TECHNICAL GUIDANCE DOCUMENT FOR THE
SOUTH ORANGE COUNTY HYDROMODIFICATION
CONTROL BMP SIZING TOOL
December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
Table of Contents
SECTION 1. INTRODUCTION ...................................................................................... 1-1
1.1. Applicability ........................................................................................................................... 1-1
1.1.1. Priority Development Project Categories .................................................................... 1-1
1.1.2. Redevelopment Projects ................................................................................................. 1-2
1.1.3. Effective Date ................................................................................................................... 1-3
1.2. Interim Hydromodification Criteria ................................................................................... 1-3
1.2.1. Flow Duration Matching ................................................................................................ 1-4
1.2.2. Flow Range of Interest .................................................................................................... 1-4
1.2.3. Baseline Condition .......................................................................................................... 1-4
1.2.4. Length of Rainfall Record .............................................................................................. 1-5
1.3. Hydromodification Control BMPs ..................................................................................... 1-5
1.3.1. Distributed/Onsite BMPs .............................................................................................. 1-5
1.3.2. Detention/Retention Basins .......................................................................................... 1-5
1.3.3. In-Stream Controls .......................................................................................................... 1-6
SECTION 2. BMP SIZING TOOL .................................................................................. 2-1
2.1. Methodology ........................................................................................................................... 2-1
2.2. BMP Sizing Curves ................................................................................................................ 2-6
2.3. Instructions for Spreadsheet Sizing Tool .......................................................................... 2-8
2.3.1. Inputs ................................................................................................................................ 2-8
2.3.2. Outputs ............................................................................................................................. 2-8
2.3.3. Modifying the BMP Design Configuration ................................................................. 2-9
APPENDIX I.MODELING METHODOLOGY ............................................................ A-1
List of Figures
FIGURE 1: BIORETENTION FACILITY SCHEMATIC .................................................................................... 2-2
F
IGURE 2: RECTANGULAR UNDERGROUND VAULT SCHEMATIC WITH OPEN BOTTOM ...................... 2-3
F
IGURE 3: RECTANGULAR UNDERGROUND VAULT SCHEMATIC WITH CLOSED BOTTOM ................... 2-4
F
IGURE 4: PLANTER BOX SCHEMATIC ...................................................................................................... 2-5
F
IGURE 5. SIZING CHART FOR UNIT BMP FOOTPRINT AREA ................................................................ 2-6
F
IGURE 6. SIZING CHART FOR UNIT BMP CAPTURE VOLUME .............................................................. 2-7
F
IGURE 7. SIZING CHART FOR UNIT BMP TOTAL VOLUME ................................................................... 2-7
i December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
Section 1. Introduction
This South Orange County Hydromodification Control BMP Sizing Tool Guidance Document
has been developed by the County of Orange in cooperation with the incorporated Cities of
South Orange County (Aliso Viejo, Dana Point, Laguna Beach, Laguna Hills, Laguna Niguel,
Laguna Woods, Lake Forest, Mission Viejo, Rancho Santa Margarita, San Clemente, and San
Juan Capistrano) to aid agency staff and project proponents with addressing the Interim
Hydromodification Criteria in the Fourth Term South Orange County MS4 Permit (Order R9-
2009-0002). This document serves as the technical resource companion to the
Hydromodification Control BMP Sizing Tool (Sizing Tool - South OC Interim Hydromod
Criteria v1.xlsx).
1.1. Applicability
Priority Development Projects subject to the Interim Hydromodification Criteria are described
below (see also R9-2009-0002
Section F.1.d.)
1.1.1. Priority Development Project Categories
Projects in the following categories are considered Priority Development Projects. Where a new
development project feature, such as a parking lot, falls into a Priority Development Project
category, the entire project footprint is subject to the Interim Hydromodification Criteria.
1. New development projects that create 10,000 square feet or more of impervious
surfaces (collectively over the entire project site) including commercial, industrial,
residential, mixed-use, and public projects. This category includes development projects
on public or private land which fall under the planning and building authority of the
Copermittees.
2. Automotive repair shops. This category is defined as a facility that is categorized in any
one of the following Standard Industrial Classification (SIC) codes: 5013, 5014, 5541,
7532-7534, or 7536-7539.
3. Restaurants. This category is defined as a facility that sells prepared foods and drinks
for consumption, including stationary lunch counters and refreshment stands selling
prepared foods and drinks for immediate consumption (SIC code 5812), where the land
area for development is greater than 5,000 square feet. Restaurants where land
development is less than 5,000 square feet are not subject to the Interim
Hydromodification Criteria.
4. All hillside development greater than 5,000 square feet. This category is defined as any
development which creates 5,000 square feet of impervious surface which is located in
an area with known erosive soil conditions, where the development will grade on any
natural slope that is twenty-five percent or greater.
1-1 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
5. Environmentally Sensitive Areas (ESAs)
1
. All development located within or directly
adjacent to or discharging directly to an ESA (where discharges from the development
or redevelopment will enter receiving waters within the ESA), which either creates 2,500
square feet of impervious surface on a proposed project site or increases the area of
imperviousness of a proposed project site to 10 percent or more of its naturally occurring
condition. “Directly adjacent” means situated within 200 feet of the ESA. “Discharging
directly to” means outflow from a drainage conveyance system that is composed
entirely of flows from the subject development or redevelopment site, and not
commingled with flows from adjacent lands.
6. Parking lots 5,000 square feet or more or with 15 or more parking spaces and
potentially exposed to runoff. Parking lot is defined as a land area or facility for the
temporary parking or storage of motor vehicles used personally, for business, or for
commerce.
