-Targeted Maximum Considered Earthquake (MCE
R
) Ground
Motion Response Acceleration parameters (S
MS
and S
M1
) and the Design Earthquake (DE)
Ground Motion Response Acceleration parameters (S
DS
and S
D1
) shall not be less than the
respective BSE-2N (MCE
R
) and BSE-1N (DE) values
given in Table 1 of Attachment B for
the Site Class corresponding to the site-specific subsurface conditions of the building
location. Corresponding Peak Ground Acceleration parameter values (PGA
M
and PGA
D
) to
be used for the evaluation of potential geologic/seismic hazards are also given in Table 1
of Attachment B.
Similarly, the ground motion response acceleration parameters used for evaluation
and/or retrofit of existing buildings shall not be less than the respective BSE-C (S
CS
and
S
C1
) and BSE-R (S
RS
and S
R1
) values
given in Table 1 of Attachment B for the Site Class
corresponding to the site-specific subsurface conditions of the building location.
As specified in the CBC, the BSE-C and BSE-R parameters are related to the hazard levels
of 5% and 20% probabilities of exceedance (P
E
) in 50 years, respectively, and are not
constrained by BSE-2N (MCE
R
) and BSE-1N (DE) values. Corresponding Peak Ground
Acceleration parameter values (PGA
C
and PGA
R
) to be used for the evaluation of potential
geologic/seismic hazards at the respective hazard level are also given in Table 1 of
Attachment B.
CSU Seismic Requirements
February 15, 2024
Page 6
The campus seismic ground motion parameters given in Table 1 of Attachment B
correspond to reference rock Site Class BC (V
S30
= 760 m/s) as utilized by the United
States Geological Survey (USGS) in developing the U.S. Seismic Design Maps, as well as
Site Classes C and D, with adjustments made using site coefficients F
a
and F
v
per
ASCE/SEI 7-16 Tables 11.4-1 and 11.4-2, respectively, and F
PGA
, per ASCE/SEI 7-16
Table 11.8-1. The SMS and SM1 values given in Table 1 of Attachment B for Site Class BC
represent the mapped spectral response acceleration parameters at short periods (SS)
and at a period of 1 second (S1), respectively.
The site-specific subsurface conditions are to be determined for the building/facility site
by the geotechnical engineer as part of the project’s development. Site Class at a given
building/facility site location shall be determined based on site-specific soil and/or rock
properties data following the Site Class definitions given in ASCE/SEI 7 Chapter 20. If soil
and/or rock properties information is not available in adequate detail to designate the
Site Class per ASCE/SEI 7 Chapter 20, the Default D Site Class shall be used unless
geologic/geotechnical information indicates that Site Class E or F ground conditions may
be present at the site that could trigger the need for site-specific hazard analyses.
For locations not covered in Attachment B, the University shall request and the CSU
Seismic Review Board shall provide such values for design.
Use of the seismic ground motion parameters given in Table 1 of Attachment B satisfies
the provisions of ASCE/SEI 7 Chapter 11, Section 11.4.8, requiring site-specific ground
motion hazard and/or site response analyses for structure locations at CSU campuses
for any Site Class except as provided below. Site-specific ground motion hazard and/or
site response analyses are required for Site Classes E and F ground conditions.
Site-specific ground motion hazard and/or site response analyses are permitted for any
Site Class if warranted by the nature or special characteristics of a project; however, the
need for such site-specific analyses, as well as the methodology for these analyses and
analysis results, shall be subject to peer review by the geotechnical member of the CSU
Seismic Review Board.
3.4 Applications to Existing Buildings
The California Code of Regulations, the California Existing Building Code (CEBC), Sections
317 through 323, governs work on CSU existing buildings and provides a level of life
safety generally consistent with that of new buildings, but not particularly to achieve
any other function, maintenance, or damage limitation objectives. These CEBC sections
reference sections of ASCE 41-17, but they supersede the application of ASCE 41 as the
basis of the design directly unless SRB approves.
Whenever a construction project on an existing building is planned, CEBC requires, if any
of the triggers defined in Section 317.3.1 are exceeded, a two-level structural
assessment of the seismic performance of the building, and possibly its modification, to
assure adequate seismic performance of the modified building.
For projects that include new construction that is not structurally connected to
above-grade existing elements, that is adequately separated from the existing elements
to avoid possible contact, and that share only below-grade basement and/or foundation
elements, CBC Part 2, Chapter 16 applies to the new construction.
CSU Seismic Requirements
February 15, 2024
Page 7
Seismic improvements are not required for the adjacent above-grade existing elements
unless required for another reason. It must be verified by rational analysis that loads
imposed on the existing below-grade structural elements by the new structure do not
compromise the gravity load supporting and lateral load resisting performance of the
existing structure as determined using the provisions of CEBC.
Even when no structural modifications are planned, CEBC may require evaluation and
modification of the structural system as a part of the construction project. The SRB has
determined for some specifically identified seismic priority buildings that the triggers for
CEBC are predetermined to require its application. The lists of such buildings are
discussed in Section 7.
Through this regularized assessment procedure, the University seeks to ensure, over
time, that its building stock will align with the current code-defined standard of
performance desired.
When the planned construction project incorporates existing structural elements into the
lateral force-resisting system of the modified structure, CEBC allows the use of the
resistance capacity of all existing structural elements that participate in the building’s
seismic response, even when those elements do not meet CBC requirements for new
construction. The provisions of CEBC apply to the entire structure.
The resistance capacity of the existing structural elements may be included in the lateral
force-resisting system using CEBC. New and existing elements may be jointly considered
to be part of the lateral force-resisting system only when the load-deformation
characteristics of each of the elements are considered and the forces are apportioned in
accordance with their relative rigidities. The rigidities assumed should be representative
of the conditions, including deterioration, and expected to exist at the maximum
seismically-induced cyclic deformations expected to occur at the seismic performance
level being assessed.
Building renovation cost levels defined in CEBC Section 317.3.1, Item 1, are cumulative
for alterations occurring after the effective date of the 1995 CBC. Any building alteration
whose cost exceeds the threshold requirement of this Item 1 must be reviewed to
determine if structural modifications are required to meet CEBC seismic performance
requirements. This requires an evaluation to assess that the building’s anticipated
seismic performance is adequate and may require a retrofit of the building.
Seismic retrofit is required only when the evaluation determines the building lacks
sufficient seismic force resistance to achieve the specified performance levels.
Determination if a Seismic Assessment is Required for Existing Building
Modification:
The assessment of whether a proposed modification of an existing building requires
seismic assessment and potential seismic retrofit depends on whether any of the five
triggers for the project in Section 317.3.1 are exceeded:
1. Total construction cost for the building, not including the cost of furnishings,
fixtures, equipment, or normal maintenance, exceeds 25 percent of the
construction cost for the replacement of the existing building. The changes are
cumulative for past modifications to the building that occurred after the
adoption of the 1995 California Building Code and did not require seismic
retrofit.
CSU Seismic Requirements
February 15, 2024
Page 8
2. There are changes in the risk category.
3. The modification to the structural components increases the seismic forces in, or
strength requirements of, any structural component of the existing structure by
more than 10 percent cumulative since the original construction unless the
component has the capacity to resist the increased forces determined following
Section 319. If the building's seismic base shear capacity has been increased
since the original construction, the percent change in base shear may be
calculated relative to the increased value.
4. Structural elements need repair where the damage has reduced the lateral-load-
resisting capacity of the structural system by more than 10 percent.
5. Changes in live or dead load increase story shear by more than 10 percent.
If any of the five triggers are exceeded or applicable, then an assessment is required that
could lead to a seismic retrofit being required for the proposed work to be allowed.
Whether Items 2 through 5 apply is determined by the design team. Item 1 requires an
assessment of all building construction-related activity since the effective date of the
1995 CBC (January 1, 1998). The key metric is whether the cumulative work done is 25%
or more of the cost of construction for the replacement of the building.
Item 1 shall be evaluated as follows:
a. Determine the current replacement cost of the building in its current condition,
not as improved.
b. Determine the cost of qualifying work for all projects since completion of the
building or January 1, 1998, whichever is later, including the total cost of the
proposed project. Prior project costs are not inflated to the present day. If the
ratio of the qualifying costs plus the proposed project to the replacement cost is
less than 15%, then the trigger is deemed not to have been exceeded.
This approach simplifies the trigger evaluation by eliminating the need to inflate
past costs to current costs.
c. Alternatively, determine the regional Engineering News Record (ENR)
construction cost index applicable to each qualifying project to inflate it to the
present cost basis. From these values for each project, compute the equivalent
present-day cost estimate, including the proposed project. If the ratio of
qualifying costs to the replacement cost is less than 25%, then the trigger has
not been exceeded.
The cost basis for Section 317.3.1, Item 1, does not include normal maintenance work:
ordinary upkeep and repair work such as replacement in kind, repainting, re-plastering,
and re-roofing. However, any work caused by an earthquake is not considered as normal
maintenance.
For either b or c above, if the building has been retrofitted to then-current CEBC
requirements, then the date for assessing qualifying costs begins when this work was
completed.
CSU Seismic Requirements
February 15, 2024
Page 9
If at any time, the construction cost of the project exceeds that used in either b or c and
the ratio is more than 15% or 25%, as applicable, the Building Official shall determine if
this is because of cost escalation or increase of the project scope; if the latter, then the
project must be reassessed to determine if the revised seismic retrofit cost ratio requires
evaluation and modification of the design. If it does, then the building shall be
immediately evaluated in accordance with the requirements of Section 7, and placed the
buildings on List 1, List 2, or No List.
When a seismic retrofit satisfying the requirements of Table 317.5 is completed, then
the cumulative total cost ratio is reset to zero and the effective date in Section 317.3.1,
Item 1, is advanced to the completion date of the seismic retrofit.
3.5 Code Enforcement
California State University is responsible for the enforcement of the CBSC. By delegation,
one person is designated as the Deputy Building Official (DBO) for that campus and its
other administrative locations. While the SRB is principally concerned with structural
issues related to design and modifications of new and existing buildings, design teams
must consider all 12 Parts.
When deemed necessary, the Building Official shall appoint a member of the SRB during
an emergency as an Emergency Designated Building Official (EDBO), see Section 6.
The EDBO is responsible for enforcing the requirements of CBSC to make the final
determination as it relates to structural and seismic safety when buildings or portions of
buildings at the campus can continue to be used or re-occupied. Another member of the
SRB may provide the technical review of the seismic aspects of projects and reports
findings to the EDBO, see Section 4.
CEBC Section 319.12 for existing state buildings states that, notwithstanding other
requirements of the code, voluntary modifications to the lateral force resisting system
are permitted under certain conditions. Among these is that:
5. A dangerous condition is not created.
CEBC Section 3.16.6 states that:
“… buildings in existencemay have the existing use or occupancy continued if such
occupancy was legal …, provided such continued use is not dangerous to life.
The term dangerous is not defined as used in these sections within the CEBC. The 2022
CBC defines dangerous as any building structure or portion thereof that meets any of the
conditions described below:
1. The building or structure has collapsed, has partially collapsed, has moved off
its foundation, or lacks the necessary support from the ground.
2. There exists a significant risk of collapsed detachment or dislodgment of any
portion, member, appurtenance, or ornamentation of the building or structure
under permanent, routine, or frequent loads; under actual loads already in
effect; or under snow, wind, rain, flood, earthquake, or another environmental
load when such loads are imminent. (2022 edition, CBC Section 202)
CSU has determined that for its buildings undergoing seismic upgrades, this term is
defined as:
A building is deemed dangerous if it does not satisfy the ASCE 41 S-5 performance
criterion based on BSE-R.
CSU Seismic Requirements
February 15, 2024
Page 10
Such a dangerous building determination must be peer-reviewed for accuracy based on
Method B of CEBC Section 321. Method A may be used for the design of the voluntary
seismic upgrade.
3.6 Active Faults
Faults capable of rupture can traverse campuses where construction is planned. It is
recognized that the locations of future fault ruptures are not specifically known, but
locations of past ruptures are good indicators of where the fault rupture may occur.
The California Geological Survey (CGS) delineates earthquake study zones along known
active faults in California. An active earthquake fault is defined as one that has exhibited
surface displacement within Holocene time (about 11,000 years) as determined by the
CGS under the Seismic Hazards Mapping Act of 1990, previously called the Alquist-Priolo
Earthquake Fault Zoning Act, or another authoritative source, federal, state, or local
governmental agency. The purpose of this Act is to prohibit the location of new
structures for human occupancy across the traces of active faults and to mitigate
thereby the hazards associated with fault rupture. Zone boundaries are generally drawn
about 500 feet from major faults and 200 to 300 feet away from well-defined minor
faults.
State agencies, including CSU, with jurisdiction over sites within an earthquake fault
zone regulate the development of projects within these zones, and the Trustees will
withhold development permits for sites within these zones until geologic investigations
demonstrate those sites are not threatened by surface displacement from future
faulting. These maps are available online from the CGS web address given in
Attachment F. In the case of a fault not zoned by the CGS, CSU will determine whether
an individual fault is active when there is sufficient evidence of an active fault traversing
a campus, and it will apply the requirements for investigations pending evaluation by
CGS of its status. The SRB determines the sufficient level of evidence regarding possible
fault zones and maintains maps of zones determined to warrant treatment as a fault
hazard zone. Currently enforced additional seismic hazard zones are identified in Table
1
of Attachment B under the heading Active Fault Zone.
When an active fault traverses a campus within a defined seismic zone as determined by
CGS or by the SRB for the subject fault:
All planned construction within the Earthquake Fault Zone shall have
detailed geologic studies of the building site to determine if a fault trace
passes through, or is within
50 feet of, the building perimeter. Such studies
shall be completed under the peer review requirements of Section
4.
The distance from a building to a fault is measured from the closest point of the
building, including its foundation, to the fault along a line normal to the plane of the
fault. No new building shall be constructed, or the existing building’s envelope
extended, where the closest portion of the building, including foundations, is less than
50 feet from an active fault. Where the geological assessment is determined to support
a smaller value than
50 feet, the SRB may approve the value on a case-by-case basis.
Campuses within a known active fault zone are identified in Table
1
of Attachment B.
The Building Official and SRB must approve the selection of the engineer for a site study
within a seismic zone before the initiation of the investigation. Once a geological study
is completed and the Seismic Peer Reviewer accepts the results, this study will provide a
basis for the design of the subject building for no more than five years after acceptance
CSU Seismic Requirements
February 15, 2024
Page 11
of the report by the Seismic Peer Reviewer, or a new study must be completed to
determine findings for the site consistent with current scientific and field investigations.
Within an Earthquake Fault Zone, CEBC applies wherever the structure is to be modified
without regard to its extent or purpose, notwithstanding the allowances of CEBC Section
317.3. Normal building maintenance and repairs of mechanical systems do not
themselves trigger retrofit requirements unless the replacement unit outweighs the
original unit by more than 10% and/or the supporting structural elements are altered.
For new determinations or relocations of fault locations at a campus, the SRB shall
evaluate the incremental hazard posed to all existing buildings within an Earthquake
Fault Zone and include this hazard in their overall evaluation of the seismic risk of the
building.
Where a portion of the building is removed as a part of the building modifications, then
the new perimeter of the modified building shall be used to determine if these
conditions are met. Such actions will trigger CEBC consideration without consideration of
the allowances for the triggers of CEBC Section 317.5.1.
These procedures apply only to buildings that are occupied, and not to storage buildings
that are not occupied by staff except for placement or removal of stored materials;
buildings where maintenance functions or other work are performed do not qualify for
this exemption. Under no circumstances should such buildings house chemical or
hazardous substances that, if released, could pose a toxic threat to the area around the
building.
3.7 Peer Review for Small Projects
For projects with a total project cost of $3,000,000 or less, and for any amount of
building element replacements-in-kind, or repairs and maintenance projects, the CDBO
is obligated to evaluate the nature of the contemplated work, and they may self-certify
compliance with these requirements (see also Section
5.5 Projects Not Warranting Peer
Review). The CBDO will notify the Building Official in writing of this determination. If the
proposed work involves increases in weight from that in place or modifies the structural
system as stated by the designer-of-record, then peer review is not optional. This topic
is discussed in more detail in Section 4.
3.8 Peer Review Verification
Verification that the construction documents comply with the CSU Seismic
requirements, including an acceptable plan check for compliance with the CBC and/or
CEBC, is a prerequisite to construction initiation. Seismic peer review verification shall
be documented by a letter of concurrence signed by the Peer Review. The letter shall
include specific references to the document set reviewed (i.e., date, revision number,
sheets, identification of the Engineer-of-Record (EOR), etc.) sufficient to identify the
project and the specific document set considered in the peer review. As construction
continues, the Seismic Peer Reviewer shall review as appropriate any changes that occur
to the design to assure that they are consistent with the approved plans and with CSU
Policy.
CSU Seismic Requirements
February 15, 2024
Page 12
3.9 Engineer-of-Record
All aspects of the structural design of a CSU project shall be under the responsible
charge of one licensed California Architect, Civil Engineer, or Structural Engineer that
serves as the EOR for the project through the completion of construction. The EOR shall
be determined at the beginning of the design process and shall not be changed in the
course of construction without approval by CSU. The structural design includes the
design of the structural frame, lateral force-resisting system, foundations, structural
aspects of the building skin/façade, and support and anchorage of equipment, building
systems, and architectural features. The EOR has responsibility for the structural aspects
of the entire project and must sign and stamp all final documents, including deferred
submittals, see also Section 5.13.
3.10 Responsibility of Design Professionals during Construction
The CSU recognizes that regardless of the project delivery method employed, the
approved plans for each project may be modified or supplemented during the
construction process. The University expects each licensed design professional engaged
in the design to review and approve all such modifications proposed within their area of
responsibility as a professional obligation before its execution. CSU project management
team members do not have the authority to approve substantive changes during
construction without the approval of the design professional and, where necessary, the
Seismic Peer Reviewer. The CSU project manager will document these approvals in
writing if the design team has not done so.
