Initial Inspections for Building Permit (BP)
Pre-foundation Inspections
Post Framing Inspections
Framing Stage Inspections
Final Inspections
1
2
4
3
5
RESIDENTIAL INSPECTIONS
PROCESS
––from start to finish––
DevelopmentATX.com
Address must be posted on the site at all times and visible from the street throughout the construction process.
Prior to the start of construction, erosion & sediment controls as well as tree protection measures need to be in
place if applicable to your project.
If applicable to your project, these inspections are required prior to the installation of insulation or wall board and after all trade work is complete.
for Plumbing Permit (PP), Mechanical Permit (MP), and Electrical Permit (EP)
100 Pre-construction Inspection BP
101 Layout Inspection BP
301 Electric Rough Inspection
EP
Frame Group Inspections
103 Framing BP
502 Plumbing Top out PP
400 Mechanical Rough
Inspections MP
106 Fire Resistance-Rated
Construction BP
(typically only required for townhouses and
duplexes)
Frame Non-Grouped Inspections
103 Framing Inspection: (non-
grouped)
Exterior Plumbing Inspections
506 Water Yard line PP
506 Sewer Yard line PP
510 Sewer tap PP
300 Electrical Slab Inspection EP
302 Electrical Grounding Inspection EP
500 Plumbing Rough Inspection PP
501 Plumbing Pre-pour Inspection PP
104 Insulation Inspection BP 105 Wallboard Inspection BP
One Time Inspections:
Pre-requisite inspections from other divisions
and/or departments they are not required for
all projects.
Water tap inspections
Environmental inspection
On Site sewage Facilities
Tree inspections
Fire Inspection
Driveway/Sidewalk Inspections
Landscaping Inspections
305 Electrical Final EP
This inspection must be approved prior to
scheduling your final group inspection
Final Group Inspections
111 Final energy BP
405 Final Mechanical MP
521 Final Plumbing PP
105 Wallboard Inspection BP
112 Final Building BP
Third party inspection reports:
On site or uploaded to permit
A/C duct leakage reports
Envelope leakage report
(new construction only)
*Termite report
**Foundation report
***Wallboard report
Impervious cover survey
(if required)
This flow chart was created as a guide to navigate through
the residential inspection process. Its contents are not
all inclusive. Compliance with this document does not
constitute compliance with all City of Austin codes and by
no means does it grant the user occupancy rights.
Anyone linked to your permit can
schedule an Inspection:
Schedule using Interactive Voice
Response (IVR) System
512-974-9405
Schedule & Pay Online
AustinTexas.gov/ABC
July 2019
Initial Inspections for
Building Permit (BP)
Pre-foundation Inspections
for Plumbing Permit (PP), Mechanical
Permit (MP), and Electrical Permit (EP)
Final Inspections
Post Framing Inspections
Framing Stage Inspections
1
2
5
4
3
RESIDENTIAL INSPECTIONS
PROCESS
––from start to finish––
DevelopmentATX.com
Address must be posted on the site at all times and visible from the street
throughout the construction process.
Prior to the start of construction, erosion & sediment controls as well as
tree protection measures need to be in place if applicable to your project.
100 Pre-construction Inspection BP
Required for:
Non-Complying structures (re-models) and Certification of
Compliance Program (Certified Applicant New Construction Projects)
101 Layout Inspection BP
Required for:
Most building permits
Approved plans required onsite
For new buildings or additions, this inspection is required after
forms have been set or the new building/addition footprint is
established
For remodels, a layout inspection is required prior to the start of
construction
A new survey is required for new construction and additions. The
survey must be done by a State of Texas Licensed Surveyor
If applicable to your project, these inspections are required prior to the
installation of insulation or wall board and after all trade work is complete.
301 Electric Rough Inspection EP
This inspection must either pass or be conducted with minimal
violations prior to scheduling the frame group inspection.
Frame Group Inspections
Grouped inspections are required for the Frame inspection and the Final
building inspection. This is to ensure our resources are being used as
efficiently as possible and minimize inspector trips to the project.
103 Framing BP
Required documentation for this stage. 3rd party pre frame
inspection (for new construction and large remodels). C.O.A approved
stamped set of plans. Truss and I joist layouts and full specification
packet from mfg.
502 Plumbing Top out PP
400 Mechanical Rough Inspections MP
These three inspections make up the frame group inspection and
must be scheduled together on the same day for most projects.
106 Fire Resistance-Rated Construction BP
(typically only required for townhouses and duplexes)
Frame Non-Grouped Inspections
103 Framing Inspection: (non-grouped)
This inspection is for small projects without trade work such as minor
remodels/renovations. A framing inspection is required any time 64
square feet of interior or exterior wall covering is removed or anytime
structural framing members are added, removed or altered.
104 Insulation Inspection BP
The application of insulation is not permitted until the frame inspection
is approved or authorization is given by residential inspection staff.
105 Wallboard Inspection BP
The installation of wall board is not permitted until the insulation
inspection is approved or authorization is given by residential
inspection staff.
300 Electrical Slab Inspection EP
(Requested and passed prior to the installation of concrete for slabs;
may also be used for underground work)
302 Electrical Grounding Inspection EP
Requested in Conjunction with 300 Slab (requested and passed prior
to the installation of concrete for foundations; must pass to receive
power)
500 Plumbing Rough Inspection PP
Required for any project with plumbing work done below the finished
floor level
501 Plumbing Pre-pour Inspection PP
Required for any project with any portion of the plumbing system
located in the buildings foundation
Exterior Plumbing Inspections
These inspections can be scheduled any time with or after the Plumbing
Rough. Must be complete before final if applicable to your project.
506 Water Yard line PP
506 Sewer Yard line PP
510 Sewer tap PP
One Time Inspections:
These are pre-requisite
inspections from other divisions
and/ or departments they are
not required for all projects. It is
important to be aware of which
of these are applicable to your
project as they can delay your
final inspections.
Water tap inspections
Environmental inspection
On Site sewage Facilities
Tree inspections
Fire Inspection
Driveway/Sidewalk Inspections
Landscaping Inspections
305 Electrical Final EP
This inspection must be
approved prior to scheduling
your final group inspection
Final Group
Inspections
111 Final energy BP
405 Final Mechanical MP
521 Final Plumbing PP
105 Wallboard Inspection BP
112 Final Building BP
Third party inspection
reports:
On site or uploaded to permit
A/C duct leakage reports
Envelope leakage report
(new construction only)
*Termite report
**Foundation report
***Wallboard report
Impervious cover survey (if
required)
***Third party wallboard inspections are required for all new
construction projects. For all other projects this inspection can either
be conducted by City Of Austin inspection staff or a third party
inspector. If using a third party inspector they are required to be a
registered design professional or an ICC certified building inspector. A
copy of their report can be collected at the final building inspection or
uploaded to your permit.
*Termite treatment typically required at this phase of construction
pursuant to the International Residential Code. Documentation of an
approved treatment by a certified applicator will be collected at the final
building inspection.
**The City of Austin does not conduct a physical foundation inspection.
Once all of the pre-foundation inspections are approved, a State of Texas
Licensed Engineer will need to inspect the foundation. A copy of their
sealed assessment is required for foundation approval. That foundation
inspection needs to be scheduled with the final group inspection and can
be collected at the final building inspection or uploaded to your permit.
July 2019
Anyone linked to your permit can schedule an Inspection
Schedule using Interactive Voice Response (IVR) System 512-974-9405
or Schedule & Pay Online AustinTexas.gov/ABC