7. Street, roads, highways, and freeways. This category includes any paved surface that is
5,000 square feet or greater used for the transportation of automobiles, trucks,
motorcycles, and other vehicles.
8. Retail Gasoline Outlets (RGOs). This category includes RGOs that meet the following
criteria: (a) 5,000 square feet or more or (b) a projected Average Daily Traffic (ADT) of
100 or more vehicles per day.
9. One acre threshold. Effective December 16, 2012, Priority Development Projects also
includes all other pollutant-generating development projects
2
that result in the
disturbance of one acre or more of land. As an alternative to this one-acre threshold, the
Copermittees may collectively identify a different threshold, provided the Copermittees’
threshold is at least as inclusive of development projects as the one-acre threshold.
1.1.2. Redevelopment Projects
Those redevelopment projects that create, add, or replace at least 5,000 square feet of
impervious surfaces on an already developed site and the existing development and/or the
redevelopment project falls under the project categories or locations listed in Section 1.1.1.
1
Environmentally Sensitive Areas (ESAs) are areas that include but are not limited to all Clean Water Act Section
303(d) impaired water bodies; areas designated as Areas of Special Biological Significance by the State Water
Resources Control Board (Water Quality Control Plan for the San Diego Basin (1994) and amendments); State
Water Quality Protected Areas; water bodies designated with the RARE beneficial use by the State Water Resources
Control Board (Water Quality Control Plan for the San Diego Basin (1994) and amendments); areas designated as
preserves or their equivalent under the Natural Communities Conservation Program within the Cities and County of
Orange; and any other equivalent environmentally sensitive areas which have been identified by the Copermittees.
2
Pollutant generating development projects are those projects that generate pollutants at levels greater than natural
background levels.
1-2 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
Where redevelopment results in an increase of less than 50 percent of the impervious surfaces of
a previously existing development, and the existing development was not subject to SSMP
requirements, the Interim Hydromodification Criteria applies only to the addition or
replacement, and not to the entire development. Where redevelopment results in an increase of
more than 50 percent of the impervious surfaces of a previously existing development, the
Interim Hydromodification Criteria applies to the entire development.
1.1.3. Effective Date
The Interim Hydromodification Criteria apply to all projects or phases of projects, unless, on
December 16, 2010, the projects or project phases meet any one of the following conditions:
1. The project or phase has begun grading or construction activities; or
2. The local permitting authority determines that lawful prior approval rights for
the project or project phase exist, whereby application of the Interim
Hydromodification Criteria to the project is legally infeasible.
1.2. Interim Hydromodification Criteria
Order No. R9-2009-0002 contains the following interim hydromodification control (IHC)
requirement:
Within one year of adoption of this Order, each Copermittee must ensure that all Priority Development
Projects are implementing the following criteria by comparing the pre-development (naturally
occurring) and post-project flow rates and durations using a continuous simulation hydrologic model
such as US EPA’s Hydrograph Simulation Program-Fortran (HSPF):
(a) For flow rates from 10 percent of the 2-year storm event to the 5 year storm event, the post-
project peak flows shall not exceed predevelopment (naturally occurring) peak flows.
(b) For flow rates from the 5 year storm event to the 10 year storm event, the post-project peak flows
may exceed pre-development (naturally occurring) flows by up to 10 percent for a 1-year
frequency interval.
The interim hydromodification criteria do not apply to Priority Development Projects where the project
discharges (1) storm water runoff into underground storm drains discharging directly to bays or the
ocean, or (2) storm water runoff into conveyance channels whose bed and bank are concrete lined all
the way from the point of discharge to ocean waters, enclosed bays, estuaries, or water storage
reservoirs and lakes.
Within one year of adoption of this Order, each Copermittee must submit a signed, certification
statement to the Regional Board verifying implementation of the interim hydromodification criteria.
The following sections discuss some of the key concepts contained in the criteria and their
relevance to preventing excessive stream erosion and sedimentation.
1-3 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
1.2.1. Flow Duration Matching
A basic concept in hydromodification management control is to design hydromodification
control BMPs such that runoff from a project does not exceed the baseline condition. The
introduction of new or increasing impervious surfaces can increase both the magnitude and
duration of runoff and it is these characteristics that the interim hydromodification criteria is
intended to address. Moreover, the effect of increased runoff on stream channel erosion is not
restricted to a specific flow rate (or design storm), but rather a range of flows are important. The
concept of flow duration matching is to incorporate hydrologic controls such that the flows and
their durations do not differ from the baseline case over some specified range of flows. Plots
showing flow versus duration are referred to as “flow duration curves
3
.” The goal of the IHC is
to integrate hydrologic controls into a proposed project such that the flow duration curve
corresponding to the post-project condition agrees with the baseline condition curve over the
range of flows of interest. When this is accomplished, runoff from the proposed development
would not contribute additional erosive forces in the receiving stream channel.
1.2.2. Flow Range of Interest
Geomorphic research has found that the most important range of flows, from the perspective of
affecting channel form, are the relatively more frequent flows that are contained primarily
within the active channel and not the rare, high magnitude flows. Flows which create shear
stresses (forces) high enough to initiate sediment transport within the channel and which occur
frequently enough to have influence over long-term stream morphology are considered
“geomorphically-significant” flows. Sand bedded streams have lower critical shear stresses and
are readily moved by increased flows, whereas channel materials that are larger, such as gravels
and cobbles, and more cohesive, such as clays, are more resistant to being moved. The IHC calls
for considering a range of flows extending from 10% of the 2-year peak flow (0.1Q2) to the 10-
year peak flow (Q10)
4
.