To assure the structural seismic performance of its buildings is consistent with the
approved plans, CSU looks to the design professionals (including Structural-,
Component-, Mechanical-, and Geotechnical-Engineers of Record and
Architect-of-Record) to directly notify the CSU of potential construction changes or
modifications to the approved design documents that can substantively impact
expected seismic or gravity load response performance.
CSU requires the responsible EOR, or equivalent person (e.g. Component Engineers of
Records), to make the structural/seismic assessments and to directly contact the Seismic
Peer Reviewer for consideration of and concurrence in the changes as specific
conditions warrant. This is similar to the process described for Delegated Design and/or
Deferred Approvals in Section
5.13. CSU has determined that all substantive changes to
the foundation system, vertical load-bearing system, and/or lateral load-resisting
system require such notification. This responsibility is a non-delegable professional duty
of the EOR regardless of the project delivery contract employed.
In some cases, the EOR, and/or contractor may advise the CSU that the original Plan
Check Agency review documents that have altered plans for compliance with the
approved design and the CBSC; delegated and/or deferred items from the original
approved plans are in this category. This is consistent with the delegated and/or
deferred approval procedures unless the change involves the seismic force-resisting
system in which case the Seismic Peer Reviewer must be involved. CSU shall cause these
reviews to be performed when it deems them necessary, which is any modification that
could be questioned on its technical impact on the structural performance of the
building. Each member of the project team, including the contractor, design team
members, and CSU project manager, will have various schedule imperatives. It is
important that where review or further plan check review is deemed necessary, that it
be initiated promptly, and that sufficient time is allocated to complete the review.
CSU Seismic Requirements
February 15, 2024
Page 13
3.11 Special Inspections
Chapter 17 of the CBSC requires the design professional to prepare special inspection
and testing requirements for a proposed project, the Owner to confirm responsibility for
their completion, and the Building Official to approve the proposed plan. CBSC requires
these to be listed on the permit drawings. The materials sections of the CBSC and many
referenced standards therein contain requirements for inspection that must also be
considered in the development of the testing and inspection program for construction.
The Chancellor’s Office maintains model forms that can be used as the basis for
preparing the required Special Inspections Program. Where there are deferred
approvals items, the special inspection requirements specific to the deferred work must
be prepared and submitted with the design documents for each deferred item. Special
inspections do not constitute Structural Observation.
3.12 Structural Observations
Structures requiring structural observation are identified in CBC Chapter 17 and as
required by the Building Official in consultation with the Seismic Peer Reviewer.
As discussed in Seismic Requirements Section 3.1, many CSU projects will trigger this
requirement because they are Risk Category III structures. Some projects will involve
structural observation of nonstructural components and systems. With the concurrence
of the Seismic Peer Reviewer, the approved structural design shall specify structural
observations required by the CBC and those recommended by the design team and
required by the Building Official. Component engineers of record shall specify structural
observations applicable to their designs on their drawings. This concurrence shall be
obtained prior to initiating structural observations. Unless otherwise agreed to by the
Building Official, the structural observation shall be performed by the design professional
specifying the structural observation. Documentation of the structural observations and
a statement regarding the resolution of observed deficiencies shall be submitted to the
Building Official.
4. PEER REVIEW
Peer review is a mandatory part of the construction process of the California State University
system. The seismic peer review is independent of the plan check requirement of the CBSC whose
principal focus is conformance with the CBSC requirements, not necessarily the total building
seismic performance and its reliability. CSU performs both independent peer reviews for fire and
panic safety, Mechanical, Electrical, and Plumbing (MEP) aspects of the design, as well as other
plan checks for Code compliance.
Peer review is to be performed for all building projects and all engineered structures, such as
trailers and bridges. Other construction activities may be referred for seismic peer review at the
discretion of the Building Official or CDBO. If the Seismic Peer Reviewer concludes that a seismic
peer review is not required, then a letter to this effect will be issued. This letter is an adequate
record of peer review of the project, provided the scope of the project does not change.
The purpose of peer review is to assure project quality, to provide a measure of additional
assurance regarding the performance and safety of the completed project, to provide advice on
methods and means, and to provide relevant specific campus information. When the peer
review of the design has been completed but aspects of the design are not complete because of
deferred submittals, discovered conditions, etc., then these should be identified in the reviewed
permit documentation and reviewed during the construction period when identified by the
EOR’s evaluation or the Seismic Peer Reviewer’s observations as having implications for the
CSU Seismic Requirements
February 15, 2024
Page 14
seismic performance.
Peer review is not intended to and does not replace the design responsibilities of the EOR.
Peer review is not a plan check for detailed determination of the compliance of the developed
plans to the requirements of applicable codes and standards.
Peer review is an objective technical review by an independent, knowledgeable reviewer(s)
experienced in structural design, analysis, and performance issues. The reviewer(s) shall
examine the available information on the condition of the building, the basic engineering
concepts employed, and the recommendations for action. This may include any structural
issues, seismic and non-seismic, necessary to achieve adequate building structural performance.
The SRB has assigned individual Seismic Peer Reviewers for each campus (Attachment C) and
will assign Seismic Peer Reviewers for locations not listed as needed.
The principal Seismic Peer reviewer may assign one or more qualified individuals to provide
independent review under their direction. The SRB will periodically review such assignments.
A Seismic Peer Reviewer performs a different service than an organization’s internal technical
review, a Building Official’s plan review, or a third-party plan check review. The peer review
provides the EOR with a qualified technical opinion on the adequacy of the structural
engineering approaches used and the resulting design. The peer review is not intended to check
the project for code compliance or to validate computations or conduct a detailed examination
of the retrofit design. Any such actions by the Seismic Peer Reviewer will be limited to those
deemed required to complete her/his responsibilities. A peer review is not the same as value
engineering but may include elements of value engineering. The purpose of value engineering is
to suggest alternative systems, materials, and methods for a project to reduce its cost or
improve its seismic performance. The purpose of the peer review is to assure that the seismic
response characteristics of the building are well-considered, appropriate, and acceptable.
Because the Seismic Peer Reviewer is responsible to review the expected seismic performance
characteristics of the buildings, in light of the Trustees’ Seismic Requirements and specific CSU
policies adopted to achieve this purpose, the review may exceed minimum building code
requirements in assessing the performance of the overall structural system(s).
The Seismic Peer Reviewer is responsible and accountable solely to the SRB and CSU Trustees
for their actions. Although the Seismic Peer Reviewer may advise the CSU Deputy Building
Official and CDBO on seismic-related code compliance issues, it is the Building Official who
retains the responsibility and authority for code compliance determination.
4.1 Scope of Review
Documents submitted for review shall include available construction documents,
geotechnical reports, observations of the condition of the structure, all inspection and
testing reports (including methods of sampling), analyses prepared by the EOR and
consultants, and the retrofit or repair design. Peer review is both site- and
building-specific and considers proximity to faults, and soils/geologic conditions.
The expected seismic performance characteristics for each building include the
geometry of the building, the structural system(s) proposed, lateral and gravity load
paths, and whether these are supported by design, calculations, and detailing in the
project documents. The review shall include consideration of the proposed design
approach, methods, materials, and details.
CSU Seismic Requirements
February 15, 2024
Page 15
Peer review tasks include any or all of the following:
1. Assess appropriateness of analysis and provide additional assurance of a highly
reliable design performance under applicable environmental loads and
conditions;
2. Suggest additional design options, analysis perspectives, and provide knowledge
of experience in materials performance considerations;
3. Provide constructive comments on work-in-progress;
4. Assist in achieving consistency of design and design approach among different
CSU projects and in expected retrofit project seismic performance;
5. Aid in communication regarding local conditions;
6. Provide technical assistance for the resolution of technical problems
encountered in the design and construction;
7. Communicate with SRB on technical issues and concerns with system-wide
implications;
8. Offer positive engineering input where new and/or innovative design or analysis
procedures are proposed;
9. Confirm that the design of seismic protection of nonstructural components in or
on the building is appropriately addressed and consistent with CSU’s desire to
limit earthquake damage.
10. During the construction phase, review additions and modifications to approved
drawings that may impact the seismic performance of the building.
The EOR for the project and University project manager shall provide the Seismic Peer
Reviewer with all available information determined by the Seismic Peer Reviewer to be
necessary for the completion of the peer review.
The effort undertaken in peer review is commensurate with the size and complexity, or
lack thereof, of the project, but shall not be limited so as to compromise the technical
reliability of the process.
4.2 Timing of Peer Review
The Seismic Peer Reviewer should be engaged for the entire project, from concept to
final construction, and should participate during early structural design to ensure
concurrence with systems proposed for the specific project. The peer review is
completed when the construction is completed, and an occupancy permit is issued.
Where the delivery method is Design-Build, including collaborative Design-Build, the
Seismic Peer Reviewer’s effort begins when the RFP is prepared, see Section 5.
4.3 Reports
The peer reviewer(s) shall prepare written reports to the CSU Project Administrator and
CDBO describing all aspects of the review performed to date, including conclusions
reached by the reviewer. Reports shall be issued, as appropriate, after conceptual
design, schematic design, during design development, and at the completion of
construction documents, but before their issuance for a permit. On phased projects, a
CSU Seismic Requirements
February 15, 2024
Page 16
report shall be issued after the completion of each phase. Such reports should include in
aggregate, as relevant, statements of the following issues:
1. Scope of engineering design peer review with limitations defined.
2. Status of the project documents at each review stage.
3. Design, performance, and loading criteria.
4. The ability of selected materials and framing systems to meet performance
criteria with given loads and the configuration.
5. Degree of structural system redundancy and the deformation compatibility
among structural and nonstructural elements.
6. Basic constructability of the retrofit or repair system.
7. Other recommendations as appropriate to the specific project.
8. Presentation of the reviewer’s conclusions identifying any areas needing
further review, investigation, and/or clarification.
9. Recommendations for actions.
The final report shall be prepared when all the peer review comments are resolved.
It shall indicate that in the Seismic Peer Reviewer’s opinion the design is appropriate for
construction. From time to time the design team may propose significant alterations to
the design during construction; the Seismic Peer Reviewer will assess their merits and
issue a letter reporting the recommended acceptance or rejection of the proposed
alterations. In those cases where they are accepted as is, a written acceptance note to
this effect should be sent.
4.4 Responses and Corrective Actions
The EOR shall develop corrective actions and other responses as appropriate, based on
the report submitted by the Seismic Peer Reviewer. Construction changes that affect the
seismic force-resisting system shall be reported to the reviewer in writing for review and
recommendations.
4.5 Distribution of Reports
Copies of reports, responses, and notices of corrective actions shall be submitted to the
University Project Manager for use and distribution, and the Building Official.
4.6 Design Professional Responsibility
Although the Seismic Peer Reviewer will exercise usual and customary professional care
in performing the seismic peer review, the responsibility for structural design is fully and
solely the responsibility of the design professional of record as outlined in the California
Business and Professional Code. The seismic peer review is undertaken to enhance the
quality of the design and to provide additional assurance regarding the performance of
the completed project consistent with the Board of Trustees’ direction of Section 1.
4.7 Resolution of Differences
If the EOR does not agree with the recommendation of the Seismic Peer Reviewer, then
the SRB shall resolve such differences. Peer review should be a cooperative process
between the structural EOR and project Seismic Peer Reviewer, both having the
CSU Seismic Requirements
February 15, 2024
Page 17
objective to produce a quality project. Direct and free communication between the EOR
and the project’s Seismic Peer Reviewer is vital to avoid misunderstanding. Despite this,
honest differences may arise between the EOR and the project Seismic Peer Reviewer.
In such cases, the EOR and project Seismic Peer Reviewer may determine the issue
under consideration and the solution adopted may be controversial and would benefit
from examination by the full SRB. Such cases will be presented to the SRB for
consideration, evaluation, and resolution. All interested parties will have the
opportunity to present their technical arguments to the SRB for its consideration.
The project’s Seismic Peer Reviewer will not participate in these proceedings as a
member of the SRB. The decision of the SRB will be submitted to the Building Official
with a recommendation of disposition.
4.8 Peer Review Contract and Cost
The Chancellor’s Office maintains a fully executed, system-wide master enabling seismic
peer review agreement with each Seismic Peer Reviewer. Terms and conditions, including
specific services and fees, have been fixed in these agreements. Peer review fees normally
are based on total project construction costs and shall not be amended without both
University’s and Seismic Peer Reviewer’s concurrence. Copies of the agreements and
amendments are provided for reference on the CPDC website. To authorize services under
these Agreements, the University need only execute a Service Order to the reviewer
assigned to its University and specify the fee and other relevant particulars.
5. SPECIAL CONSIDERATION
5.1 Private Buildings Constructed on CSU Land
When a private developer constructs a building on land owned or controlled by the
California State University or any of its foundations or entities, or the building is
expected to come under CSU control at a future date, the project shall be peer-reviewed
in accordance with the requirements of this document as recommendations made to the
design team as required for their considerations but not an expansion of CBSC
requirements for the project.
5.2 Geotechnical Investigations
Determination of the seismic loading conditions requires that the building site’s soils be
classified. Any geotechnical investigation conducted for a project shall include
consideration of all seismically induced site failure hazards, including liquefaction,
differential settlement, lateral spreading, land-sliding, and surface faulting.
Note that CSU has determined campus-specific seismic design ground motion
parameters to be used for new and modification of existing buildings that supersede
those in the CBC. These are given in Attachment B. The engineer preparing geotechnical
reports for projects at locations where the CSU values are prescribed need not do
additional site exposure work for determining CBC seismic design requirements unless
unique conditions are believed to exist.
5.3 EOR References to Geotechnical Investigation
Construction document directions to see soils reportare not permitted on CSU
projects. The Engineer of Record, not the contractor, is the responsible party to take
from the geotechnical report the relevant information and then conveying it as a part of
the construction documents; the geotechnical engineer shall remain responsible for its
contents of the geotechnical report and recommendations.
CSU Seismic Requirements
February 15, 2024
Page 18
The geotechnical report itself shall not be portrayed as a part of the construction
documents. The construction documents may reference the geotechnical report as a
‘supporting document’ (providing name, title, author, date, etc.) for the contractor’s
reference and if desired, state that the geotechnical report was relied upon in the
development of the construction documents. The Seismic Peer Reviewer will request a
review by the geotechnical engineer to confirm that the design reflects the geotechnical
recommendations of the geotechnical report.
5.4 Changes and Additions to Published SRB Requirements
The SRB may establish additional requirements relating to the design and construction
of new buildings, and the retrofit or modification of existing buildings that have yet to
be incorporated into these CSU Seismic Requirements. The assigned Seismic Peer
Reviewer is responsible for informing the project manager and design team of these
additional requirements as appropriate at the initiation of a project.
5.5 Projects Not Warranting Peer Review
By Trustee policy, all construction, whether above or below grade, requires a seismic
review determination. Where the CDBO determines that there are no structural issues
warranting a seismic peer review, the University shall submit project documentation to
the Seismic Peer Reviewer for an initial determination. If the Seismic Peer Reviewer
concurs, the Seismic Peer Reviewer will provide a letter documenting this to the
University. This letter shall satisfy the requirements of peer review for this project.
There is no charge to the University for an initial determination.
The CDBO is authorized to make an initial determination for projects with a total project
cost of $3,000,000 or less, non-structural tenant improvements of any amount if they do
not impact the structural system, building element replacements-in-kind, or repairs and
maintenance projects. Should a peer review be deemed warranted, the University shall
issue a Service Order Authorization for a seismic review of the project.
Special non-building capital project types that typically require peer review include
bridges, tanks, cellular towers, and field lighting that illuminates a surface 30 feet or
greater below the light fixture.
Special project types not required to be submitted for peer review generally include
under 30-foot tall streetlight and traffic components installed consistent with
Green Book (or equivalent) standards, public utility elements installed by a public
utility, storm drainage elements, and tree/palm installations not supported by
above-grade structural elements.
Student structures that are designed, constructed, and possibly used after
construction, whether by student labor or contractors, shall be peer-reviewed.
There is no charge for this peer review.
5.6 Demolition Projects
Demolition of existing facilities up to 45 feet total height from the lowest adjacent
ground plane generally does not require peer review. Taller structures and all planned
implosions require review. Even when not required, the SRB and campus Seismic Peer
Reviewer is available to the University to provide technical advice and counsel on such.
CSU Seismic Requirements
February 15, 2024
Page 19
5.7 Material Properties of Existing Buildings
Material properties (i.e., strength, stiffness, damping, mass) must be established on all
projects involving existing buildings where structural modifications are involved or
structural evaluations are required to determine load carrying capacity of structural
elements.
This may be established based on existing documentation (e.g., record drawings)
acceptable to the Engineer-of-Record and the Seismic Peer Reviewer or by a materials
testing program.
ASCE/SEI
41-16 prescribes the methodology for the degree of destructive and
non-destructive examination and testing to establish material properties and knowledge
factor (k) to be used in the analysis and design. Where testing is to be performed, the
Engineer-of-Record must define the destructive and non-destructive testing program
using the guidelines of ASCE/SEI
41. ASCE/SEI 41 Commentary states Where a
destructive and non-destructive testing program is necessary to obtain as-built
information, it is prudent to perform preliminary calculations on key selected locations
or parameters before establishing a detailed testing program.” The ASCE standard for
this notes the importance of obtaining this “knowledge at a reasonable cost and with as
little disruption as possible of construction features and material properties at
concealed locations”.