1.2.3. Baseline Condition
The baseline condition assumption depends on the requirements of the MS4 Permit. The
baseline condition in the South Orange County MS4 Permit is the pre-development (naturally
occurring) condition. This is equivalent to the most prominent naturally vegetated condition
that existed prior to urbanization and agriculture in those portions of southern Orange County
that are likely to be developed. For example, the oak grasslands habitat is one possible pre-
development condition that might be adopted as part of the interim criteria.
3
A flow duration curve is a plot of flow rate (y-axis) vs. the cumulative duration, or percentage of time, that a flow
rate is exceeded in the simulation record (x-axis).
4
Specifically, the South Orange County Interim Hydromodification Criteria requires that post-project peak flows
not exceed pre-development flows up to Q
5
. For flow rates from Q
5
to Q
10
, post-project peak flows may exceed pre-
development peak flows by up to 10 percent for a 1-year frequency interval.
1-4 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
1.2.4. Length of Rainfall Record
The IHC calls for the use of continuous hydrologic modeling to account for the response of
channels to a range of flows, as described above. These types of models use a continuous
rainfall record to predict project runoff. As a practical matter, the longer the rainfall record the
better, but at a minimum, a rainfall record of at least 20 years with an hourly time interval of
rainfall readings should be used. Upwards of 50 years is preferred if the data is available.
1.3. Hydromodification Control BMPs
A variety of volume / flow management structural BMPs are available that utilize the following
two basic principles:
Detain runoff and release it in a controlled way that either mimics pre-development
hydrograph or reduces flow durations to account for a reduction in sediment supply.
Manage excess runoff volumes through one or more of the following pathways:
infiltration, evapotranspiration, storage and use, discharge at a rate below the critical
rate for adverse impact, or discharge downstream to a non-susceptible water body.
1.3.1. Distributed/Onsite BMPs
Distributed BMPs are small scale facilities, typically treating runoff from less than ten acres.
These types of facilities include, but are not limited to, infiltration trenches, bioretention areas,
permeable pavement, green roofs, cisterns, and underground vaults or pipes. These types of
facilities may also help to achieve the MS4 Permit’s LID performance standard.
1.3.2. Detention/Retention Basins
Detention/retention basins are stormwater management facilities that are designed to detain
and infiltrate runoff from one or multiple projects or project areas. These basins are typically
shallow with flat, vegetated bottoms. Detention/retention basins can be constructed by either
excavating a depression or building a berm to create above ground storage, such that runoff can
drain into the basin by gravity. Runoff is stored in the basin as well as in the pore spaces of the
surface soils. Pretreatment BMPs such as swales, filter strips, and sedimentation forebays
minimize fine sediment loading to the basins, thereby reducing maintenance frequencies.
Detention/retention basins for hydromodification management incorporate outlet structures
designed for flow duration control. These basins can also be designed to support flood control
and water quality treatment objectives in addition to hydromodification. If underlying soils are
not suitable for infiltration, the basin may be designed for flow detention only, with alternative
practices to manage increased volumes, such as storage and use, discharge at a rate below the
critical rate for adverse impacts, or discharge to a non-susceptible water body.
Detention/retention basins should be designed to receive flows from developed areas only, for
both design optimization as well as to avoid intercepting coarse sediments from open spaces
1-5 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
1-6 December 13, 2010
that should ideally be passed through to the stream channel. Reduction in coarse sediment
loads contributes to channel instability.
1.3.3. In-Stream Controls
Hydromodification management can also be achieved by in-stream controls, including drop
structures, bed and bank reinforcement, and grade control structures.
Drop Structures
Drop structures are designed to reduce the channel slope, thereby reducing the shear stresses
generated by stream flows. These controls can be incorporated as natural appearing rock
structures with a step-pool design which allows drop energy to be dissipated in the pools while
providing a reduced longitudinal slope between structures.
Grade Control Structures
Grade control structures are designed to maintain the existing channel slope while allowing for
minor amounts of local scour. These control measures are often buried and would entail a
narrow trench across the width of the stream backfilled with concrete or similar material, as
well as the creation of a “plunge pool” feature on the downstream side of the sill by placing
boulders and vegetation. A grade control option provides a reduced footprint and impact
compared to drop structures, which are designed to alter the channel slope.
Bed and Bank Reinforcement
Channel reinforcement serves to increase bed and bank resistance to stream flows. In addition
to conventional techniques such as riprap and concrete, a number of vegetated approaches are
increasingly utilized, including products such as vegetated reinforcement mats. This technology
provides erosion control with an open-weave material that stabilizes bed and bank surfaces and
allows for re-establishment of native plants, which serves to further increase channel stability.
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
Section 2. BMP Sizing Tool
Hydrologic modeling was used to develop a series of simplified sizing charts and a sizing
spreadsheet tool to standardize the sizing of four types of BMPs for hydromodification control.
The sizing tool allows project proponents to easily determine the necessary BMP storage
volume and footprint area for flow duration control as a function of the proposed level of
imperviousness and the onsite Hydrologic Soil Group
5
(A/B or C/D). The sizing tool takes into
account a reasonable range of design and environmental conditions. In addition, because the
BMP footprint is expressed as a percentage of the project catchment area, the BMPs can range in
size. This flexibility allows a project proponent to strategically situate many small scale
distributed facilities or fewer larger facilities depending on site constraints.
The four BMP types incorporated in the sizing tool are: (1) a bioretention facility, (2) a
rectangular underground vault with an open bottom, (3) a rectangular underground vault with
a closed bottom, and (4) a planter box. The bioretention facility and open-bottomed vault allow
for infiltration into the underlying soils and the closed bottom vault and planter boxes do not.
Figures 1 through 4 illustrate the BMP configurations that were modeled to develop the sizing
tool.
2.1. Methodology
For each BMP type, ten continuous hydrologic simulations using US EPA’s Storm Water
Management Model (SWMM) were conducted with a combination of two soil types (A/B and
C/D) and five imperviousness values (1%, 25%, 50%, 75%, and 100%). The simulations were
performed on a generic catchment area in order to generate long-term flow records. A generic 1
acre catchment area was selected to size the bioretention facility, a 10 acre catchment area was
used to size the underground vaults, and a ¼ acre catchment area was used to size the planter
box
6
. The 1% imperviousness simulation represents the baseline (pre-development) flow
records and the 25%, 50%, 75%, and 100% imperviousness simulations represent a range of
post-development conditions. The BMPs were sized by iteratively adjusting the BMP footprint
until flow duration control was achieved with the minimum BMP footprint.
Appendix I provides more detail on the modeling approach.
5
Based on NRCS soil survey data, approximately 47% of South Orange County is considered Type D soil, 37% is
Type C, 13% is Type B, and 3% is Type A.
6
These areas were used because they are between the expected lower and upper limits of catchment areas likely to
drain into each BMP type. Bioretention facilities were expected to be applied to catchments ranging between 5,000
square feet (0.11 acres) to 5 acres. Underground vaults were expected to be applied to catchments ranging between
1 acre and 50 acres. Planter boxes were expected to be applied to catchments less than 1 acre.
2-1 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
2.2. BMP Sizing Curves
Figure 5 below shows the resulting BMP footprint area, Figure 6 shows the BMP capture
volume, and Figure 7 shows the total volume (including the suggested freeboard volumes
illustrated on Figures 1 to 4). The BMP footprint is defined as the plan view area at the overflow
weir crest elevation and is expressed as a percentage of the tributary catchment area. The BMP
capture volume is defined as the storage volume in the BMP below the overflow crest elevation
and has units of watershed inches. The total BMP volume is defined as the storage volume
contained beneath the suggested freeboard elevation, also expressed in watershed inches.
Regression lines are provided on the charts so that the unit footprint area and storage volume
can be interpolated for any value of imperviousness.
Figure 5. Sizing Chart for Unit BMP Footprint Area
2-6 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
Figure 6. Sizing Chart for Unit BMP Capture Volume
Figure 7. Sizing Chart for Unit BMP Total Volume
2-7 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
2.3. Instructions for Spreadsheet Sizing Tool
The South Orange County Hydromodification Control BMP Sizing Tool spreadsheet is
structured so that inputs entered in the “master” worksheet generate the necessary parameters
for sizing BMPs to meet the IHC. The inputs and outputs to the spreadsheet master worksheet
are described below, as well as allowable modifications to the design configurations illustrated
in Figures 1 through 4 that would comply with the IHC.
2.3.1. Inputs
Catchment ID is a label that helps to organize different drainage areas within a Priority
Development Project. The user can choose any naming convention they wish for the Catchment
ID.
BMP Type must be selected from a pull-down menu of the four BMP types included in the tool.
Soil Type must be selected from a pull-down menu as “A/B” if the catchment is a Type A or B
soil or “C/D” if the catchment is a Type C or D soil
7
.
Catchment Area is the acreage tributary to the BMP being sized. For a bioretention facility or
planter box, the catchment area must include the area of the BMP itself. This is not the case for
the underground vault BMPs because precipitation does not fall directly on the BMPs.
Imperviousness is the proportion of impervious surface area in the project catchment.
Impervious areas include, but are not limited to, rooftops, asphalt pavement, and concrete
surfaces. For a bioretention facility or planter box, the BMP footprint area should be assumed to
be impervious.
85th Percentile Storm Depth is used to compute the Stormwater Quality Design Volume
(SQDV) per the Orange County Drainage Area Management Plan Exhibit 7.II, Model Water
Quality Management Plan.
2.3.2. Outputs
BMP Footprint Area is the area, in square feet, of the BMP at the overflow weir crest.
BMP Capture Volume is the storage capacity, in cubic feet, of the BMP below the overflow weir
crest. This volume includes the air space above the media material, as well as the interstitial
space in the media (i.e. gravel, choke stone, sand, plant media, and mulch).
Total BMP Volume is the storage capacity, in cubic feet, below the suggested freeboard
elevation. Total BMP Volume is not viewed to be as crucial to flow duration control as the
Capture Volume.
7
Hydrologic Soil Group for a site can be found at http://websoilsurvey.nrcs.usda.gov/app/websoilsurvey.aspx.
2-8 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
Orifice Diameter is the size of the low flow control opening, in inches. The diameter is rounded
to the nearest 1/32nd inch, so that standard drill bits can be used to create the orifice.
The last output provides a yes or no answer to the question, “Is the Hydromodification Capture
Volume greater than the SQDV?” If the answer is “yes”, then the hydromodification BMP
sizing outputs are appropriate. If the answer is “no” then the SQDV should be used in place of
the Hydromodification BMP Capture Volume. For guidance on sizing treatment control BMPs,
see Orange County Drainage Area Management Plan Exhibit 7.II, Model WQMP
8
.
2.3.3. Modifying the BMP Design Configuration
If a project proponent wishes to modify the design configurations provided in Figures 1
through 4 while still using the spreadsheet tool to size the BMP, then the modified BMP shall
meet the following criteria:
1. If the BMP allows for infiltration into the underlying soils (i.e. bioretention or vault with
open bottom), then the footprint area at the bottom of the BMP shall be equal to or
greater than the bottom footprint calculated using the sizing tool
9
.