CSU encourages the EOR to use engineering judgment and experience and a preliminary
evaluation to establish a cost-effective testing program. In developing a testing
rogram, the following shall be considered:
Fewer tests may be justified based on the confidence conference level of
available information, uniformity of test results, and seismic or other loading
demands on the existing structural elements.
Phasing the testing program and using the results of the initial phase to qualify
the number of locations in a subsequent phase.
Focus the tests on critical structural elements.
Utilize different appropriate testing procedures (i.e., cores, Schmidt Hammer
tests, etc.).
The methods used to determine the material values must be approved by the Seismic
Peer Reviewer.
5.8 Design Build and CM at Risk Projects
Collaborative Design Build, Design-Build, Construction Manager at Risk, and other
project delivery systems (collectively called Design-Build) projects pose a special set of
issues for the application of the CSU Seismic Requirements.
As noted in Section
4.2, seismic peer review of a project shall be initiated by the
University when the project requirements and goals are in development, that is, well
before the request for proposals or qualifications is issued to potential performers.
CPDC maintains model procurement and contract language for use in Design-Build
procurement to assure that CSU seismic requirements are incorporated in the
procurement and implementation process. The intent is to ensure an adequate review
of the seismic requirements for the project when the specifications are written.
CSU Seismic Requirements
February 15, 2024
Page 20
The specifications shall clearly define the code requirements and seismic performance
requirements for the project, thus reducing the potential for additional charges in the
event of disputes regarding code interpretation and peer review.
The requirements for Design-Build projects include provisions that peer review, plan
check, and testing and inspection services are paid for and under the direction of CSU.
The contract may contain a provision that the contractor shall reimburse the University
under the contract for these services. In such case, it is agreed that their duties for the
project are to the University as representative of the Trustees, and not to the
contractor.
5.9 Moment Frame Structural Systems
The following requirements apply when special moment frame structural systems are
used. They apply to all moment frame structures, including concrete, masonry, and
steel:
1. Where rigid elements, such as ramps, exist in the structure, a detailed assessment of
the interaction of the ductile frame and rigid element shall be completed to assure
adequate post-yielding behavior of the structural system at the maximum expected
deformation.
2. Columns with variable, unsupported height shall be detailed to be ductile. As an
alternate, double-column support systems can be used to accommodate sections at
breaks in elevation, with seismic separations between the columns and slabs.
3. For parking structures, all concrete columns shall include confinement reinforcing,
even if they are not part of the designated moment frame lateral load-resisting
system of the structure. Ramps are to be included in the structural model used for
analysis, and the interaction effects and deformation compatibility requirements
must be included in the design of the structural system.
5.10 Post-tensioned Structural Elements
CSU Guidelines for post-tensioned concrete structures are found in Attachment E.
The Guidelines are not intended as direction to the design team, but as alerts to
important technical performance issues in the design that are likely to be of concern
during the peer review.
5.11 Alternate Methods of Construction
Construction assemblies not specified in the CBSC may be used provided that:
1. They have been accepted for use by the ICC Evaluation Service (ICCES), IAPMO, the
State Architect (DSA), or the Department of Health Care Access and Information
(DHCAI) and are used in accordance with the referenced research report or
approved memorandum for application.
2. The Building Official approves the application for alternate materials, alternate
design, and methods of construction under Part I, Chapter 1.2.3. The Building
Official may engage the responsible Seismic Peer Reviewer to examine technical
materials submitted in support of requests for alternate methods of construction
that have implications on the seismic performance of the resulting construction.
CSU Seismic Requirements
February 15, 2024
Page 21
5.12 Use of Engineered Wood Products
1. The use of equivalently rated oriented strand board (OSB) as an alternative to
plywood in shear walls and diaphragms is prohibited.
Exception: The use of OSB may be used in areas where exposure to moisture is
prevented during construction and use. Examples of where OSB shall not be
used include roof sheathing, exterior wall sheathing, and floor sheathing under
bathrooms and kitchens. Examples of where OSB may be acceptable include
interior wall sheathing and floor sheathing except beneath kitchens and
bathrooms.
2. Plywood used as a part of the seismic load-resisting systems shall be at least
15/32 inches thick.
3. Construction documents shall require the Contractor to protect OSB and plywood
during construction from exposure to water during construction and use. If OSB or
plywood deteriorates due to exposure to moisture, the material shall be replaced
unless it can be demonstrated to the satisfaction of the Engineer-of-Record and
Seismic Peer Reviewer that no loss of strength has occurred.
4. CSU supports the consideration of mass timber and variations of heavy timber
construction on an alternate means basis.
5.13 Delegated Design and/or Deferred Approvals
The CSU permits delegated design. The Architect and/or Engineer-of-Record (AOR or
EOR) shall identify the delegated scope of work on the drawings. Delegated design is
typically confined to specialty items such as pre-engineered metal buildings, proprietary
structural components or foundation systems, precast concrete, exterior cladding,
skylights, steel stairs, and mechanical, electrical, and sprinkler and plumbing anchorage
and bracing.
If a delegated design or other portion of the design is not submitted at the time of permit
application, it becomes a deferred approval. Deferred approvals are discouraged by the
CSU, and advance permission to defer approval must be obtained from the CDBO or the
Building Official.
To establish responsibility for the overall design and component design, the EOR has the
following responsibilities:
1. The EOR’s drawings shall list all delegated designs and/or deferred approvals that
require EOR review. This list shall be reviewed by the Seismic Peer Reviewer.
2. The EOR shall establish component design criteria. These criteria shall be reviewed
by the Seismic Peer Reviewer before approval of the project. The criteria shall be
placed on the EOR’s drawings. If criteria are detailed in the specifications, the
drawings shall reference the relevant specification section.
3. The Component Engineer of Record (CEOR) shall provide, at a minimum, the
following:
A. Calculations indicating design criteria, applicable loads, properties, and
deformation analysis as required by the construction documents.
B. Plans and details indicating all structural elements of the component,
including appropriate profiles, connections, welding, bracing, and
attachments to elements designed by others.
CSU Seismic Requirements
February 15, 2024
Page 22
C. Statement of required testing, special inspection, and structural observation
of each component design shall be listed on the component drawings.
Note that the Building Official and CDBO reserve the right to require
additional testing, inspection, and structural observation.
4. The EOR shall review all delegated designs and/or deferred submittals listed on the
EOR’s drawings and consider all structural modifications to the approved plans that
are proposed during construction. At the beginning of the construction phase, the
Peer Reviewer and EOR will determine the conditions that warrant Peer Review. The
EOR review shall confirm conformance with the component design criteria and
coordination with the overall structural design including the ability of the structure
to support all component loads. The Peer Reviewer shall review all structural
modifications presented by the EOR that warrant review to confirm that the
modifications are appropriate. The Peer Review in conjunction with the responsible
CSU Project Manager shall determine if and when the modifications warrant
independent plan review or not.
5. The EOR shall issue a signed and stamped letter confirming that the design satisfies
the component design criteria, building code requirements, and applicable design
standards. It shall confirm that the component design has been coordinated with the
overall structural design and that structure is capable of supporting all component
loads. A shop drawing stamp is not an acceptable alternative to this letter.
The following is a typical stamp for this purpose:
6. The EOR shall annotate the component drawings to clarify work done under their
responsible charge, if this is the case.
7. Responsibilities of the EOR and CEOR during construction shall be as described in
Section 3.10.
5.14 Pre-engineered Structures
Pre-engineered structures frequently, used without alteration, may have certificates
from ICCES or other certification authorities. These are provided in place of
project-specific engineering calculations demonstrating adequate seismic performance
for the project for a specific level of seismic demand. These and the vendor’s technical
documents usually contain requirements for installation that must be followed for the
certificated performance to be achieved. Other pre-engineered structures have
project-specific designs.
The following requirements apply to such pre-engineered structures, which may include
“Butler”-style buildings, awnings, bridges, and antennas. All such structures must have
design documents signed and stamped by a California professional engineer.
When the pre-engineered structure is free-standing, with an acceptance certificate
applicable to the site’s seismic coefficients, then the structure may be accepted for CSU
use without peer review of the seismic characteristics of the structure itself.
The structure shall be consistent with the size and framing depicted on the certificate,
The EOR has reviewed the components engineered by others for
conformance with the component design criteria and has verified that
the structure can support the components as detailed. The EOR
established the component design criteria but was not in responsible
charge of the component design.
CSU Seismic Requirements
February 15, 2024
Page 23
and there shall be no applied loads to the structure other than its self-weight and
resulting environmental loads. This precludes adding floors or mezzanines to such
structures or replacing storage racks or equipment that are braced to, or supported by,
the structure. Piping, lighting, and similar elements may be attached to the structure
only insofar as the manufacturer’s specifications allow. Where the proposed structure
has mezzanines, added floors above grade, or there is a basement below the structure,
then the structure shall be peer-reviewed.
When the pre-engineered structure is not free-standing, such as an environmental cover
on a roof, an awning, a cellular antenna, or similar addition to an existing building, and
the element has a certificate applicable to the site’s seismic coefficients, then the
element may be used without peer review of its seismic performance provided the
design limitations of the certificate are met and the structure to which it is attached is
verified to be able to accommodate the applied gravity, wind, and seismic loads. If the
pre-engineered structure’s certificate of approval does not specify for foundations or
anchorage to other structures, such as for a cellular antenna, the foundation design
shall be peer-reviewed. Submittals shall include the acceptance certificate for the
structure appropriate to the seismic environment of the site and structural calculations
and design documents from a licensed California Professional Engineer The calculations
shall confirm the ability of the structure to support loads imposed by the pre-engineered
structure.
Trailers or other transportable structures subject to Caltrans, not Title 24, regulations
are considered to be pre-engineered structures and peer review is not required. When a
trailer is placed and either the wheels are removed and/or are not in contact with the
ground, then CSU seismic requirements apply. The peer review shall focus on the lateral
bracing of the installation and not the unit itself, except as required to verify the
capacity of the anchor points to transfer applied lateral loads.
If the structure’s certificate of approval does not specify foundation requirements, such
as for a cellular antenna, the foundation design shall be peer-reviewed. Submittals shall
provide the ICCES or equivalent certificate for the structure appropriate to the seismic
environment of the site and a report from a licensed California Professional Engineer
that the foundations are capable of performing acceptably under the applied seismic
loads, and these documents shall be peer-reviewed.
Structures with attachment requirements to other structural elements of existing or
new construction, such as an entrance cover, or for a portable classroom (trailer), shall
have the attached documents peer reviewed. The construction documents shall provide
information applicable to the site’s seismic coefficients, and a report from a California
licensed architect or a civil or a structural engineer that the structure to which
attachment is made is capable of performing acceptably under the applied seismic loads
and these shall be peer-reviewed.
Pre-engineered metal buildings (PEMB) without acceptance certificates shall be
peer-reviewed. Foundations for this type of building are nearly always designed by
another professional engineer using loads provided by the PEMB engineer.
The foundations shall be peer-reviewed. Submittals for both peer reviews shall include
structural calculations and design documents from a California Professional Engineer.
The PEMB engineer shall also submit a letter confirming that the correct loads have been
used in the foundation design.
CSU Seismic Requirements
February 15, 2024
Page 24
PEMB design drawings shall be complete, shall present the structural information
required by CBC Section 1603.1 and AISC 341 Section A4, and shall represent the
structure independent of shop drawings or piece drawings. Foundation loads are to be
shown on the PEMB drawings and foundation drawings. Details, elevations, and sections
shall be properly referenced, and symbols used on the drawings shall be clearly defined
in the design drawings. All distributed and point loads shall be shown on the drawings
and be included in the design, including suspended lights, ceilings, MEP units, storage
areas, as well as any other loads the structure is to support. Components of these
buildings must be acceptable per the CBC (e.g., materials and connectors must have
ASTM or AWS designations and/or ICC approvals), or test results prepared by an
independent testing laboratory must be submitted to justify values used in the structural
design.
A PEMB designed by the manufacturer that does not comply with the first four
paragraphs of this section is to be reviewed by the Seismic Peer Reviewer.
Foundations for this type of building are often designed by an independent structural
engineer. As there can only be one structural engineer of record for the building per
Section 3.9, the Structural Engineer of Record (either the independent structural
engineer or the engineer responsible for designing the PEMB) must take responsibility for
the overall design and must review and sign all the design drawings. This responsibility is
normally, but not necessarily, taken on by the structural engineer responsible for the
design of the foundations.
5.15 Designated Seismic Systems
Most CSU projects do not include Designated Seismic Systems (DSS), as defined in
CBC Chapter 2 and ASCE 7 Chapter 13, e.g., emergency generators, critical switchgear,
etc. For those that do, and for all buildings designated Risk Category IV, the DSS shall be
identified within the construction documents by the Mechanical/Electrical/Plumbing
Engineer with concurrence by the EOR. The DSS seismic qualification requirements of
ASCE 7 Chapter 13 apply. Qualifications must be at or above the BSE-1 ground motion
level of ASCE 7 for mechanical and electrical elements.
In addition to project-specific qualification, the CSU will permit the use of a DSS if it
satisfies the requirements of Section 5.11.1, and the intended use of the equipment is
consistent with the DSS certificate of compliance.
5.16 Phased and Voluntary Retrofit
Voluntary lateral-force-resisting system modifications allow seismic enhancements to
buildings to be implemented when CBC 317.3 and CSU Seismic Requirements do not
require a seismic retrofit. Projects on Priority List 1 and List 2 buildings may have partial
or phased retrofit corresponding to the requirements of the CEBC with the restriction
that a date (Section 317.6) approved by the Building Official is given for the completion
of the total retrofit. Notwithstanding the allowances for seismic retrofit actions, other
CBC requirements for the specific project, e.g., accessibility, fire, and life safety issues,
must be completed before the seismically modified building may be lawfully occupied.
If the approved date is not met, then at their discretion, the CSU Building Official can
direct the building to be vacated until such work is completed and a certificate of
occupancy issued.
Buildings not on List 1 or List 2
may have voluntary seismic retrofits consistent with the
requirements of CEBC Section 319.12
. All phased retrofits require written concurrence
CSU Seismic Requirements
February 15, 2024
Page 25
from CPDC. The request shall be signed by the University Vice President for
Administration. A confirming letter from the CPDC Assistant Vice Chancellor and
co-signed by the Building Official shall be required for such a plan to be considered
approved. The construction documents shall indicate how the work shown thereon
corresponds to the approved phased retrofit.
5.17 Final Approval
Acceptance and completion of a construction project is contingent, in part, upon the
written representation by the Architect/Engineer that the permitted plan has been
implemented and that changes or deferred approvals for the project were completed
with her/his written approval. A written statement will be provided by the Seismic Peer
Reviewer that the reviews have been performed and that issues raised during
construction and brought to the Seismic Peer Reviewer’s attention were satisfactorily
resolved. A written statement will be provided by the CSU project manager that issues
raised during construction were satisfactorily resolved.
5.18 Earthquake Soil Pressures
Lateral pressures on the basement or retaining walls, as well as other below-grade
structures or elements, shall be designed and reviewed for loadings due to earthquake
ground motion based on established procedures. The following shall be considered:
a. The horizontal pseudo-static acceleration shall be taken as ½ (one-half) of the
Site-Class adjusted BSE-2N (MCE
R
) peak ground acceleration value (PGA
M
) for
new buildings and ½ (one-half) of the Site-Class adjusted BSE-C peak ground
acceleration value for existing buildings from Table
1 of Attachment B of the
CSU Seismic Requirements. The vertical pseudo-static acceleration shall be
taken as zero.
b. The applicable lateral soil pressure is the active total earth pressure, including
the static active earth pressure and seismic increment. These earth pressure
components should include consideration of sloping ground conditions adjacent
to the wall or below-grade structure, as well as long-term surcharge loads
present within the active earth pressure zone of influence. The lateral load, H, is
a result of this total active earth pressure.
Soil pressure applied to structures or elements of structures due to differential ground
deformations shall also be considered in the design if the geotechnical evaluations of
site conditions suggest that there is the potential for seismically-induced geo-hazards
(e.g., settlement, lateral spreading, etc.) to be experienced at the site during earthquake
ground shaking. Such consideration may include the loss or increase of lateral or vertical
support due to ground movements.
Passive lateral resistance provided by below-grade soils against elements of the
foundation (e.g., footings, grade beams, piles and pile caps, walls, etc.) or subsurface
utility pipes, tunnels, or appendages structurally connected to the structure in analyses
of a structure shall be evaluated based on deformation compatibility of the foundation
elements.
CSU Seismic Requirements
February 15, 2024
Page 26
5.19 Temporary Use of Buildings and Structures
The CBC defines temporary in relationship to buildings as follows:
TEMPORARY: Buildings and facilities intended for use at one location for not more
than one year and seats intended for use at one location for not more than 90 days.
For seismic evaluation purposes, CSU defines temporary use for a period of not more
than 14 days. The CDBO may choose to define temporary as less than 14 days for other
environmental loads.
When a building has been designed based upon a specific [structural] Risk Category, I, II,
III, or IV, this limits occupancy of a building to its approved occupancy type and numbers
until other Code-based actions are taken to change it (i.e., A Special Event permit).
From time to time, a University may temporarily wish to use a building space in a way
non-conforming to its approved normal occupancy. When such is proposed, then the
CBDO shall make a determination that the hazard and risk posed by this use are
acceptable and consistent with the direction of CBC Section
108.2. For the temporary
use to be allowed, the CDBO must approve in writing the planned use, which shall
specify the occupancy type and occupancy load compared to the approved use and
propose, where appropriate, the specific mitigation steps to be taken to manage the
risk; such steps may include fire watches during occupancy, pre-notification or
positioning of emergency responders, etc. For terms exceeding seven days, a specific
evaluation by a registered structural engineer must be made to determine the extent of
the risk posed by this use for review by the CDBO in deciding to authorize such
use.
When the temporary structure is a membrane structure, including tents of all types, to
be used for a specific temporary purpose, there are special requirements that must be
met. The California Fire Code (CFC) has prescriptive requirements in Sections 3104 and
3105 that govern the use of tents that extend beyond just fire hazards. They characterize
temporary as 180 days or less use. The CFC references the CBC for structural issues, but
they are the principal focus of regulations of temporary structures such as tents and
stages, covered or not.
It is CSU Policy that whenever a tent or stage, whether covered or not, is to be used as a
temporary use structure, then the use of that tent is regulated by CFC Section 3104
(tents) and 3105 (temporary stage canopies) and that to receive a temporary use permit
for 45 or fewer days requires submission of the documentation requirements of
Section 3105.5 to the Fire Marshal and the responsible CDBO for review and approval.
Note that the Fire Code applies these sections to 3105 structures only, but that CSU
requires the same reporting requirements for Section 3104 structures.
For CSU applications, the design documents and design calculations are to include
structural and inspection requirements, including the reliability of the building for
gravity and wind loadings. CSU requires that documentation be provided to verify these
performance issues for both Sections 3104 and 3105 applications. Where hold-down
devices are used to stabilize the structure, then special inspection of the installation is
consistent with CBC code requirements for such elements.
5.20 Suspended Ceilings
CSU adopts CBC Section 1617.11.16, Item 3, requirements for (metal) lay-in panels, and
Item 4 requiring lateral force bracing for suspended ceilings 144 square feet (SF) in area
or larger.
CSU Seismic Requirements
February 15, 2024
Page 27
6. POST-EARTHQUAKE REVIEWS
When an earthquake occurs near a CSU campus or facility, there is need for evaluation of the
safety of buildings and facilities at the campus. Under Section 3.5, an assigned EDBO is
responsible for the University’s safety reviews. After any significant seismic event, the EDBO will
contact the University to determine if damage occurred at the campus. From authority from the
Building Official and the Chancellor’s Office, the EDBO has been authorized to evaluate the
safety of buildings on campus and make recommendations for additional engineering
investigations to determine the condition and appropriate actions to repair individual buildings.
When so notified, the University Police will restrict occupancy or entry of all buildings on
campus to those authorized by the EDBO to enter buildings to determine their structural safety.
Following evaluation, all campus buildings will be posted as:
Safe for lawful occupancy (Green);
Restricted entry (Yellow), with the limitations on entry explicitly stated on the
placard; or
Unsafe for entry (Red). If warranted, the assessor shall give notice to the University
Police to enforce compliance with no-entry if the building may pose a collapse hazard
under gravity loads or in aftershocks.
These designations shall be enforced to limit the risk to occupants until such time as the placard
is modified or removed. In some cases, the reason for a red tag may be that the building is not
to be entered or used until an inspection is completed to assess the appropriate tagging.
The safety designation of any building may only be altered by the EDBO who posted the building
or by the Building Official. From time to time, it is expected that re-postings may increase or
decrease the rating of the building, depending on new information or possibly additional
damage occurring.
The restoration of the University and campus facilities shall be completed to the requirements
of CEBC and these CSU Seismic Requirements. Plans for all repairs shall be approved for
implementation by the EDBO or the Building Official. The plans shall be peer-reviewed as
determined by the EDBO. With suitable record keeping, the reviews and plans may be
developed and implemented rapidly with appropriate approvals. Where emergency shoring is
required to stabilize a building to prevent its further deterioration, the scheme and plans for
shoring shall be peer-reviewed. Upon peer review acceptance, under such situations, such
designs are approved for construction. After a suitable period, as determined by the
Chancellor’s Office, the CDBO will reassume the responsibility for review and approval of the
repair of damaged buildings.
The SRB has determined that welded steel moment frame (WSMF) buildings constructed to
engineering procedures used prior to
1995 may be subject to significant damage that is not
readily apparent without detailed investigation. When an earthquake occurs, all CSU WSMF
buildings permitted before 1995 in the region of strong motion exceeding 0.20g peak horizontal
acceleration or a WSMF that has been reported damaged nearby shall be inspected to determine
the conditions of their welded connections, even if the building shows no outward signs of
damage. At the direction of the EDBO, such investigations shall be completed for all WSMF
buildings assessed to have been subjected to ground motions sufficient to have potentially
caused WSMF connection damage.
During the post-earthquake period, it may be necessary for a building to be condemned because
its structural system is deemed in such a condition that repair is not practical or that the building
poses an unacceptably high seismic threat to other buildings. The EDBO has the authority to
CSU Seismic Requirements
February 15, 2024
Page 28
condemn buildings subject to concurrence by the Building Official. Condemned buildings shall be
demolished as soon as practical; in the interim period, the University shall take reasonable
actions necessary to limit the possibility of injury to the public.
7. CSU SEISMIC BUILDING ASSESSMENT PROCEDURES
Seismic risk management decisions depend on risk assessments based on professional
judgments. Some judgments are predictive and can be verified when the outcome becomes
known in a short to medium time period. However, many judgments are unverifiable in part
because of the period over which they apply. Determining the acceptable seismic performance of
a building falls in this latter category. The quality of such judgments can be assessed only by the
quality of the thought process and information that produced them. The seismic risk
management program for the CSU building stock has been underway since 1993 and was
modified in 2022, to formalize the procedures and to institute a program to systematically assess
and reassess buildings regularly. The objective is to provide prudent, legally defensible, and
transparent risk management decisions. The goal is to distinguish seismically Good from Bad
buildings quickly, with limited information and great uncertainty, and then determine how
limited resources should be used to the greatest advantage by distinguishing really bad buildings
from those that are so-so Bad. The procedure is based on modified FEMA P-154 as discussed in
Attachment G. When a building is evaluated, the results can be several:
based on the evaluation
results and its reliability rating of the assessment as evaluated by the SRB, a building can be
assigned to one of three dispositions representing the priority assessed for dealing with the
seismic hazard posed:
CSU has used for over 20 years a system of identifying building hazards as follows:
List 1: A building posing a significant risk that warrants detailed seismic assessment and
retrofit to be implemented as soon as funds are available to do so.
List 2: A building posing a sufficient risk to warrant detailed seismic assessment when any
work requiring a permit is undertaken at the owners initiative, whether the
applicable Building Code requires it or not.
No List assignment for a building that has a seismic vulnerability that does not warrant
assignment to Lists 1 or 2. When any work requires a permit where a trigger limit
applies for evaluation and retrofit.
The new procedure allows the assignment to these lists the following Decision Rule:
Decision Rule: The decision on List assignment for an assessed building is to be made
based on allowing an R(t, ,
2
) acceptable upper bound limit as follows:
1. If the reliability of the building’s quality assessment is less than 0.30, then the
SL2 assessment is provisionally not prudent for decisions, and a more reliable
assessment needs to be performed. This can be done by improving the methods
or information available to the assessor to achieve at least a 0.30 rating and/or
by performing a more reliable engineering assessment procedure (e.g., detailed
building investigation and engineering analyses).
2. If the building’s Risk Class is I, II, or III (if not housing CEBC-restricted quantities
of hazardous materials) and the quality of the assessment’s performance is 0.30
or better, then provisionally:
Assign to List 1 if SL2 ≤0.3. This is equivalent to establishing a priority that
the building is seismically assessed and retrofitted to meet CEBC Section 3.17
CSU Seismic Requirements
February 15, 2024
Page 29
requirements as soon as practical, notwithstanding whether any other work
is to be done.
Assign the building to List 2 if 0.3 SL2< 0.7. This means that the CEBC
Section 3.17 trigger limits do not apply. If work requiring a permit is
proposed, then it is required to seismically assess and retrofit the building to
meet CEBC requirements.
Do not assign to a list if SL2 0.7; This is equivalent to letting CEBC Section
3.17 control seismic improvement based on permit applications and whether
any of the threshold’s triggers requiring seismic assessment and related
retrofit have been exceeded.
3. If the building’s Risk Class is III and the reliability of the building’s quality
assessment performance is 0.30 or better, then the following score limits apply
only for those buildings having Risk Category III hazardous materials storage:
Assign the building to List 1 if SL2 ≤0.7. This is equivalent to establishing a
priority that the building is seismically assessed and retrofitted to meet CEBC
Section 3.17 requirements as soon as practical, notwithstanding whether
any other work is to be done.
Assign the building to List 2 if 0.7 SL2< 1.0. This means that CEBC Section
3.17 does not allow any option other than to seismically assess and retrofit
the building to meet CEBC requirements.
Do not assign the building to a list if SL2 1.0; This is equivalent to letting
CEBC Section 3.17 control seismic improvement based on permit applications
and whether any of the threshold triggers have been exceeded, which
requires assessment.
4. If the building’s Risk Class is IV and SL2 ≤2.0 and the reliability of the building’s
quality assessment performance is 0.30 or better, then provisionally assign the
building to List 1, unless 1.5<SL2<2.0, then assign it to List 2.
5. The Building Official will consider the results of this assessment process and its
basis and consider whether the provisional dispositions are appropriate or not.
According to its professional judgment, the CB will assign the final score and
recommend the appropriate Priority List to the Chancellors Office.
The full text of the Assessment Procedure and its application can be found in papers by
Thiel and Zsutty (https://juniperpublishers.com/cerj/pdf/CERJ.MS.ID.555857.pdf, and
https://juniperpublishers.com/cerj/pdf/CERJ.MS.ID.555858.pdf) of how the assessments
are done, and the technical basis of how the methods were developed. It is important to
note that the FEMA 154 approach has been significantly modified and that the CSU has
included a formal method of evaluating whether the assessment procedure used is
technically adequate and appropriately applied. The application of the method results in
one of three assignments: List 1, List 2, or No List. Experience suggests that since there is
no mandate for the steps that need to be taken to make the hazard incurred more
obvious. The following actions become necessary:
1. When a building is newly assigned to List 1, then the Chancellor’s Office shall
sponsor a detailed engineering evaluation of the building’s expected
performance when funds become available. The intent is to determine the type
and extent of retrofit work required to meet the CEBC seismic requirements.
In essence, this proposed additional requirement is to serve to develop a
provisional approach to retrofit such that the University can have a clear
CSU Seismic Requirements
February 15, 2024
Page 30
understanding of the amount of work necessary to make the building seismically
safe. Such a study should be conducted under the review of the SRB and be
completed within no more than two years of the date the building is assigned to
List 1. Although desirable for planning, no such additional evaluation work
would be required for buildings on List 1 that predate the approval of this
assessment process, or for those buildings placed on List 2.
2. When a building has been on List 2 for 20 years since its assignment, it shall be
moved to List 1. This suggests that the probability of collapse is less than or
equal to 2% and more than 0.8% in the prior 20 years and in 30 years if nothing
is done less than or equal to 4.9% and more than 2%. A 2.0% minimum
probability is deemed unacceptable. In the intervening time, there may have
been a CEBC evaluation completed as CEBC requires, then one of two conclusions
could have been reached: the building is not hazardous, in which the SRB would
have removed it from List 2, or, the University has chosen not to implement the
planned permit modifications. Promotion of the building to List 1 does not
require assessment and retrofit; it means that a permit is required for a
modification if the CEBC requires it. By placement on List 2, the building has been
identified as one that needs seismic performance attention as a priority.
Action should not be delayed until there are other programmatic needs to
modify the building.
3. We understand that the Chancellor’s Office has recently initiated the
incorporation of the List 1 and List 2 status of campus buildings into its annual
capital allocation including consideration of seismic safety as one of several
considerations for making allocations. The SRB endorses this and urges that
University Planners use their SRB seismic reviewer as a resource in
understanding the consequences of how allocations are made.
The Seismic Review Board regularly evaluates the buildings on each campus and
off-campus facilities to determine if changes in the understanding of seismic hazards
and/or structural performance warrant specific actions to moderate the seismic risk of
specific buildings.
It should be noted that prior lists of buildings on which the current lists were based were
determined by different procedures in the past from those now used. In time all CSU
buildings will be assessed using the new procedures.
8. PROJECT PLANNING
8.1 Priority Lists
The Chancellor’s Office maintains a seismic three-priority list of buildings identified by
the Seismic Review Board for which there are additional seismic retrofit requirements
above and beyond the seismic requirements of the CBC. These are:
List 1: These buildings are a priority for seismic retrofit and should be retrofitted as
soon as resources are available without regard to other modifications of the
building. The list is in two parts, those that are occupied and those that are not:
Part A (CSU – Seismic Priority List 1A) are buildings that are in use and regularly
occupied. For these buildings, CSU has administratively determined that whenever
any work which is betterment, that is, not maintenance or repair, is performed to
CSU Seismic Requirements
February 15, 2024
Page 31
the building that a CEBC seismic evaluation shall be performed and the building
retrofitted to CBC seismic performance requirements notwithstanding the CEBC
triggers of Section 3.17, which may allow nonmandatory seismic evaluation.
Seismic Priority List 1A designation does not necessarily require that the building
be placed in limited or restricted use; however, the final determination will be
made by the Building Official based on recommendations from the SRB. In addition
to the CBC requirements, CSU has administratively determined that whenever any
work, excluding routine maintenance or minor repair exempt from a permit as
listed in the California Building Code (CBC), is performed on a Seismic Priority List
1A building, a seismic evaluation shall be performed and the building retrofitted to
satisfy California Existing Building Code (CEBC) seismic performance requirements
and CSU Policy.
Part B (CSU – Seismic Priority List 1B) are buildings whose seismic risk has been
mitigated by not allowing permanent occupancy by any staff in the building and
by limiting their use to storage and where the building's failure would not cause
potential injuries to those outside the building. Occupancy is limited to the
occasional entrance to place or retrieve stored items, with no office functions
performed. (This may be achieved by fences and other means.) Seismic Priority
List 1B designation indicates a building that can be used for storage, not
including any toxic materials that could pose a threat to people outside the
building. A CEBC seismic compliant retrofit consistent with the CSU Seismic
Requirements must be completed prior to any additional type of use of the
building. Whenever any work, including routine maintenance or minor repair,
and/or including work exempt from a permit as listed in the CBC, is performed
on a Seismic Priority List 1B building, a seismic evaluation shall be performed,
and the building retrofitted to satisfy CEBC seismic performance requirements
and CSU Policy.
Once designated, the building cannot be used by occupants as a normal building
without demonstrating that the building has been modified to the safety
requirements of these CSU requirements to allow occupancy.
List 2: (CSU – Seismic Priority List 2) are those buildings that must be evaluated and
retrofitted if non-compliant with CEBC requirements when a major capital
project is allocated to the building, notwithstanding an allowance from CEBC to
not do so. For these buildings, CSU has administratively determined that the
seismic evaluation of Section 317.5 is required, notwithstanding whether the
Section 3417.3 triggers are exceeded. Seismic Priority List 2 designation
indicates a building that, when a major capital project is allocated to the
building, must be seismically evaluated for compliance with CEBC seismic
performance requirements if its detailed engineering analysis indicates such is
required, regardless of whether or not the project exceeds the code triggers.
If the evaluation indicates the building does not satisfy the code requirements,
then the necessary seismic improvements must be included in the project.
These lists are regularly updated and maintained on the CPDC website.
Seismic evaluations and retrofit for buildings not on these lists may be required by the
CEBC.
The Chancellor’s Office has recently initiated incorporating the Lists 1 and 2 buildings in
its annual capital allocation inclusion process for consideration of seismic safety as one
CSU Seismic Requirements
February 15, 2024
Page 32
of several considerations of making allocations.
Changes in the use of an existing building trigger the seismic evaluation by CEBC of an
existing building. Where a portion or all of a List 1 or 2 building’s use is proposed to be
changed and there are no structural modifications of the building, then the following
information shall be required for consideration in the approval of the altered use plan:
1. Determination by the Building Official whether the proposed change triggers
under the CEBC whether a seismic evaluation is required by Section 3.7A of these
CSU requirements. If it does, have it completed as part of the review.
2. The total number of rooms and their total square footage are affected by the
changes, in relation to the building's total SF.
3. A detailed listing of the proposed changes, including items to be removed and
the nature of the subsequent repairs and patching.
4. Confirmation that the proposed change of use (such as conversion from lab use
to lecture/classroom use) will not result in an increase in the building's
assignable square footage or occupant load, or individual room occupant
loading exceeding the existing occupancy or 50, whichever is greater.
5. Confirmation that the proposed changes and/or change of use do not trigger
associated fire protection or accessibility requirements or improvements.
The CDBO shall consult with and receive concurrence from the Building Official before
approval.
8.2 Project Considerations
All planned projects shall meet the specific technical requirements of the CBC and/or
where applicable, CBEC, as detailed in previous sections of this document. A building
meets the CSU requirements for seismic performance if it provides essential life safety
to its occupants as required by these CSU requirements.
The requirements of the CBC, including Chapter
16 for new buildings, and CEBC Part 10
for modification of existing buildings, provide the minimum standards for construction.
In many cases, modification of an existing building may not trigger seismic improvements
to meet the requirements of CEBC or other structural provisions of Title
24.
Some occupancies for buildings under the CBC required higher than standard seismic
performance (e.g., educational facilities having over 5,000 occupants, emergency
operations centers, buildings with significant quantities of highly hazardous materials,
etc.) and must be designed and constructed to achieve the required performance levels
consistent with the assigned CBC Risk Category.
The Trustees’ Seismic Requirements require that all projects shall include consideration
of the projects’ seismic safety implications and shall evaluate the practicality and cost of
protective measures against the severity and probability of injury resulting from seismic
occurrences. This applies to all projects, including those that do not trigger
CEBC-mandated evaluations of the structural system.
Planning for all capital projects, regardless of size, shall address potential options
considered to improve seismic performance beyond minimally required code
conformance. The University shall document in writing the basis for the determination
CSU Seismic Requirements
February 15, 2024
Page 33
of the option selected for implementation.