2. The BMP Capture Volume stored below the overflow weir crest shall be equal to or
greater than the capture volume calculated using the sizing tool.
3. The available freeboard height and storage above the overflow weir crest can be
modified as long as the peak design discharge, required by the Orange County Local
Drainage Manual (OCEMA 1996) and Hydrology Manual (OCEMA 1986) or the local
permitting authority, can be properly conveyed.
4. If the full brim pressure on the bottom orifice is modified, then the low flow orifice
diameter shall be modified such that the low flow threshold (0.1Q
2
) is conveyed at the
new full brim pressure.
One example of a configuration modification is to reduce the depth of an underground vault
with an open bottom. If the design depth is changed from 7 feet, as shown in Figure 2, to 4 feet,
then the footprint area must increase to maintain the BMP Capture Volume. For this case the
footprint must increase by at least 7/4 (1.75) times assuming the walls are vertical. Increasing
the design depth beyond 7 feet in order to reduce the footprint, however, is not an allowable
modification.
If the underground vault requires a low flow orifice, then the orifice diameter must increase
such that the low flow threshold (0.1Q
2
) is conveyed at the reduced brim-full depth. For
8
The SQDV will only be greater than the Hydromodification Capture Volume if the developed catchment has low
imperviousness (2% to 4% or lower). Most Priority Development Projects are expected to have greater
imperviousness than this threshold.
9
For the bioretention facility, the bottom footprint area is the same as the top of media, which can be calculated
assuming 3:1 side slopes dropping 1.5-ft from the overflow weir crest elevation to the top of mulch.
2-9 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
2-10 December 13, 2010
instance, assume the sizing tool computes the orifice diameter to be 3 inches for a brim-full
depth of 6.5 feet. If the brim-full depth of the modified vault is 3.5 feet, then the modified low
flow orifice diameter can be computed using the following formula
10
:
D
mod
= D
tool
[H
tool
/H
mod
]
1/4
Where:
D
mod
= modified low flow orifice diameter (inches)
D
tool
= calculated low flow orifice diameter from the sizing tool (inches)
H
tool
= assumed brim-full pressure head used in the sizing tool (feet)
H
mod
= modified brim-full pressure head (feet)
Using this formula for the example, the modified low flow orifice diameter (D
mod
) is 3-½ inches
(3 * [6.5/3.5]
1/4
).
10
This formula is derived from the orifice discharge equation provided in Appendix I.
OC LID TECHNICAL GUIDANCE DOCUMENT
Appendix I. Modeling Methodology
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
APPROACH
BMP types were selected based on responses to a three question survey of the South Orange
County cities, provided in Table A-1 below. The responses indicate that smaller, site-based
BMPs were more likely to be implemented during the interim period than larger regional
detention basins.
Table A-1. BMP Survey Responses
QUESTIONS
Municipality
Mission
Viejo
Laguna
Niguel
Dana
Point
Lake
Forest
San Juan
Capistrano
1. What types of new
development and
redevelopment projects
are anticipated which may
need to use the interim
hydromodification sizing
tool?
Commercial
High
Density
Residential
Small
Redevelop-
ment
Residential,
Commercial,
Sports Park, &
Playgrounds
Redevelopment
2. What is the range of
project sizes that are
anticipated in the next
year or so?
1
0.5 to 10.3
acres
2 acres
< 1 to 2.3
acres
60 to < 800
acres
1 to < 50 acres
3. What two types of
structural BMPs would be
most useful to have a
design tool for?
Under-
ground
Detention
Vault &
Bioretention
Bioretention
Under-
ground
Detention
Vault &
Bioretention
Detention
Pond,
Detention
Vault,
Detention
Pipe, &
Bioretention
Detention Vault,
Detention Pipe,
Bioretention,
Detention
Domes, &
Combined
Bioretention and
Vault
1
Large project areas may need to be subdivided into multiple catchment areas.
ASSUMPTIONS
For each BMP type, ten continuous hydrologic simulations associated with a combination of
two soil types (A/B and C/D) and five imperviousness values (1%, 25%, 50%, 75%, and 100%),
were performed on a generic catchment area in order to generate long-term flow records. The
generic catchment area was set to 1 acre to size the bioretention facility, 10 acres to size the
underground vaults, and ¼ acre to size the planter box. These areas were used because they are
between the expected lower and upper limits of catchment areas likely to drain into each BMP
type. Bioretention facilities are expected to be applied to catchments ranging between 5,000
square feet (0.11 acres) to 5 acres, underground vaults are expected to be applied to catchments
ranging between 1 acre and 50 acres, and planter boxes are expected to be applied to catchments
less than 1 acre. While the 1% imperviousness simulation represents the baseline pre-
development flow records, the 25%, 50%, 75%, and 100% simulations represent a range of post-
development flow conditions. The BMPs were sized by iteratively adjusting the BMP footprint
until flow duration control was achieved, as stipulated by the IHC for the minimum footprint
allowable.
A-2 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
Geosyntec performed continuous simulations using US EPA’s Storm Water Management Model
(SWMM). Stage-storage-discharge relationships were included in the post-development SWMM
simulations so that the post-development flow records could be routed through the BMP being
sized. Table A-2 below provides the key SWMM catchment parameters.