It is important to note that meeting the seismic design and construction practices
described herein does not provide protection of property or equipment from
earthquake destruction or provide for the rapid restoration or maintenance of the
buildings functions or use after an earthquake.
9. SEISMIC SAFETY STANDARDS FOR ACQUIRING BUILDING AND SPACE
It is the Standard of California State University (CSU) to acquire buildings and/or spaces in
buildings owned by others that provide adequate seismic life safety to their occupants.
“Acquire building and/or space in a building as used in this Standard refers to a right to occupy
buildings or space resulting from a purchase, lease, license, transfer title, or other means.
The requirements for meeting this Standard are set forth below.
All evaluations performed under this Standard are to consider the whole building and all its
structural sections. Where a seismic hazard to the subject building clearly is posed by adjacent
buildings, e.g., an elevated unreinforced masonry wall that may collapse onto the subject
building, these hazards are to be included in the assessment required below. It is not the intent
of this standard to require detailed analyses of adjacent buildings. (See also Section
5.1 Private
Buildings Constructed on CSU Land.)
9.1 Types of Acquisitions
A. Acquire by Lease or License
Newly leased or licensed space may be occupied only if it satisfies the seismic safety
requirements of this Standard at the time the lease or license is executed, which can
be established by one of the following:
1. A
Waiver Letter that justifies the determination that it is safe consistent with
CSU Seismic Requirements, see Section 9
.2.B, or
2. A FEMA Evaluation Report that indicates the building is not expected to pose a
seismic safety risk, see Section 9
.2.B, or
3. A Certificate of Applicable Code indicates the building was designed to modern
Code requirements and does not have characteristics known to be hazardous,
see Section 9
.2.C, or
4. An Independent Review Report states that the building has an earthquake
damageability Level of IV or better, as defined in the table Earthquake
Performance Levels for Existing Buildings, see Attachment D.
The documents establishing any one of these may be produced by the University,
the building owner, or the building owner’s technical agent, and will be accepted
subject to the review of the CSU as detailed in Section 9
.2. The documents resulting
from the requirements of items
2,
3, or 4, above, remain valid for 12 months from
the date of their original issuance. This term can be extended for up to two years
provided that a letter, signed and, where applicable, stamped by the author of the
report or certificate, certifies that there have been: (i) no material changes in the
structural system, either as part of building modifications, or as the result of
accidents, and (ii) no changes in the standards of evaluating buildings that would
change the report’s or certificate’s conclusions, and (iii) no seismic or wind events
that could change the report’s or certificate’s conclusions.
CSU Seismic Requirements
February 15, 2024
Page 34
B. Acquire by Purchase or Title Transfer
Whenever a building is acquired by purchase or other title transfer (e.g., exchange,
gift), the due diligence examination of the property shall include a signed and
stamped independent review report from a structural engineer licensed in the
State of California or the state in which the property is located that meets the
requirements of Section 9
.2
.
D, Independent Review Report, below. It is advisable
that the campus Seismic Peer Reviewer review these documents to determine if they
meet the CSU Seismic Requirements. As an alternative in lieu of Section 9.2.D
requirements, the campus Seismic Peer Reviewer with agreement from the SRB Chair
and Vice Chair may elect that the property meet the requirements of Section 9.2.B if
the building was compliant with the 1998 or subsequent editions of the CBC (1997
Uniform Building Code, as amended). See also Earthquake Performance Levels for
Existing Buildings in Attachment D.
Before the acquisition of a building(s), CSU shall evaluate the building(s) and report
on its seismic damageability. By Standard, a newly acquired building that has an
evaluation of Level IV or better seismic performance may be occupied or continue
to be occupied. A building with a Level V rating may be occupied or continue to be
occupied only if the comprehensive and feasible budget and retrofit plan are in
place at acquisition to retrofit it to achieve a Level IV within five years. A building
with Level VI or poorer ratings must be seismically retrofitted to achieve a Level IV
or better rating before it may be occupied. If the hazard classification depends on
the seismic performance of adjacent structures, then mitigation can be achieved
either by modification of the adjacent building hazard or by protecting the subject
building from the consequences of the adjacent buildings seismic performance.
Any retrofit work undertaken as part of a purchase to meet an assigned Level must
be independently peer-reviewed by the campus Seismic Peer Reviewer.
The peer review shall be of the retrofit or modification design prior to construction
and continue through the completion of construction for conformance with the
asserted Level. See also Earthquake Performance Levels for Existing Buildings given
in Attachment D.
The requirements of this section may be waived if the building is unoccupied, will
remain unoccupied after purchase, is to be demolished, will be sold without
occupancy, or is a one or two-story, wood-framed single-family residence on a level
site.
CSU Seismic Requirements
February 15, 2024
Page 35
9.2 Acceptable Evaluation Documents
A. Waiver Letter
The requirements for seismic evaluation under the Seismic Requirements may be
waived under the following limited conditions:
1. The space will be occupied for less than two years, and CSU does not
currently occupy space in the building, or
2. The area of the space to be occupied by CSU is
3,000 SF or less, and the space
is not to house pre-school age children, or
3. The building is a one-story, wood-framed building, or a one- or two-story,
wood-framed single-family residence on level site, or
4. The building is subject to the regulatory authority of the Health Care Access
and Information (HCAI) or is a schoolhouse regulated by the Division of the
State Architect, or
5. The space to be occupied is within a structure currently occupied by and
previously evaluated and accepted under this method by any of the named
entities, or
6. The space must be occupied because of administrative requirements beyond
the control of CSU as certified by a policy-level person. Each CSU
organizational unit shall designate the person(s) authorized to make such
waivers.
Any Waiver Letter issued under one or more of the above allowances must be in
writing by the person making such determination and reviewed and approved by
the campus Seismic Peer Reviewer to be acceptable.
For any building not qualifying for a Waiver Letter, proceed to Section 9.2.C below,
FEMA Evaluation report.
B. Certificate of Applicable Code
A Certificate of Applicable Code (Certificate) may be provided if the entire building
was constructed under a permit approved by the local jurisdiction and was designed
to meet one of the following requirements:
1. Not located in a designated active seismic fault zone by CGS or CSU, in a CGS or
designated seismic hazard zone (faulting, liquefaction, and other seismically
induced hazard zones), or a FEMA high-risk flood zone.
2. Compliant with 1998 or subsequent editions of the CBC (1997 Uniform Building
Code, as amended) or the indicated trigger lower-bound editions of the Code
years indicated in ASCE 41’s most current edition Benchmark Buildings List for
the applicable structural types used in the building. Where several types of
structural systems were used, then the most restrictive trigger date applies.
C. FEMA P-154 Evaluation Report
Seismic compliance may be met by an evaluation using the FEMA P-154
methodology (Rapid Visual Screening) that results in a score higher than the Basic
Hazard Score provided in the FEMA handbook, see Section III for references.
The FEMA P-154 benchmark years for building types in Table 2-2 are replaced by
Table QX Benchmark Buildings List for different building types. All campuses are to
be in areas of seismicity consistent with P-154 definitions based on the ground
motions of the building site, which determines the form to be used. The P-154 Level 1
and 2 evaluations must be completed by a licensed structural engineer. A building
CSU Seismic Requirements
February 15, 2024
Page 36
with SL2 2.0 is potentially acceptable if the SRB campus assessor approves the
conclusion.
For any building not qualifying for a favorable FEMA P-154 report, proceed to
Section 9.2.D below.
D. Independent Review Report
An Independent Review Report of the entire building and its critical nonstructural
components shall be prepared by a structural engineer licensed by the State of
California or the state in which the property is located, who has had no prior
involvement in the buildings design or evaluation and has no ownership interest in
the property.
As a matter of policy, all acquisitions by Purchase or other Title Transfer (see Section
9.1.A. above) require an Independent Review Report. The CSU will not approve for
occupancy a newly leased building having a seismic performance level of V or
poorer. See the attached table titled Earthquake Performance Levels for Existing
Buildings given in Attachment D.
The Independent Review Report and its preparation, at a minimum, shall include the
following:
1. A visit to the building to observe its condition and characteristics;
2. A review of available design drawings and soil reports for the original
construction and subsequent modifications;
3. An assessment shall be given based on an ASCE 41 Tier 1 or higher-level
assessment, or some other procedure approved by the SRB. In addition, a
qualitative (and quantitative, if needed) evaluation of the building’s gravity
systems shall be completed;
4. A qualitative (and quantitative, if needed) evaluation of the likelihood of
earthquake-induced site failure that could cause damage to the facility, that
is, the building is in the vicinity of earthquake faults listed in the State of
California Earthquake Zones Act of
1990 (previously Alquist-Priolo) or
liquefaction susceptibility zone as identified by the local jurisdiction, or the
building site is subject to failure due to earthquake-induced landslide risk;
5. Identification of any potential falling hazards in areas that will be occupied
or common areas within the building that poses a life-safety threat to the
building occupants during an earthquake;
6. An evaluation of the earthquake damageability Level of the building using
the definitions of the attached table, Seismic Earthquake Performance
Levels for Existing Buildings, given in Attachment D;
7. A list of the documents, plans, and other materials examined.
If the assessment is done by an SRB member and the procedures of Section 7 are
followed, then the Section 7-style report shall be reviewed by the SRB and the
building leased if it meets them.
For leases, if a landlord intends to complete modifications to bring a building into
compliance with the required Level (minimum), the landlord shall certify that the
work to be completed will meet the requirements of this section, and (ii) describe
the work in sufficient detail to allow CSU’s technical review and approval. In either
case, confirmation that the completed modifications meet the requirements of this
CSU Seismic Requirements
February 15, 2024
Page 37
section shall be done by the landlord’s structural engineer.
The Independent Review Report must be signed and stamped by the professional
who certifies that the evaluation was Level IV or better before occupancy occurs,
then the landlord’s structural engineer must state that the work was done by this
person or under this person’s direct supervision, that they have no prior
involvement in the buildings design or evaluation, and the firm or individuals of the
firm have no ownership interest in the property. CSU may have the Independent
Review Report prepared to meet Section 8.2 requirements peer-reviewed to
confirm its technical reliability prior to acceptance of the report’s conclusions and
reliance upon it in the execution of the real estate transaction.
CSU Seismic Requirements
February 15, 2024
Page 38
Attachment A
California State University Seismic Review Board
The following persons are members of the CSU SRB:
Charles C. Thiel Jr., Ph.D., Chairman; President, Telesis
K. Dirk Bondy, S.E., President, Seneca Structural Engineers, Inc.
Debra Murphy, C.E., Consulting Civil Engineer - Geotechnical
Barry Schindler, S.E., Partner, John A. Martin and Associates, Inc.
Richard Niewiarowski, S.E., Consulting Structural Engineer
Maryann Phipps, S.E., President, Estructure, Inc.
Thomas Sabol, Ph.D., S.E., Principal, Englekirk Institutional, Inc.
John A. Martin Jr., S.E. (Emeritus); retired, President, John A. Martin and Associates, Inc.
CSU Seismic Requirements
February 15, 2024
Page 39
ATTACHMENT B
CSU Seismic Requirements values for use on all projects subject to the 2022 edition
of the California Building Code
Seismic Coefficients for CSU Campus Locations
Seismic ground motion parameters for CSU campuses are given in Table 1 below for Site Class
designations corresponding to reference rock Site Class BC (V
S30
= 760 m/s) as utilized by the U.S.
Geological Survey (USGS) in developing the U.S. Seismic Design Maps, as well as Site Class C (very dense
soil and soft rock), Site Class D (stiff soil), and Default Site Class D.
Site Class definitions are as given in ASCE/SEI 7 Chapter 20; if soil and/or rock properties information is
not available in adequate detail to designate the Site Class per ASCE/SEI 7 Chapter 20, then Default D
Site Class values shall be used, unless the site geotechnical report indicates that an exception should be
made, and the Seismic Peer Reviewer’s concurs.
As noted in Section 3.3, these values are to be used for all projects on the University’s campus.
Use of the seismic ground motion parameters given in Table 1 supersedes the provisions of ASCE/SEI 7
Chapter 11, Section 11.4.8, requiring site-specific ground motion hazard and/or site response analyses
for structure locations at CSU campuses with Site Class D ground conditions. Site-specific ground motion
hazard and/or site response analyses may still be required for Site Classes E and F ground conditions
unless the exceptions of ASCE/SEI 7-16 Supplement 3 (adopted by the CBC) are met. Site-specific ground
motion hazard and/or site response analyses are permitted for any Site Class if warranted by the nature
or special characteristics of a project; however, the need for such site-specific analyses, as well as the
methodology for these analyses and analysis results, shall be subject to peer review by the geotechnical
member of the CSU Seismic Review Board. The value of S1 used to determine the Seismic Design
Category in ASCE 7 corresponds to the SM1 value for Site Class BC in Table 1.
If there is a known active fault that traverses the campus as determined by the California Geological
Survey or the Seismic Review Board, then it is so indicated, see Section 3.6. CSU has not implemented
the CBC Latest edition allowance to reduce the BSE-C and/or BSE-R if they exceed the BSE-2N (MCE
R
)
and BSE-1N (DE)values; the values determined below apply without modifications. If there is a known
California Geological Survey liquefaction map that includes portions of the site that are subject to
liquefaction, they have been noted. Note that some local jurisdictions publish supplemental liquefaction
maps that should be referenced if they apply. The liquefaction and faulting annotations of the Table are
intended to alert the University for planning purposes. The soils report for all projects should address
whether the specific site exhibits these hazards as well as other soil movement and densification
characteristics to assure that the design considers them.
In addition, for investigations that are undertaken specifically to investigate the occurrence of geologic
and geotechnical seismic hazards (e.g., faulting, liquefaction, land sliding), as well as site-specific ground
motion hazard and/or site response analyses, the CSU Geotechnical Peer Reviewer shall be the peer
reviewer for all locations within the CSU systems.
The Seismic Review Board should be contacted through the campus assigned Seismic Peer Reviewer for
assignment of the appropriate values for sites not listed or a site that is not a part of the contiguous
campus.
CSU Seismic Requirements D5 SRB Edits based on review comments Page 40
Table 1 - CSU Campus Seismic Ground Motion Horizontal Response Spectral Acceleration Parameters
(Table revision date: March 5, 2020)
Campus
Active
Fault
Zone
1
Closest
UCERF3
2
Faults
for Deterministic
Ground Shaking
Considerations
Located in a
Mapped
Liquefaction
Zone
3
Site
Class
4
BSE-2N [MCER] (g)
4
BSE-1N [Design] (g)
4
BSE-C (g)
4
BSE-R (g)
4
PGAM SM0 SMS SM1 PGAD SD0 SDS SD1 PGAC SC0 SCS SC1 PGAR SR0 SRS SR1
Bakersfield No
White Wolf 34
km
&
San Andreas
52 km
--
BC
0.41 0.38 0.95 0.35 0.27 0.25 0.63 0.23 0.31 0.29 0.72 0.26 0.16 0.15 0.37 0.13
C 0.49 0.45 1.13 0.52 0.33 0.30 0.76 0.35 0.37 0.35 0.88 0.40 0.20 0.19 0.48 0.20
D
0.49 0.42 1.06 0.68 0.33 0.28 0.71 0.45 0.40 0.35 0.88 0.55 0.24 0.22 0.55 0.31
Default
D
0.49 0.45 1.13 0.68 0.33 0.30 0.76 0.45 0.40 0.35 0.88 0.55 0.24 0.22 0.55 0.31
Bakersfield
Antelope
Valley
No
San Andreas
10 km
No
BC 0.67 0.61 1.52 0.62 0.44 0.40 1.01 0.42 0.56 0.57 1.43 0.58 0.25 0.24 0.60 0.22
C
0.80 0.73 1.82 0.87 0.53 0.49 1.21 0.58 0.67 0.68 1.71 0.82 0.30 0.30 0.76 0.33
D
0.73 0.61 1.52 1.06 0.49 0.40 1.01 0.71 0.62 0.57 1.43 1.00 0.34 0.32 0.79 0.48
Default
D
0.73 0.73 1.82 1.06 0.49 0.49 1.21 0.71 0.62 0.68 1.71 1.00 0.34 0.32 0.79 0.48
Cal Maritime
Academy
No
Franklin ≈ 1¼ km,
West Napa ≈ 11
km, Green Valley
≈ 11 km, &
Hayward ≈ 14 km
--
BC 0.50 0.60 1.50 0.60 0.33 0.40 1.00 0.40 0.65 0.68 1.69 0.60 0.35 0.35 0.88 0.30
C
0.60 0.72 1.80 0.84 0.40 0.48 1.20 0.56 0.78 0.81 2.03 0.84 0.43 0.42 1.05 0.45
D 0.55 0.60 1.50 1.02 0.37 0.40 1.00 0.68 0.72 0.68 1.69 1.03 0.44 0.40 1.01 0.60
Default
D
0.55 0.72 1.80 1.02 0.37 0.48 1.20 0.68 0.72 0.81 2.03 1.03 0.44 0.42 1.05 0.60
Chancellor’s
Office
No
Compton ≈
km,
Newport-
Inglewood
≈ 5 km,
&
Palos Verdes ≈
5¼ km
Yes
BC
0.72 0.65 1.63 0.59 0.48 0.43 1.09 0.40 0.49 0.48 1.19 0.42 0.23 0.21 0.54 0.18
C 0.87 0.78 1.96 0.84 0.58 0.52 1.30 0.56 0.59 0.57 1.43 0.63 0.28 0.28 0.69 0.27
D
0.80 0.65 1.63 1.01 0.53 0.43 1.09 0.68 0.54 0.49 1.22 0.79 0.32 0.29 0.74 0.41
Default
D
0.80 0.78 1.96 1.01 0.53 0.52 1.30 0.68 0.54 0.57 1.43 0.79 0.32 0.29 0.74 0.41
CSU Seismic Requirements D5 SRB Edits based on review comments Page 41
Campus
continued
Active
Fault
Zone
1
Closest
UCERF3
2
Faults
for Deterministic
Ground Shaking
Considerations
Located in a
Mapped
Liquefaction
Zone
3
Site
Class
4
BSE-2N [MCER] (g)
4
BSE-1N [Design] (g)
4
BSE-C (g)
4
BSE-R (g)
4
PGAM SM0 SMS SM1 PGAD SD0 SDS SD1 PGAC SC0 SCS SC1 PGAR SR0 SRS SR1
Channel
Islands
No
Simi-Santa Rosa
≈ 8 km,
&
Oak Ridge ≈ 15
km
Yes
BC
0.64 0.59 1.49 0.54 0.43 0.40 0.99 0.36 0.45 0.45 1.13 0.40 0.23 0.22 0.54 0.19
C 0.77 0.71 1.78 0.79 0.51 0.48 1.19 0.53 0.54 0.54 1.35 0.60 0.28 0.28 0.70 0.28
D 0.70 0.59 1.49 0.95 0.47 0.40 0.99 0.64 0.52 0.47 1.18 0.76 0.32 0.30 0.74 0.42
Default
D
0.70 0.71 1.78 0.95 0.47 0.48 1.19 0.64 0.52 0.54 1.35 0.76 0.32 0.30 0.74 0.42
Chico No
Cascadia
Subduction Zone
≈ 125 km
--
BC 0.34 0.31 0.77 0.32 0.23 0.21 0.51 0.21 0.25 0.23 0.57 0.23 0.12 0.11 0.26 0.11
C 0.41 0.37 0.92 0.47 0.27 0.25 0.62 0.32 0.30 0.29 0.72 0.35 0.15 0.14 0.34 0.16
D
0.43 0.37 0.92 0.63 0.29 0.24 0.61 0.42 0.34 0.30 0.76 0.49 0.18 0.17 0.42 0.25
Default
D
0.43 0.37 0.92 0.63 0.29 0.25 0.62 0.42 0.34 0.30 0.76 0.49 0.18 0.17 0.42 0.25
Dominguez
Hills
No
Newport-
Inglewood
< 1 km,
Compton ≈ 8¾
km,
&
Palos Verdes ≈
11 km
No
BC 0.75 0.70 1.74 0.62 0.50 0.46 1.16 0.41 0.52 0.51 1.29 0.45 0.26 0.24 0.60 0.20
C
0.90 0.83 2.09 0.87 0.60 0.56 1.39 0.58 0.62 0.62 1.54 0.67 0.31 0.30 0.76 0.30
D 0.83 0.70 1.74 1.06 0.55 0.46 1.16 0.70 0.57 0.51 1.29 0.83 0.34 0.32 0.79 0.44
Default
D
0.83 0.83 2.09 1.06 0.55 0.56 1.39 0.70 0.57 0.62 1.54 0.83 0.34 0.32 0.79 0.44
East Bay
Concord
No
Concord/Green
Valley ≈ 3 km
--
BC 0.94 0.93 2.33 0.69 0.62 0.62 1.56 0.46 0.75 0.77 1.92 0.65 0.39 0.38 0.95 0.31
C
1.12 1.12 2.80 0.97 0.75 0.75 1.87 0.65 0.90 0.92 2.31 0.91 0.47 0.46 1.14 0.47
D 1.03 0.93 2.33 1.18 0.69 0.62 1.56 0.78 0.83 0.77 1.92 1.11 0.47 0.43 1.06 0.62
Default
D
1.03 1.12 2.80 1.18 0.69 0.75 1.87 0.78 0.83 0.92 2.31 1.11 0.47 0.46 1.14 0.62
CSU Seismic Requirements D5 SRB Edits based on review comments Page 42
Campus
continued
Active
Fault
Zone
1
Closest
UCERF3
2
Faults
for Deterministic
Ground Shaking
Considerations
Located in a
Mapped
Liquefaction
Zone
3
Site
Class
4
BSE-2N [MCER] (g)
4
BSE-1N [Design] (g)
4
BSE-C (g)
4
BSE-R (g)
4
PGAM SM0 SMS SM1 PGAD SD0 SDS SD1 PGAC SC0 SCS SC1 PGAR SR0 SRS SR1
East Bay
Hayward
Yes,
Hayward
Hayward < 1 km
Yes,
&
Landslide
Zone
BC
0.97 0.92 2.30 0.88 0.64 0.61 1.54 0.59 0.95 0.98 2.45 0.89 0.49 0.49 1.22 0.42
C
1.16 1.11 2.76 1.23 0.77 0.74 1.84 0.82 1.14 1.17 2.94 1.25 0.59 0.58 1.46 0.63
D
1.06 0.92 2.30 1.50 0.71 0.61 1.54 1.00 1.05 0.98 2.45 1.51 0.55 0.49 1.23 0.79
Default
D
1.06 1.11 2.76 1.50 0.71 0.74 1.84 1.00 1.05 1.17 2.94 1.51 0.55 0.58 1.46 0.79
Fresno No
Great Valley ≈ 72
km
&
San Andreas
≈ 115 km
--
BC
0.24 0.22 0.56 0.22 0.16 0.15 0.37 0.15 0.18 0.16 0.40 0.16 0.09 0.08 0.20 0.09
C
0.29 0.28 0.71 0.33 0.19 0.19 0.47 0.22 0.21 0.21 0.52 0.25 0.12 0.11 0.27 0.14
D
0.33 0.30 0.75 0.48 0.22 0.20 0.50 0.32 0.25 0.24 0.59 0.37 0.15 0.13 0.33 0.22
Default
D
0.33 0.30 0.75 0.48 0.22 0.20 0.50 0.32 0.25 0.24 0.59 0.37 0.15 0.13 0.33 0.22
Fullerton No
Puente Hills Blind
Thrust < 1 km
&
Whittier ≈ 6 km
Yes
BC 0.72 0.67 1.69 0.59 0.48 0.45 1.12 0.40 0.51 0.50 1.26 0.43 0.26 0.24 0.61 0.21
C 0.87 0.81 2.02 0.83 0.58 0.54 1.35 0.56 0.62 0.60 1.51 0.65 0.31 0.31 0.77 0.31
D 0.80 0.67 1.69 1.01 0.53 0.45 1.12 0.67 0.56 0.50 1.26 0.81 0.35 0.32 0.80 0.45
Default
D
0.80 0.81 2.02 1.01 0.53 0.54 1.35 0.67 0.56 0.60 1.51 0.81 0.35 0.32 0.80 0.45
Humboldt
Yes,
Fickle
Hill
Fickle Hill < 1 km,
Little Salmon ≈ 9
km,
&
Cascadia
Subduction Zone
≈ 18 km
--
BC 0.99 0.98 2.44 1.07 0.66 0.65 1.63 0.72 0.99 0.91 2.27 0.91 0.43 0.37 0.92 0.34
C 1.19 1.17 2.93 1.50 0.80 0.78 1.95 1.00 1.18 1.09 2.72 1.28 0.52 0.44 1.11 0.51
D 1.09 0.98 2.44 1.82 0.73 0.65 1.63 1.22 1.08 0.91 2.27 1.55 0.50 0.42 1.04 0.66
Default
D
1.09 1.17 2.93 1.82 0.73 0.78 1.95 1.22 1.08 1.09 2.72 1.55 0.50 0.44 1.11 0.66
Humboldt
Marine Lab
Trinidad
No
Trinidad
km,
Mad River ≈ 4
km,
&
Cascadia
Subduction Zone
≈ 16 km
--
BC 1.21 1.08 2.71 1.10 0.81 0.72 1.81 0.73 0.92 0.80 2.01 0.85 0.36 0.31 0.78 0.29
C 1.46 1.30 3.25 1.54 0.97 0.87 2.17 1.02 1.10 0.97 2.41 1.19 0.43 0.37 0.93 0.43
D 1.34 1.08 2.71 1.86 0.89 0.72 1.81 1.24 1.01 0.80 2.01 1.45 0.45 0.37 0.92 0.58
Default
D
1.34 1.30 3.25 1.86 0.89 0.87 2.17 1.24 1.01 0.97 2.41 1.45 0.45 0.37 0.93 0.58
CSU Seismic Requirements D5 SRB Edits based on review comments Page 43
Campus
continued
Active
Fault
Zone
1
Closest
UCERF3
2
Faults
for Deterministic
Ground Shaking
Considerations
Located in a
Mapped
Liquefaction
Zone
3
Site
Class
4
BSE-2N [MCER] (g)
4
BSE-1N [Design] (g)
4
BSE-C (g)
4
BSE-R (g)
4
PGAM SM0 SMS SM1 PGAD SD0 SDS SD1 PGAC SC0 SCS SC1 PGAR SR0 SRS SR1
Long Beach No
Newport-
Inglewood
≈ 1½ km
&
Compton ≈
km
Yes
BC 0.67 0.62 1.55 0.56 0.45 0.41 1.03 0.37 0.46 0.45 1.12 0.39 0.22 0.21 0.53 0.18
C 0.81 0.74 1.86 0.80 0.54 0.50 1.24 0.54 0.55 0.54 1.35 0.59 0.27 0.27 0.68 0.27
D 0.74 0.62 1.55 0.97 0.49 0.41 1.03 0.65 0.52 0.47 1.18 0.75 0.31 0.29 0.73 0.40
Default
D
0.74 0.74 1.86 0.97 0.49 0.50 1.24 0.65 0.52 0.54 1.35 0.75 0.31 0.29 0.73 0.40
Los Angeles No
Upper Elysian
Park
< 1 km
No
BC 0.87 0.80 2.01 0.72 0.58 0.54 1.34 0.48 0.61 0.61 1.53 0.53 0.29 0.28 0.69 0.23
C 1.04 0.96 2.41 1.01 0.69 0.64 1.61 0.67 0.73 0.73 1.83 0.78 0.35 0.34 0.85 0.35
D 0.95 0.80 2.01 1.23 0.64 0.54 1.34 0.82 0.67 0.61 1.53 0.94 0.38 0.34 0.86 0.50
Default
D
0.95 0.96 2.41 1.23 0.64 0.64 1.61 0.82 0.67 0.73 1.83 0.94 0.38 0.34 0.86 0.50
Monterey Bay
East
No
Reliz ≈ 1¼
km&San Andreas
≈ 28 km
--
BC
0.60 0.59 1.47 0.53 0.40 0.39 0.98 0.35 0.45 0.45 1.12 0.40 0.26 0.26 0.64 0.22
C 0.72 0.71 1.77 0.78 0.48 0.47 1.18 0.52 0.54 0.54 1.35 0.60 0.32 0.32 0.80 0.32
D 0.66 0.59 1.47 0.93 0.44 0.39 0.98 0.62 0.52 0.47 1.18 0.76 0.35 0.33 0.83 0.47
Default
D
0.66 0.71 1.77 0.93 0.44 0.47 1.18 0.62 0.52 0.54 1.35 0.76 0.35 0.33 0.83 0.47
Monterey Bay
West
No
Reliz ≈ 3 km
&
San Andreas
31 km
--
BC
0.58 0.57 1.41 0.51 0.39 0.38 0.94 0.34 0.43 0.43 1.07 0.39 0.25 0.24 0.60 0.21
C
0.70 0.68 1.70 0.76 0.47 0.45 1.13 0.51 0.51 0.52 1.29 0.58 0.30 0.30 0.76 0.31
D
0.64 0.57 1.41 0.91 0.43 0.38 0.94 0.61 0.50 0.46 1.15 0.74 0.33 0.32 0.79 0.45
Default
D
0.64 0.68 1.70 0.91 0.43 0.45 1.13 0.61 0.50 0.52 1.29 0.74 0.33 0.32 0.79 0.45
Moss Landing
Marine
Laboratories
No
San Andreas
19 km
--
BC
0.68 0.67 1.69 0.61 0.46 0.45 1.12 0.41 0.53 0.53 1.31 0.47 0.32 0.31 0.77 0.26
C
0.82 0.81 2.02 0.85 0.55 0.54 1.35 0.57 0.63 0.63 1.58 0.71 0.38 0.37 0.92 0.38
D
0.75 0.67 1.69 1.04 0.50 0.45 1.12 0.69 0.58 0.53 1.31 0.86 0.41 0.37 0.91 0.53
Default
D
0.75 0.81 2.02 1.04 0.50 0.54 1.35 0.69 0.58 0.63 1.58 0.86 0.41 0.37 0.92 0.53
CSU Seismic Requirements D5 SRB Edits based on review comments Page 44
Campus
continued
Active
Fault
Zone
1
Closest
UCERF3
2
Faults
for Deterministic
Ground Shaking
Considerations
Located in a
Mapped
Liquefaction
Zone
3
Site
Class
4
BSE-2N [MCER] (g)
4
BSE-1N [Design] (g)
4
BSE-C (g)
4
BSE-R (g)
4
PGAM SM0 SMS SM1 PGAD SD0 SDS SD1 PGAC SC0 SCS SC1 PGAR SR0 SRS SR1
Northridge No
Santa Susana ≈ 7
km,
Northridge Hills
≈ 1 km,
&
Mission Hills ≈
km
No
BC 0.80 0.78 1.96 0.68 0.54 0.52 1.31 0.45 0.69 0.70 1.75 0.60 0.37 0.35 0.88 0.28
C 0.96 0.94 2.35 0.95 0.64 0.63 1.57 0.64 0.83 0.84 2.10 0.84 0.45 0.42 1.06 0.42
D 0.88 0.78 1.96 1.16 0.59 0.52 1.31 0.77 0.76 0.70 1.75 1.02 0.46 0.41 1.01 0.57
Default
D
0.88 0.94 2.35 1.16 0.59 0.63 1.57 0.77 0.76 0.84 2.10 1.02 0.46 0.42 1.06 0.57
Pomona
Yes,
San
Jose
San Jose < 1 km,
Chino ≈ 7½ km,
&
Sierra Madre ≈ 8
km
Yes
BC 0.73 0.69 1.72 0.62 0.49 0.46 1.14 0.41 0.52 0.52 1.31 0.47 0.27 0.26 0.65 0.23
C 0.88 0.82 2.06 0.87 0.58 0.55 1.37 0.58 0.62 0.63 1.57 0.70 0.33 0.32 0.81 0.34
D 0.80 0.69 1.72 1.05 0.54 0.46 1.14 0.70 0.57 0.52 1.31 0.85 0.36 0.33 0.84 0.48
Default
D
0.80 0.82 2.06 1.05 0.54 0.55 1.37 0.70 0.57 0.63 1.57 0.85 0.36 0.33 0.84 0.48
Pomona
Campus
South
(Lanterman)
No
San Jose ≈ 2½
km,
Chino ≈ 6 km,
&
Sierra Madre
10 km
Yes
BC
0.75 0.70 1.75 0.63 0.50 0.47 1.17 0.42 0.53 0.53 1.34 0.47 0.28 0.27 0.66 0.23
C 0.90 0.84 2.10 0.88 0.60 0.56 1.40 0.58 0.64 0.64 1.60 0.71 0.33 0.33 0.82 0.34
D 0.82 0.70 1.75 1.06 0.55 0.47 1.17 0.71 0.59 0.53 1.34 0.86 0.37 0.34 0.84 0.49
Default
D
0.82 0.84 2.10 1.06 0.55 0.56 1.40 0.71 0.59 0.64 1.60 0.86 0.37 0.34 0.84 0.49
Sacramento No
Great Valley
(Midland) ≈ 38
km
&
San Andreas
130 km
--
BC
0.22 0.21 0.53 0.24 0.15 0.14 0.35 0.16 0.17 0.16 0.39 0.19 0.10 0.09 0.22 0.10
C
0.27 0.27 0.68 0.36 0.18 0.18 0.45 0.24 0.21 0.20 0.51 0.28 0.12 0.11 0.28 0.15
D
0.30 0.29 0.73 0.51 0.20 0.19 0.48 0.34 0.25 0.23 0.58 0.41 0.15 0.14 0.35 0.24
Default
D
0.30 0.29 0.73 0.51 0.20 0.19 0.48 0.34 0.25 0.23 0.58 0.41 0.15 0.14 0.35 0.24
San
Bernardino
No
San Andreas
≈ 1½ km
&
San Jacinto ≈ 4½
km
--
BC
1.03 0.96 2.39 1.02 0.69 0.64 1.60 0.68 0.96 0.97 2.42 0.96 0.48 0.46 1.15 0.40
C
1.24 1.15 2.87 1.43 0.82 0.77 1.92 0.95 1.15 1.16 2.90 1.35 0.58 0.55 1.38 0.60
D
1.13 0.96 2.39 1.73 0.76 0.64 1.60 1.15 1.05 0.97 2.42 1.63 0.54 0.48 1.20 0.76
Default
D
1.13 1.15 2.87 1.73 0.76 0.77 1.92 1.15 1.05 1.16 2.90 1.63 0.54 0.55 1.38 0.76
CSU Seismic Requirements D5 SRB Edits based on review comments Page 45
Campus
continued
Active
Fault
Zone
1
Closest
UCERF3
2
Faults
for Deterministic
Ground Shaking
Considerations
Located in a
Mapped
Liquefaction
Zone
3
Site
Class
4
BSE-2N [MCER] (g)
4
BSE-1N [Design] (g)
4
BSE-C (g)
4
BSE-R (g)
4
PGAM SM0 SMS SM1 PGAD SD0 SDS SD1 PGAC SC0 SCS SC1 PGAR SR0 SRS SR1
San
Bernardino
Palm Desert
No
San Andreas ≈ 6
km
--