Table A-2. Key SWMM Catchment Parameters
PARAMETER VALUE
Precipitation Gage Trabuco
Area
1 acre (Bioretention)
10 acres (Underground Vault)
Catchment Slope 5 %
% Imperviousness
Pre-development: 1%
Post-Development: 25%, 50%, 75%, & 100%
Depression Storage – Impervious 0.02 inches
Depression Storage – Pervious 0.10 inches
Infiltration Method GREEN AMPT
Hydraulic Conductivity
Pre-Development A/B Soils: 0.30 inches/hour
Post-Development A/B Soils: 0.23 inches/hour
Pre-Development C/D Soils: 0.05 inches/hour
Post-Development C/D Soils: 0.04 inches/hour
Detailed SWMM parameters are listed in Table A-3 below.
Table A-3. Detailed SWMM Catchment Parameters
PARAMETER UNIT
VALUE
A/B Soils
VALUE
C/D Soils
Subcatchment SWMM Parameters
Precipitation Gage -- Trabuco Trabuco
Outlet -- N/A N/A
Area Acres 10, 1, 0.25 10, 1, 0.25
Width Feet 660, 209, 104 660, 209, 104
% Slope % 5 5
% Imperv % 1, 25, 50 75, & 100 1, 25, 50 75, & 100
N-Imperv -- 0.012 0.012
N-Perv -- 0.15 0.15
Dstore-Imperv Inches 0.02 0.02
Dstore-Perv Inches 0.1 0.1
%Zero-Imperv % 25 25
Subarea Routing -- OUTLET OUTLET
Percent Routed % 100 100
Infiltration Method GREEN_AMPT GREEN_AMPT
Suction Head Inches 1.5 8
Undeveloped Conductivity in/hr 0.3 0.05
Developed Conductivity in/hr 0.23 0.04
A-3 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
PARAMETER UNIT
VALUE
A/B Soils
VALUE
C/D Soils
Initial Deficit Fraction 0.33 0.30
Groundwater yes/no NO NO
Climatology SWMM Parameters
Temperature -- N/A N/A
Evaporation Monthly Averages CIMIS Zone 4 CIMIS Zone 4
Wind Speed -- N/A N/A
Snow Melt -- N/A N/A
Areal Depletion -- N/A N/A
Simulation Options
Infiltration Model -- Green Ampt Green Ampt
Routing Method -- None None
Reporting Time Step Days:Hr:Min:Sec 1 hour 1 hour
Dry Weather Time Step Days:Hr:Min:Sec 4 hours 4 hours
Wet Weather Time Step Days:Hr:Min:Sec 15 minutes 15 minutes
Routing Time Step Seconds 60 60
Dynamic Wave Inertial Terms -- Dampen Dampen
Define Supercritical Flow By -- Both Both
Force Main Equation -- Hazen-Williams Hazen-Williams
Variable Time Step
Adjustment Factor
% 75 75
Conduit Lengthening Seconds 0 0
Minimum Surface Area Square Feet 0 0
Additional model parameters and assumptions include:
Precipitation Data: The Trabuco precipitation record was used because the rainfall
intensity is greater than that measured at the Laguna gage, the other long-term
precipitation record in South Orange County. By using a more intense rainfall record,
this results in more conservative BMP sizes.
Catchment Dimensions: The assumed generic catchment width is square.
Slope: A typical South Orange County terrain is assumed to have a 5% catchment slope.
Infiltration Parameters: The assumed pre-development hydraulic conductivity is based
on typical values associated with Soil Types A/B and C/D, as referenced in SWMM
Hydrology: Runoff and Service Modules (James et al, 2002)
11
. The post-development
hydraulic conductivity was assumed to be 75% of the pre-development hydraulic
11
James W., Huber W.C., Pitt R.E., Dickinson R.E., James W.R.C. 2002. SWMM Hydrology: Runoff and Service
Modules.
A-4 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
conductivity in order to account for disturbance and compaction. The post-development
hydraulic conductivity was also used as the infiltration rate within the BMPs.
BMP CONFIGURATION ASSUMPTIONS
Bioretention Facility Assumptions (Figure 1)
Low flow threshold = 10% of the 2-year pre-development flow rate (0.1Q
2
)
12
.
Infiltration rate into A/B soils = 0.23 inches/hour. Infiltration rate into C/D Soils = 0.04
inches/hour.
Media storage capacity = porosity – field capacity. This assumes that only freely drained
storage is considered. The storage capacity used for gravel and choke stone is 0.4, for
sand and plant media is 0.26, and for mulch is 0.5.
An underdrain and low flow orifice is used for C/D Soils, but not for A/B Soils.
Low flow orifice is sized to discharge the low flow threshold at the head associated with
the overflow weir elevation (C/D Soils only)
13
.
Slotted underdrain pipe capacity and infiltration rate through media is significantly
greater than the low flow threshold of 0.1Q
2
(C/D Soils only).
Overflow weir crest length is sized to convey the peak design flowrate determined from
the Orange County flood control standards
14
.
Slotted underdrain pipe invert and low flow orifice @ 0.5-ft from bottom of facility (C/D
Soils only).
Top of Media @ 4.75-ft from bottom of facility.
Vertical walls between the bottom of facility and top of media.
3:1 side slopes above top of media.
Overflow weir @ 6.25-ft from bottom of facility.
0.5-ft of freeboard above overflow weir.
Underground Vault with Open Bottom Assumptions (Figure 2)
Low flow threshold = 10% of the 2-year pre-development flow rate (0.1Q
2
).
12
0.1Q2 was determined by constructing a partial-duration series as follows. For the entire runoff time series
generated by the model, the runoff time series was divided into a set of discrete events. Flow events were
considered separate when the flow rate dropped below a threshold value of 0.002 cfs/acre for a period of at least 24
hours. The peak flow was determined for each event and ranked to establish the 2 year return frequency.
13
Discharge from an orifice is calculated using the equation Q = 3.78 D
2
H
1/2
where:
Q = discharge (cfs); D = diameter (ft); H = head above the orifice center (ft).