BC 0.77 0.72 1.81 0.74 0.52 0.48 1.20 0.49 0.65 0.66 1.64 0.63 0.32 0.31 0.77 0.26
C 0.93 0.87 2.17 1.04 0.62 0.58 1.45 0.69 0.78 0.79 1.97 0.88 0.39 0.37 0.92 0.39
D 0.85 0.72 1.81 1.26 0.57 0.48 1.20 0.84 0.71 0.66 1.64 1.06 0.41 0.37 0.92 0.54
Default
D
0.85 0.87 2.17 1.26 0.57 0.58 1.45 0.84 0.71 0.79 1.97 1.06 0.41 0.37 0.92 0.54
San Diego No
Rose
Canyon/Newport-
Inglewood 10
km
--
BC 0.40 0.37 0.91 0.32 0.27 0.24 0.61 0.22 0.28 0.27 0.69 0.24 0.13 0.12 0.31 0.12
C 0.48 0.44 1.10 0.48 0.32 0.29 0.73 0.32 0.33 0.34 0.84 0.36 0.17 0.16 0.40 0.17
D 0.48 0.41 1.04 0.64 0.32 0.28 0.69 0.43 0.37 0.34 0.86 0.51 0.20 0.19 0.48 0.27
Default
D
0.48 0.44 1.10 0.64 0.32 0.29 0.73 0.43 0.37 0.34 0.86 0.51 0.20 0.19 0.48 0.27
San Diego
Imperial
Valley
Brawley
No
Brawley Seismic
Zone <1 km
&
Imperial ≈8 km
--
BC 0.55 0.60 1.50 0.60 0.37 0.40 1.00 0.40 0.808 0.84 2.11 0.74 0.48 0.48 1.20 0.38
C 0.66 0.72 1.80 0.84 0.44 0.48 1.20 0.56 0.937 1.01 2.53 1.03 0.56 0.58 1.44 0.58
D 0.61 0.60 1.50 1.02 0.40 0.40 1.00 0.68 0.873 0.84 2.11 1.25 0.54 0.49 1.22 0.74
Default
D
0.61 0.72 1.80 1.02 0.40 0.40 1.20 0.68 0.873 0.84 2.11 1.25 0.54 0.49 1.44 0.74
San Diego
Imperial
No
Cerro Prieto ≈
km
&
Imperial ≈ 10 km
--
BC
0.54 0.60 1.50 0.60 0.36 0.40 1.00 0.40 0.67 0.70 1.76 0.64 0.39 0.40 0.99 0.33
C
0.65 0.72 1.80 0.84 0.43 0.48 1.20 0.56 0.80 0.84 2.11 0.90 0.47 0.47 1.19 0.50
D
0.59 0.60 1.50 1.02 0.40 0.40 1.00 0.68 0.73 0.70 1.76 1.09 0.47 0.44 1.09 0.66
Default
D
0.59 0.72 1.80 1.02 0.40 0.48 1.20 0.68 0.73 0.84 2.11 1.09 0.47 0.47 1.19 0.66
San Diego
Mission
Valley
No
Rose
Canyon/Newport-
Inglewood
km
--
BC
0.48 0.43 1.07 0.37 0.32 0.29 0.71 0.25 0.31 0.31 0.78 0.27 0.14 0.13 0.32 0.12
C
0.57 0.51 1.29 0.56 0.38 0.34 0.86 0.37 0.38 0.38 0.94 0.40 0.17 0.17 0.42 0.18
D
0.54 0.46 1.15 0.72 0.36 0.31 0.77 0.48 0.40 0.37 0.93 0.55 0.21 0.20 0.50 0.28
Default
D
0.54 0.51 1.29 0.72 0.36 0.34 0.86 0.48 0.40 0.38 0.94 0.55 0.21 0.20 0.50 0.28
CSU Seismic Requirements D5 SRB Edits based on review comments Page 46
Campus
continued
Active
Fault
Zone
1
Closest
UCERF3
2
Faults
for Deterministic
Ground Shaking
Considerations
Located in a
Mapped
Liquefaction
Zone
3
Site
Class
4
BSE-2N [MCER] (g)
4
BSE-1N [Design] (g)
4
BSE-C (g)
4
BSE-R (g)
4
PGAM SM0 SMS SM1 PGAD SD0 SDS SD1 PGAC SC0 SCS SC1 PGAR SR0 SRS SR1
San
Francisco
No
San Andreas
4¼ km
Yes
BC 0.87 0.81 2.03 0.84 0.58 0.54 1.35 0.56 0.72 0.74 1.86 0.75 0.33 0.32 0.81 0.29
C 1.05 0.97 2.44 1.17 0.70 0.65 1.62 0.78 0.87 0.89 2.23 1.05 0.40 0.39 0.97 0.44
D 0.96 0.81 2.03 1.43 0.64 0.54 1.35 0.95 0.80 0.74 1.86 1.28 0.42 0.38 0.95 0.59
Default
D
0.96 0.97 2.44 1.43 0.64 0.65 1.62 0.95 0.80 0.89 2.23 1.28 0.42 0.39 0.97 0.59
San
Francisco
Tiburon
No
San Andreas
16 km
&
Hayward ≈ 13 km
--
BC 0.50 0.60 1.50 0.60 0.33 0.40 1.00 0.40 0.53 0.54 1.35 0.52 0.30 0.29 0.73 0.26
C 0.60 0.72 1.80 0.84 0.40 0.48 1.20 0.56 0.64 0.65 1.62 0.77 0.36 0.35 0.88 0.39
D 0.55 0.60 1.50 1.02 0.37 0.40 1.00 0.68 0.58 0.54 1.35 0.93 0.39 0.35 0.89 0.54
Default
D
0.55 0.72 1.80 1.02 0.37 0.48 1.20 0.68 0.58 0.65 1.62 0.93 0.39 0.35 0.89 0.54
San José No
Hayward ≈ 9 km,
Calaveras ≈ 11
km,
&
San Andreas
20 km
Yes
BC
0.58 0.60 1.50 0.60 0.38 0.40 1.00 0.40 0.66 0.71 1.77 0.65 0.40 0.41 1.02 0.35
C 0.69 0.72 1.80 0.84 0.46 0.48 1.20 0.56 0.80 0.85 2.13 0.91 0.48 0.49 1.22 0.52
D 0.63 0.60 1.50 1.02 0.42 0.40 1.00 0.68 0.73 0.71 1.77 1.10 0.48 0.44 1.11 0.68
Default
D
0.63 0.72 1.80 1.02 0.42 0.48 1.20 0.68 0.73 0.85 2.13 1.10 0.48 0.49 1.22 0.68
San José
South
No
Hayward ≈ 8½
km,
Calaveras ≈ 11
km,
&
San Andreas
20 km
Yes
BC
0.56 0.60 1.50 0.60 0.37 0.40 1.00 0.40 0.66 0.71 1.77 0.64 0.40 0.41 1.02 0.35
C
0.67 0.72 1.80 0.84 0.45 0.48 1.20 0.56 0.80 0.85 2.12 0.90 0.48 0.49 1.22 0.52
D
0.62 0.60 1.50 1.02 0.41 0.40 1.00 0.68 0.73 0.71 1.77 1.09 0.48 0.45 1.11 0.67
Default
D
0.62 0.72 1.80 1.02 0.41 0.48 1.20 0.68 0.73 0.85 2.12 1.09 0.48 0.49 1.22 0.67
San Luis
Obispo
No
Oceanic-West
Huasna ≈ 3½
km&Hosgri ≈ 25
km
--
BC
0.48 0.43 1.08 0.40 0.32 0.29 0.72 0.26 0.32 0.31 0.77 0.28 0.15 0.14 0.35 0.13
C
0.57 0.52 1.29 0.59 0.38 0.34 0.86 0.40 0.38 0.37 0.92 0.43 0.19 0.18 0.45 0.19
D
0.54 0.46 1.15 0.75 0.36 0.31 0.77 0.50 0.41 0.37 0.92 0.58 0.23 0.21 0.53 0.30
Default
D
0.54 0.52 1.29 0.75 0.36 0.34 0.86 0.50 0.41 0.37 0.92 0.58 0.23 0.21 0.53 0.30
CSU Seismic Requirements D5 SRB Edits based on review comments Page 47
Campus
continued
Active
Fault
Zone
1
Closest
UCERF3
2
Faults
for Deterministic
Ground Shaking
Considerations
Located in a
Mapped
Liquefaction
Zone
3
Site
Class
4
BSE-2N [MCER] (g)
4
BSE-1N [Design] (g)
4
BSE-C (g)
4
BSE-R (g)
4
PGAM SM0 SMS SM1 PGAD SD0 SDS SD1 PGAC SC0 SCS SC1 PGAR SR0 SRS SR1
San Marco No
Rose
Canyon/Newport-
Inglewood 20
km
--
BC 0.39 0.36 0.89 0.33 0.26 0.24 0.59 0.22 0.28 0.27 0.68 0.25 0.15 0.14 0.35 0.13
C 0.46 0.43 1.07 0.49 0.31 0.29 0.71 0.33 0.34 0.33 0.83 0.37 0.19 0.18 0.45 0.19
D 0.47 0.41 1.02 0.65 0.31 0.27 0.68 0.43 0.37 0.34 0.85 0.52 0.22 0.21 0.53 0.30
Default
D
0.47 0.43 1.07 0.65 0.31 0.29 0.71 0.43 0.37 0.34 0.85 0.52 0.22 0.21 0.53 0.30
Sonoma No
Rodgers Creek-
Healdsburg ≈
km
--
BC 0.87 0.82 2.06 0.79 0.58 0.55 1.37 0.53 0.69 0.71 1.77 0.66 0.33 0.32 0.80 0.29
C 1.04 0.99 2.47 1.11 0.69 0.66 1.65 0.74 0.83 0.85 2.12 0.92 0.40 0.39 0.96 0.43
D 0.95 0.82 2.06 1.35 0.64 0.55 1.37 0.90 0.76 0.71 1.77 1.12 0.42 0.38 0.95 0.58
Default
D
0.95 0.99 2.47 1.35 0.64 0.66 1.65 0.90 0.76 0.85 2.12 1.12 0.42 0.39 0.96 0.58
Sonoma
Los Guilicos
Preserve
No
Rodgers Creek-
Healdsburg ≈ 9
km
&
West Napa ≈ 11
km
--
BC
0.66 0.63 1.56 0.60 0.44 0.42 1.04 0.40 0.61 0.64 1.60 0.58 0.32 0.32 0.80 0.28
C 0.79 0.75 1.88 0.84 0.53 0.50 1.25 0.56 0.73 0.77 1.92 0.83 0.39 0.38 0.96 0.42
D 0.72 0.63 1.56 1.02 0.48 0.42 1.04 0.68 0.67 0.64 1.60 1.00 0.41 0.38 0.94 0.57
Default
D
0.72 0.75 1.88 1.02 0.48 0.50 1.25 0.68 0.67 0.77 1.92 1.00 0.41 0.38 0.96 0.57
Stanislaus No
Great Valley
(Orestimba)
≈ 32 km
--
BC
0.28 0.26 0.66 0.26 0.18 0.18 0.44 0.18 0.21 0.20 0.49 0.20 0.12 0.11 0.27 0.11
C
0.33 0.33 0.82 0.39 0.22 0.22 0.54 0.26 0.25 0.26 0.64 0.30 0.15 0.14 0.35 0.17
D
0.36 0.34 0.84 0.55 0.24 0.22 0.56 0.36 0.29 0.28 0.69 0.44 0.18 0.17 0.43 0.27
Default
D
0.36 0.34 0.84 0.55 0.24 0.22 0.56 0.36 0.29 0.28 0.69 0.44 0.18 0.17 0.43 0.27
Stanislaus
Stockton
No
Great Valley
(Midland)
≈ 29 km
--
BC
0.30 0.29 0.72 0.28 0.20 0.19 0.48 0.19 0.22 0.21 0.54 0.22 0.13 0.12 0.30 0.12
C
0.36 0.35 0.87 0.42 0.24 0.23 0.58 0.28 0.27 0.28 0.69 0.32 0.16 0.15 0.38 0.18
D
0.39 0.35 0.88 0.57 0.26 0.23 0.59 0.38 0.31 0.29 0.73 0.47 0.20 0.18 0.46 0.29
CSU Seismic Requirements D5 SRB Edits based on review comments Page 48
Notes:
1
The active fault zones are indicated by the appropriate fault zone special studies map issued by the California Geological Survey (CGS).
The earthquake fault zone for the San Jose fault is indicated on the map prepared for and issued by the CSU Seismic Review Board. These are also
available on the Web at the site
https://maps.conservation.ca.gov/cgs/EQZApp/App/, where liquefaction, landslide and flood plain requirements are
determinable by site address.
2
Field, E.H., Biasi, G.P., Bird, P., Dawson, T.E., Felzer, K.R., Jackson, D.D., Johnson, K.M., Jordan, T.H., Madden, C., Michael, A.J., Milner, K.R.,
Page, M.T., Parsons, T., Powers, P.M., Shaw, B.E., Thatcher, W.R., Weldon, R.J., II, and Zeng, Y., 2013, Uniform California earthquake rupture
forecast, version 3 (UCERF3)The time-independent model: U.S. Geological Survey Open-File Report 20131165, 97 p., California Geological
Survey Special Report 228, and Southern California Earthquake Center Publication 1792, http://pubs.usgs.gov/of/2013/1165/.
3
Liquefaction Zonation is based on CGS maps from 1998 to 2005. Locations where a map was not available are indicated by "--".
4
As defined per ASCE/SEI 7-16, ASCE/SEI 41-17, 2019 California Building Code (CBC).
5
For sites underlain by Site Class E or F ground conditions, site-specific ground motion hazard and/or site response analyses shall be performed to
determine appropriate horizontal response spectral acceleration parameters, unless the exceptions of ASCE/SEI 7-16 Supplement 3 (adopted by the
CBC) are met.
CSU Seismic Requirements
February 15, 2024
Page 49
ATTACHMENT C
California State University Campus Assignments of Seismic Peer Reviewers
The following Seismic Peer Reviewers are assigned for the respective campuses of the California State
University and associated locations. All seismic peer reviews for the indicated campuses or their off-campus
locations are to be performed by the named individuals or their designees. For other locations, the CSU
Seismic Review Board will assign the Seismic Peer Reviewer. In addition, for investigations that are undertaken
specifically to investigate the occurrence of geologic and geotechnical seismic hazards (e.g., faulting,
liquefaction, land sliding), Debra Murphy shall be the Seismic Peer Reviewer for all locations within the CSU
system. For the updated and current list, see the link:
Seismic Peer Reviewers are assigned to individual
campuses of the CSU
Campus Principal Seismic Peer Reviewer
Name
Bakersfield
Dirk Bondy
Bakersfield Antelope Valley
Dirk Bondy
California Maritime Academy
Maryann Phipps
Chancellors Office
Barry Schindler
Channel Islands
Barry Schindler
Chico
Maryann Phipps
Dominguez Hills
Thomas Sabol
East Bay - Concord
Richard Niewiarowski
East Bay Main Campus
Richard Niewiarowski
Fresno
Maryann Phipps
Fullerton
Barry Schindler
Humboldt
Maryann Phipps
Humboldt - Trinidad
Maryann Phipps
Long Beach
Dirk Bondy
Los Angeles
Thomas Sabol
Monterey Bay-East Campus
Richard Niewiarowski
Monterey Bay- West Campus
Richard Niewiarowski
Northridge
Thomas Sabol
Pomona
Barry Schindler
Pomona - South
Barry Schindler
Sacramento
Maryann Phipps
San Bernardino
Dirk Bondy
San Bernardino-Palm Desert
Dirk Bondy
San Diego
Barry Schindler
San Diego-Brawley
Barry Schindler
San Diego-Imperial
Barry Schindler
San Diego-Mission Valley
Barry Schindler
San Francisco
Charles Thiel
San Francisco-Tiburon
Charles Thiel
San José
Richard Niewiarowski
San José South Campus
Richard Niewiarowski
SJSU - Moss Landing
Richard Niewiarowski
SJSU - Marine Laboratory
Richard Niewiarowski
San Luis Obispo
Thomas Sabol
San Marcos
Dirk Bondy
Sonoma
Maryann Phipps
Sonoma - Los Guilicos Preserve
Maryann Phipps
Sonoma - Fairfield Osborn Preserve
Maryann Phipps
Sonoma- Galbreath Wildland Preserve
Maryann Phipps
Stanislaus
Richard Niewiarowski
Stanislaus-Stockton
Richard Niewiarowski
CSU Seismic Requirements
February 15, 2024
Page 50
ATTACHMENT D
Seismic Performance Levels for Existing Buildings
(Table revision date: July 1, 2023)
Determination of expected seismic performance based on level of current CEBC Structural compliance,
Part 10 of the California Code of Regulations:
Definitions based upon California Existing Building Code (CEBC) requirements for seismic evaluation of
buildings using performance criteria in CEBC Table 317.5
2
Rating
Level 1
A building evaluated as meeting or exceeding the requirements of CEBC for Risk Category IV
performance criteria with BSE-1 and BSE-2 hazard levels without MCE
R
capping replacing BSE-R and
BSE-C respectively as given in CEBC. Alternatively, a building meeting the CBC requirements for a
new building
7
of this Category.
I
A building evaluated as meeting or exceeding the requirements of CEBC for Risk Category IV
performance criteria. Alternatively, a building meeting the CBC requirements for a new building
7
of this
Category.
II
A building evaluated as meeting or exceeding the requirements of CEBC for Risk Category I-III
performance criteria with BSE-1 and BSE-2 hazard levels without MCE
R
capping replacing BSE-R and
BSE-C respectively as given in CEBC. Alternatively, a building meeting the CBC requirements for a
new building
7.
III
5
A building evaluated as meeting or exceeding the requirements of CEBC for Risk Category I-III
performance criteria.
IV
5
A building evaluated as meeting or exceeding the requirements of CEBC for Risk Category I-III
performance criteria only if the BSE-R and BSE-C values are reduced to 2/3 of those specified for the
site.
V
5
A building evaluated as not meeting the minimum requirements for Level V designation and not
requiring a Level VII designation.
VI
A building evaluated as posing an immediate life-safety hazard to its occupants under gravity loads.
The building should be evacuated and posted as dangerous until remedial actions are taken to assure
the building can support CBC prescribed dead and live loads.
VII
Indications of Implied Risk to Life and Implied Seismic Damageability
Rating Level 1,5
Historic Risk Ratings of 6
Implied Risk to Life 3
Implied Seismic Damageability 4
DSA/SSC
UC
(In a BSE-1 Event)
I
I
Negligible
0% to 10%
II
II
Insignificant
0% to 15%
III
III
Good
Slight
5% to 20%
IV
IV
Fair
Small
10% to 30%
V
V
Poor
Serious
20% to 50%
VI
VI
Very Poor
Severe
40% to 100%
VII
VII
Dangerous
100%
Notes:
1. Earthquake damageability levels are indicated by Roman numerals I through VII. Assignments are
to be
made following a professional assessment of the building’s expected seismic performance as
measured by
the referenced technical standard and earthquake ground motions.
Equivalent Arabic numerals, fractional
values, or plus or minus values are not to be used.
These assignments were prepared by a task force of
state agency technical personnel, including
California State University, University of California, Department
of General Services, Division of the
State Architect, and Administrative Office of the Courts. The ratings
apply to structural and
non-structural elements of the building as contained in CEBC
requirements. These definitions
replace those previously used by these agencies.
CSU Seismic Requirements
February 15, 2024
Page 51
2. The current edition of the CEBC, regulates existing buildings. It uses and
references the American
Society of Civil Engineers Standard Seismic Rehabilitation of Existing Buildings,
ASCE-41.
All earthquake ground motion criteria are specific to the site of the evaluated building. The CEBC
and CBC
definitions for earthquake ground motions to be assessed are paraphrased below for
convenience:
- BSE-2, the 2,475-year return period earthquake ground motion, or the 84
th
percentile of
the Maximum Considered Earthquake ground motion for the site, whichever is lower.
- BSE-C the 975-year return period earthquake ground motion.
- BSE-1, two-thirds of the BSE-2, nominally, the 475-year return period earthquake ground
motion.
- BSE-R the 225-year return period earthquake ground motion. Risk Category is defined in
the CBC
Table 1604.5.
- The Risk Category sets the level of required seismic building performance under the CBC.
Risk Category IV includes acute care hospitals, fire, rescue and police stations and
emergency
vehicle garages, designated emergency shelters, emergency operations
centers, structures containing
highly toxic materials where the quantities exceed the
maximum allowed quantities, among others.
Risk categories I-III include all other building
uses that include most state-owned buildings.
3. Implied Risk To Life is a subjective measure of the threat of a life-threatening injury or death that
is expected
to occur in an average building in each Rating Level following the indicated technical
requirements. The terms
negligible through dangerous are not specifically defined but are
linguistic indications of the relative degree
of hazard posed to an individual occupant.
4. Implied Damageability is the level of damage expected to the average building in each Rating Level
following the
indicated technical requirements when a BSE-1 level earthquake occurs. Damage is
measured as the ratio
of the cost to repair the structure divided by the current cost to reconstruct
the structure from scratch. Such
assessments are to be completed to the requirements of ASTM
E-2557, where the damage ratio is the
Scenario Expected Loss (SEL) in the BSE-1 earthquake
ground motion evaluated at Level 1 or higher in
order to be considered appropriate.
5. The Engineer assessing the Earthquake Performance Level using the noted requirements may
conclude that the expected seismic performance is consistent with a rating one-level higher or
lower than the one assigned by the Table for Levels III, IV or V. An alternative rating may only be
assigned if an independent technical peer reviewer concurs in the evaluation that it is a better
representation of the seismic risk of the building than that determined by these definitions.
The peer review must be completed consistent with the requirements of CEBC. Note that peer
review is unlikely to improve buildings rated as VI or VII because they have fundamental seismic
system flaws. The ratings for I and II are unchanged because the performance increment between
levels is so large, and it is highly unlikely that revision could be justified.
6. Historically the University of California has used the terms good, fair, poor and very poor to
distinguish the
relative seismic performance of buildings. The concordance of values is
approximate; the former rating
procedures did not specify specific performance levels as is done
herein but were sentence fragments for
qualitative performance. For reference the historically
used Division of the State Architect and Seismic
Safety Commission levels correspond
approximately to the new numerical values.
7. For the alternative of meeting the CBC requirements for Level 3 to apply, the building must meet
all of the requirements of the CBC; this includes all requirements, including ground motions,
analysis procedures, and detailing limitations.
CSU Seismic Requirements
February 15, 2024
Page 52
ATTACHMENT E
Technical Guidelines
The CSU Seismic Requirements details requirements for CSU construction projects in addition to those that are
contained within the CBC and CEBC. The CSU Seismic Review Board (SRB) maintains guidelines on selected
topics that provide the design team additional technical details on issues that are important to the execution
of projects and represent areas of concern to the SRB. These are intended to inform the EOR so that when the
situation is encountered, the EOR can know what the SRB expects. These are not directions, but express issues
that in the experience of the SRB need to be resolved for the project to meet CSU’s objectives. They are not
intended as direction, but as alerts to important technical performance issues in the design that are likely to
be of concern in the peer review. These are intended for use for California State University construction but
may also be used by others.
1. Requirements and Recommendations for Post-Tensioned Concrete Structures
In addition to satisfying all of the requirements listed in the CSU Seismic Requirements and the applicable
sections of the California Building Standards Code, the design and construction of all post-tensioned
concrete structures shall conform to all requirements of:
American Concrete Institute ACI 318-14 for post-tensioned concrete design,
Post-Tensioning Institute - 6th Edition's recommendations for post-tensioned structures,
Additional standard of care and practice for post-tensioned structures described in this document.
A post-tensioned concrete designer shall discuss with the Seismic Peer Reviewer, at a minimum, the
recommendations in this document and comply with the intent of these requirements, unless there are
good technical reasons for not doing so.
A. American Concrete Institute 318 Requirements
1. All post-tensioning tendons shall be encapsulated in compliance with ACI 318-14 Section 20.6.3.1
through 20.6.3.3. Specifications or details that show or indicate exposed strand are not permitted.
Closure strip/pour strip details shall not show tendon tails extending into the delay strip.
2. Integrity tendons at the columns shall be clearly indicated on the structural drawings in
compliance with ACI 318-14 Section 8.7.5.6.1.
3. Minimum average of 125 psi for one- and two-way slabs and plates shall be provided in
compliance with ACI 318-14 Section 8.6.2.1.
4. Pre-compression from unbonded prestressing reinforcement, as described in ACI 318-14 Section
12.5.1.4, shall be utilized where possible to resist seismic diaphragm forces to minimize
congestion from mild reinforcement in chords and collector elements.
5. In podium structures and post-tensioned mat foundation structures where the balanced load
exceeds 100% of the concrete weight, the calculations shall clearly demonstrate that the transfer
stresses in ACI 318-14 Table 24.5.3.2 are not exceeded using a concrete compressive strength f'
ci
not greater than 75% of the 28-day compressive strength.
B. Post-Tensioning Institute Recommendations
1. Lateral curvature in banded groups of tendons should be minimized and should satisfy Section
6.3.1.3.4 and Figure 6.14 of the Post-Tensioning Manual - 6th Edition, except that the minimum
extension of straight tendon layout past an opening shall be 4'-0". The maximum lateral curvature
for banded tendon groups of 20 tendons or less shall be 1:6, with hairpin reinforcement required
for curvatures exceeding 1:12. The maximum lateral curvature for banded tendon groups in excess
of 20 tendons shall be 1:12, with hairpin reinforcement required for curvatures exceeding 1:20.
CSU Seismic Requirements
February 15, 2024
Page 53
Lateral curvature of banded groups of tendons is prohibited in areas of the slab where the
concrete top or bottom cover over the tendons is less than 2".
In general, uniformly spaced tendons should be placed orthogonally to the banded tendons.
Lateral curvature of uniform tendons should be minimized and shall satisfy Section 6.3.1.3.4 and
Figure 6.14 of the Post-Tensioning Manual - 6th Edition. When curving uniform tendons around
openings and other obstructions, tendon layout shall not exceed the maximum tendon spacing of
5'-0" or 8 times the slab thickness, whichever is smaller.
2. The seismic system layout shall adhere to the "favorable" arrangement depicted in Figure 6.2 of
the Post-Tensioning Manual - 6th Edition. The schematic layout of the seismic system shall be
provided to the Seismic Peer Reviewer at the onset of the project for a compliance review.
3. Closure strips/pour strips shall be provided in structures where significant restraint-to-shortening
exists. A minimum pour delay of 30 days from the time of the 2nd pour shall be specified for
structures with plan dimensions less than or equal to 250', and 60 days for structures with a larger
plan dimension. In structures where the plan dimensions exceed 350', a permanent expansion
joint is required.
4. Closure strips/pour strips should be limited to 30"-36" in width as stated in the Post-Tensioning
Institute document "Restraint Cracks and Their Mitigation in Unbonded Post-Tensioned Building
Structures".
5. Slab and beam thicknesses should meet or exceed the recommendations of Table 9.3 of the
Post-Tensioning Manual - 6th Edition.
C. California Building Standards Code
1. Comply with minimum fire cover as required in Table 721.1(1)4. Interior bays may be considered
restrained as described in Note k. Exterior bays shall be considered unrestrained.
D. Recommended Standards of Care & Practice
1. Unless specifically designated otherwise, when closure strips/pour strips are used, it shall be made
clear to the contractor through notes and details that the open pour strip bay is incapable of
supporting any load, including its own. Unless a greater number of bays is required by calculation,
shores shall be provided and designed such that for every open pour strip bay, a minimum of four
closed and cured bays are required for support below if the shoring does not continue to the
ground. It is recommended that all re-shores in closure/pour strip bays extend to the foundation
level.
2. When closure strips/pour strips and construction joints are used, they should be located to
minimize uneven floors, column deformations, and related construction costs. The Seismic Peer
Reviewer will want to review the basis for their locations to assure good technical performance of
the resulting structure.
3. The average compression in flat plates and flat slabs should be limited to a maximum of 250 psi,
with 150-175 psi considered optimum. Stresses may be higher in localized areas.
4. Calculations shall demonstrate the amount of dead load balanced by the post-tensioning system.
A minimum of 65% of the concrete weight shall be balanced. Balanced loads shall not exceed
125% of the concrete weight for uniformly loaded members not carrying additional floors.
5. Tendons less than 125' in length may be stressed from one end only. Tendons greater than 125' in
length shall have a "lift-off" performed at the 2nd stressing end. The maximum length of a
two-way pull is 250 feet.
CSU Seismic Requirements
February 15, 2024
Page 54
6. Every tendon shall be stressed to their full extent (one occurrence) and never partially stressed
and then restressed. This requirement is not intended to prohibit staged stressing.
7. Requiring de-tensioning of tendons should be avoided. This is a very dangerous operation for the
contractor, and alternate solutions should be thoroughly explored before de-tensioning is
proposed.
8. Care should be taken to minimize the amount and diameter of conduit placed in the decks.
Congested runs of conduit should be surface mounted below the decks. All conduits shall be
independently chaired and not supported by the post-tensioning tendons.
9. Care should be taken to minimize penetrations near column supports and tendon anchorages.
Penetrations within a 45-degree angle compression zone of post-tensioning anchors, and within
4'-0" of an anchor shall require Schedule 40 steel sleeves. PVC sleeves are not permitted in this
zone.
10. Shear stud reinforcement should be used at two-way slab banded tendon anchorages in lieu of
hairpin reinforcement to minimize congestion near anchorages.
11. In flat plates and two-way slabs, provide a minimum of #4 continuous (lapped) bottom
reinforcement, spaced not more than 30" apart each way.
12. Shot pin embedment shall be limited to 1/8” less than the cover of the concrete over the tendons.
13. Drilling into the post-tensioned slab is prohibited unless tendon locations are marked in advance,
the slab has been x-rayed, or the post-tensioning has been recorded through drone or other
photography methods. Cast-in-place non-prestressed reinforcement, bolts, plates, etc. shall be
specified in lieu of post-installed items.
14. For structures utilizing moment frames, a thorough analysis of punching shear using the story
drifts occurring during the maximum considered earthquake story drifts shall be completed.
15. Slabs 10thick or greater should utilize column caps in lieu of shear studs for punching shear
reinforcement.
16. Floor systems shall be required to be stressed within 3-5 days of the concrete pour to minimize
shrinkage cracking.
17. Deck forms shall remain in place until the deck is poured and stressed completely. Re-shores shall
be used in non-pour strip bays to distribute the weight of the wet concrete floor to cured and
stressed floors below (3 floors minimum) such that the design live load at any floor is not
exceeded. Details reflecting these requirements shall be provided on the structural design
drawings.
18. Where significant modifications over the life of the structure are anticipated, the designer should
specify a method for locating tendons, such as permanent marking on the slab, digitized
photography, etc.
Document history: First issued: November 16, 2017
CSU Seismic Requirements
February 15, 2024
Page 55
ATTACHMENT F
References
ASCE 7. Minimum Design Loads for Buildings and Other Structures, American Society of Civil Engineers, Reston,
Virginia, ASCE/SEI Standard 7-16, 2016.
ASCE-41. Seismic Rehabilitation of Existing Buildings, American Society of Civil Engineers, Reston, Virginia,
ASCE/SEI Standard 41-17, 2016.
ASTM E2557-16a. “Standard Practice for Probable Maximum Loss Evaluations for Earthquake Due Diligence
Assessments,” ASTM International, Conshohocken, PA, June 2007.
California Building Standards Code, California Code Regulations, Title 24, California Building Standards
Commission, Sacramento, California. Current Edition.
California Geological Survey, Seismic Hazard Regulatory Maps (faults, landslides, liquefaction)
http://www.conservation.ca.gov/cgs/shp
.
Code of California Regulations, Chapter 7.5 California Resources Code.
FEMA 352. Recommended Post-earthquake Evaluation and Repair Criteria for Welded Steel Moment Frame
Buildings, Federal Emergency Management Agency, Washington D.C., July 2000.
FEMAP-154. Rapid Visual Screening of Building for Potential Seismic Hazards: A Handbook, Third Edition,
Federal Emergency Management Agency, Washington D. C, 2013.
CSU Seismic Requirements
February 15, 2024
Page 56
Document history
1/15/2024
Revised Section 4.1, (10) for Scope of Review
Revised Section 5.13, (4) for Delegated Design and/or Deferred Approvals
Both Section are indicated by blue italicized text.
7/15/2023
The CSU Seismic Requirements document has been updated in its entirety including but not
limited to the following: Clarification of specific compliance requirements for the Seismic
Priory Lists; the addition of a new section for the New Seismic Assessment process;
clarifies 25% Exception in the California Existing Building Code, Section 317.3.1; clarified
sections - structural observation, pre-engineering, metal buildings & delegated design;
updated References based on new reference editions; standardizes terms and acronyms;
corrected punctuation, grammar, and spelling. All substantial revisions are indicated with
blue italicized text.
7/1/2023
All references to Seismic Policy were renamed Seismic Requirements for consistency.
The requirements were entirely edited to revise and modify many prior requirements. It is
advised that the familiar carefully reread these requirements to assure they detect the now
requirements fully. Section 5.16 on Parking structures was moved to Section 3.1. Sections
3.12 (Structural Observation was added), 5.14 (Pre-Engineered Buildings had major
additions), Section 7 (CSU Seismic Building Assessment was reorganized and the newly
adopted assessment program is discussed), Section 7 (CSU Seismic Building Assessment
Procedures) is new, Section 9 (Seismic Safety Standard for Acquired Buildings and Space)
has been modified, and Section 9.1.A changes the method of evaluation of a proposed
building to be leased.
4/30/2020
Revised Attachment C Campus Assignments for Seismic Peer Reviewers.
3/5/2020
Selected editorial change
Revised Section 3.0 with clarification of California Code of Regulations Part 2 and Part 10.
Revised Section 3.3 for Campus Seismic Coefficients.
Revised Section 3.4 with clarification of California Code of Regulations Part 10.
Revised Section 5.19 for Earthquake Soil Pressures.
Omitted Section 5.21 for Use of ASCE 7 Site Modification Factors Fa and Fv.
Revised Section 7.2 with clarification of CEBC.
Revised Attachment B and Seismic Design Table, Table 1.
Revised Attachment C Campus Assignments for Seismic Peer Reviewers.
Revised Attachment F References (to ASCE 7 & 41).
6/25/2019
Requirements for temporary structures modified to specifically apply to tents and other
temporary use structure, modification of requirements for peer review, and other items.
10/15/2018
Attachment D Table modified; added Attachment E on Post-tensioning; other minor editing;
clarification of use changes in List 1 and 2 buildings.
11/1/2016
Revises selected items and references to the new CEBC applying to existing building that
was formerly included in Part 2 Sections 3417-23.
9/10/2015
Corrected editorial items and provided accidentally deleted text.
8/11/2014
Section 5-8 First line of 3
rd
Paragraph change Design-Building to Design-Build;
Section 5-17 Change all CBC 3417 references to CEBC 3419
7/14/2014
December 21, 2011 Document Edit - 7/14/2014 Revision Issued
There are versions of the CSU Seismic Requirements that pre-date 2014.
401 Golden Shore, Long Beach CA 90802