14
Discharge from a rectangular weir is calculated using the equation Q = 3.33 L H
1.5
if the weir is suppressed and
Q = 3.33
(L - 0.2H) H
1.5
if the weir is contracted where:
Q = discharge (cfs), L = crest length (ft); H = head above weir crest (ft).
A-5 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
Infiltration rate into A/B soils = 0.23 inches/hour. Infiltration rate into C/D Soils = 0.04
inches/hour.
Low flow orifice is included for C/D Soils, not for A/B Soils.
Low flow orifice is sized to discharge the low flow threshold at the head associated with
the overflow weir elevation (C/D Soils only).
Overflow weir crest length is sized to convey the peak design flow rate determined from
Orange County flood control standards.
Low flow orifice discharge @ 0.5-ft from bottom of facility (C/D Soils only).
Vertical walls throughout.
Overflow weir @ 7.0-ft from bottom of facility.
1.0-ft of freeboard above overflow weir.
Underground Vault with Closed Bottom Assumptions (Figure 3)
Low flow threshold = 10% of the 2-year pre-development flow rate (0.1Q
2
).
No infiltration into soils.
Low flow orifice is included for C/D and A/B Soils.
Low flow orifice is sized to discharge the low flow threshold at the head associated with
the overflow weir elevation.
Overflow weir crest length is sized to convey the peak design flow rate determined from
Orange County flood control standards.
Low flow orifice discharge is located at same elevation as the bottom of vault. (Note:
sediment storage capacity should be provided below the low flow orifice plate as shown
on Figure 3; this can be accomplished by placing the outlet structure in a separate
manhole or lowering the vault floor below the outlet. Any added storage below the
outlet does not count towards the BMP Capture Volume.)
Vertical walls throughout.
Overflow weir @ 7.0-ft from bottom of facility.
1.0-ft of freeboard above overflow weir.
Planter Box Assumptions (Figure 4)
Low flow threshold = 10% of the 2-year pre-development flow rate (0.1Q
2
).
No infiltration into soils.
A-6 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
Media storage capacity = porosity – field capacity. This assumes that only freely drained
storage is considered. The storage capacity used for gravel and choke stone is 0.4, for
sand and planting media is 0.26, and for mulch is 0.5.
An underdrain and low flow orifice is used for C/D and A/B Soils.
Low flow orifice is sized to discharge the low flow threshold at the head associated with
the overflow weir elevation.
Slotted underdrain pipe capacity and infiltration rate through media is significantly
greater than the low flow threshold of 0.1Q
2
.
Overflow weir crest length is sized to convey the peak design flowrate determined from
the Orange County flood control standards.
Slotted underdrain pipe invert and low flow orifice @ bottom of facility.
Top of Media @ 4.25-ft from bottom of facility.
Vertical walls throughout.
Overflow weir @ 5.25-ft from bottom of facility.
0.25-ft of freeboard above overflow weir.
RESULTS
Figures A-1 through A-8 below provide the flow duration curves for all forty SWMM
simulations (2 soil types x 4 BMP types x 5 imperviousness values), which demonstrate that the
IHC is met. The IHC is met because the flow duration curve for the post-development
condition with BMPs is below the pre-development (naturally-occurring) condition within the
flow limits specified (0.1Q
2
to Q
10
).
In evaluating the proportions of runoff exiting the modeled BMPs, it was confirmed that the
modeled hydromodification BMPs meet the 80% runoff capture goal for treatment
15
, as shown
in Table A-4 below.
15
It was assumed that BMPs, which allow infiltration (bioretention and underground vault w/ open bottom) and are
placed in C/D soils, do require biotreatment, via a low flow orifice, in order to feasibly achieve 80% runoff capture.
BMPs, which allow infiltration and are in areas with A/B soils, do not need biotreatment to achieve 80% runoff
capture. BMPs, which do not allow infiltration (underground vault with closed bottom and planter box), do require
biotreatment, via a low flow orifice, in order to feasibly achieve 80% runoff capture.
A-7 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
Table A-4. Proportions of Runoff Exiting the BMPs
BMP Type
Soil
Type
Imperviousness
(%)
Infiltrated
Runoff
(%)
Runoff
Routed
Through
Orifice
(%)
Bypassed
Runoff
(%)
Captured
Runoff
(%)
Goal Met
for
80%
Capture
(yes/no)
Bioretention C/D 100 18.0 75.0 7.1 92.9 Yes
Bioretention C/D 75 13.8 77.6 8.6 91.4 Yes
Bioretention C/D 50 14.6 75.4 9.9 90.1 Yes
Bioretention C/D 25 15.1 71.0 14.0 86.0 Yes
Bioretention A/B 100 98.0 N/A 2.0 98.0 Yes
Bioretention A/B 75 97.2 N/A 2.8 97.2 Yes
Bioretention A/B 50 96.7 N/A 3.3 96.7 Yes
Bioretention A/B 25 93.1 N/A 6.9 93.1 Yes
Vault-Open C/D 100 20.3 74.7 5.0 95.0 Yes
Vault-Open C/D 75 17.5 75.6 6.8 93.2 Yes
Vault-Open C/D 50 18.7 73.7 7.6 92.4 Yes
Vault-Open C/D 25 14.6 72.0 13.4 86.6 Yes
Vault-Open A/B 100 98.2 N/A 1.8 98.2 Yes
Vault-Open A/B 75 97.8 N/A 2.2 97.8 Yes
Vault-Open A/B 50 96.4 N/A 3.6 96.4 Yes
Vault-Open A/B 25 94.6 N/A 5.4 94.6 Yes
Vault-Closed C/D 100 N/A 93.8 6.2 93.8 Yes
Vault-Closed C/D 75 N/A 93.0 7.0 93.0 Yes
Vault-Closed C/D 50 N/A 92.2 7.8 92.2 Yes
Vault-Closed C/D 25 N/A 86.3 13.7 86.3 Yes
Vault-Closed A/B 100 N/A 98.4 1.6 98.4 Yes
Vault-Closed A/B 75 N/A 98.0 2.0 98.0 Yes
Vault-Closed A/B 50 N/A 97.4 2.6 97.4 Yes
Vault-Closed A/B 25 N/A 96.2 3.8 96.2 Yes
Planter Box C/D 100 N/A 92.6 7.4 92.6 Yes
Planter Box C/D 75 N/A 91.8 8.2 91.8 Yes
Planter Box C/D 50 N/A 91.0 9.0 91.0 Yes
Planter Box C/D 25 N/A 89.1 10.9 89.1 Yes
Planter Box A/B 100 N/A 97.7 2.3 97.7 Yes
Planter Box A/B 75 N/A 97.7 2.4 97.7 Yes
Planter Box A/B 50 N/A 97.3 2.7 97.3 Yes
Planter Box A/B 25 N/A 96.2 3.8 96.2 Yes
A-8 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
0.01
0.10
1.00
1 10 100 1,000 10,000
Discharge [cfs]
Duration [hrs]
Flow Duration Curves for Bioretention Discharge:
C/D Soils, 1 Acre Catchment
Pre-Development
25% Imperviousness
50% Imperviousness
75% Imperviousness
100% Imperviousness
Q1 0=0.906cfs
Q5 =0.808 cfs
0.1Q2= 0.055 cfs
Figure A-1. Flow Duration Results for Bioretention BMP with C/D Soils
0.01
0.10
1.00
110100
Discharge [cfs]
Duration [hrs]
Flow Duration Curves for Bioretention Discharge:
A/B Soils, 1 Acre Catchment
Pre-Development
25% Imperviousness
50% Imperviousness
75% Imperviousness
100% Imperviousness
Q1 0=0.660cfs
Q5 =0.571 cfs
0.1Q2= 0.030 cfs
Figure A-2. Flow Duration Results for Bioretention BMP with A/B Soils
A-9 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
0.10
1.00
10.00
1 10 100 1,000 10,000
Discharge [cfs]
Duration [hrs]
Flow Duration Curves for Open Bottom Underground Vault Discharge:
C/D Soils, 10 Acre Catchment
Pre-Development
25% Imperviousness
50% Imperviousness
75% Imperviousness
100% Imperviousness
Q1 0=8.22cfs
Q5 =7.02 cfs
0.1Q2=0.49cfs
Figure A-3. Flow Duration Results for Open Bottom Underground Vault BMP with C/D Soils
0.10
1.00
10.00
110100
Discharge [cfs]
Duration [hrs]
Flow Duration Curves for Open Bottom Underground Vault Discharge:
A/B Soils, 10 Acre Catchment
Pre-Development
25% Imperviousness
50% imperviousness
75% imperviousness
100% Imperviousness
Q1 0=5.21cfs
Q5 =4.09 cfs
0.1Q2=0.21cfs
Figure A-4. Flow Duration Results for Open Bottom Underground Vault BMP with A/B Soils
A-10 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
0.10
1.00
10.00
1 10 100 1,000 10,000
Discharge [cfs]
Duration [hrs]
Flow Duration Curves for Closed Bottom UndergroundVault Discharge:
C/D Soils, 10 Acre Catchment
Pre-Development
25% Imperviousness
50% Imperviousness
75% Imperviousness
100% Imperviousness
Q1 0=8.22cfs
Q5 =7.02 cfs
0.1Q2=0.49cfs
Figure A-5. Flow Duration Results for Closed Bottom Underground Vault with C/D Soils
0.10
1.00
10.00
110100
Discharge [cfs]
Duration [hrs]
Flow Duration Curves for Closed Bottom Underground Vault Discharge:
A/B Soils, 10 Acre Catchment
Pre-Development
25% Imperviousness
50% imperviousness
75% imperviousness
100% Imperviousness
Q1 0=5.21cfs
Q5 =4.09 cfs
0.1Q2=0.21cfs
Figure A-6. Flow Duration Results for Closed Bottom Underground Vault with A/B Soils
A-11 December 13, 2010
SOUTH ORANGE COUNTY HYDROMODIFICATION CONTROL BMP SIZING TOOL GUIDANCE DOCUMENT
A-12 December 13, 2010
0.00
0.01
0.10
1 10 100 1,000
Discharge [cfs]
Duration [hrs]
Flow Duration Curves for Planter Box Discharge:
C/D Soils, 0.25 Acre Catchment
Pre-Development
25% Imperviousness
50% Imperviousness
75% Imperviousness
100% Imperviousness
Q1 0=0.228cfs
Q5=0.204 cfs
0.1Q2=0.014cfs
Figure A-7. Flow Duration Results for Planter Box BMP with C/D Soils
0.00
0.01
0.10
1 10 100 1,000
Discharge [cfs]
Duration [hrs]
Flow Duration Curves for Planter Box Discharge:
A/B Soils, 0.25 Acre Catchment
Pre-Development
25% Imperviousness
50% Imperviousness
75% Imperviousness
100% Imperviousness
Q1 0=0.170cfs
Q5 =0.150 cfs
0.1Q2=0.008 cfs
Figure A-8. Flow Duration Results for Planter Box BMP with A/B Soils