United States General Accounting Office
GAO
Briefing Report to the Honorable
Hank Brown, U.S. Senate
October 1994
NEW DENVER
AIRPORT
Impact of the Delayed
Baggage System
GAO/RCED-95-35BR
GAO
United States
General Accounting Office
Washington, D.C. 20548
Resources, Community, and
Economic Development Division
B-258641
October 14, 1994
The Honorable Hank Brown
United States Senate
Dear Senator Brown:
This briefing report responds to certain issues in your May 5, 1994, letter
concerning delays in the opening of the new Denver International Airport.
It documents the briefing we provided to your office on September 22,
1994, and specifically addresses three areas regarding the new airport:
(1) problems with the baggage handling system that delayed the airport’s
opening, (2) the added costs resulting from the delay, and (3) the adequacy
of expected revenues at the new airport to cover the cost of operating the
facility and to service its debt. This report addresses issues you identified
as requiring an immediate response. We will meet with your staff to
discuss the other, longer-term, issues raised in your letter.
Background
The new Denver International Airport was built to replace Stapleton
International Airport, a facility that has experienced serious air traffic
congestion and noise problems.
1
The new airport is the first major airport
to be built in the United States since 1974. Spread out over 50 square miles,
it has the capacity to expand eventually to 12 runways. On opening, the
airport will have a terminal building and three concourses, the farthest of
which will be about 1 mile from the terminal. Concourse A will serve
Continental Airlines, Continental Express, GP Express, and a variety of
international carriers. Concourse B will serve United Airlines and United
Express. American, Delta, Frontier, Markair, Northwest, TWA, and USAir
will use Concourse C.
On the basis of cost estimates as of September 1, 1994, the total cost to
build the new airport will be about $4.9 billion, of which the Federal
Aviation Administration (
FAA) has committed $685 million from the Airport
and Airway Trust Fund. Most of the money needed to build the airport has
come from revenue bonds issued by the Denver Airport System.
2
(See sec.
1 for details on the total cost of the airport and sec. 2 for a breakdown of
federal funds.)
1
We addressed other issues relating to the new airport in two prior reports: New Denver Airport:
Safety, Construction, Capacity, and Financing Considerations (GAO/RCED-91-240, Sept. 17, 1991) and
New Denver Airport Followup (GAO/RCED-92-285R, Sept. 14, 1992).
2
Denver Airport System is headed by the Manager of the Department of Aviation, who reports directly
to the Mayor of the City of Denver.
GAO/RCED-95-35BR New Denver AirportPage 1
B-258641
Because the airport is so large, airport planners decided that a
state-of-the-art automated baggage handling system, capable of moving
bags much more quickly than conventional tug-and-cart/conveyor belt
systems, would be needed. BAE Automated Systems Incorporated was
awarded a $193 million contract to design, build, and test an automated
baggage handling system. This system was designed to move baggage from
the check-in areas to the aircraft within 20 minutes. However, the baggage
handling system installed at the new airport has had many problems and
does not yet work satisfactorily. Originally, the airport was scheduled to
open in October 1993, but problems with the baggage handling system
have caused several postponements.
Results in Brief
The automated baggage handling system has had serious mechanical and
software problems and has yet to successfully pass the tests necessary for
it to be certified operational. In previous tests of the system, bags were
misloaded, were misrouted, or fell out of telecarts, causing the system to
jam. BAE is modifying the automated system to correct these problems.
However, the airport is installing an alternative, conventional baggage
handling system using conveyor belts, tugs, and carts that will be used at
the airport at least until the automated system is operating. The alternative
system is estimated to cost about $51 million.
Although Denver airport officials believe that this alternative system can
be completed in time to allow the airport to open by February 28, 1995, the
airport cannot open until an operating baggage system has been
successfully tested. In addition, the contractor responsible for the
conventional system has only recently started to make the structural
modifications necessary to operate the system. Airport officials hope that
Concourse B, serving United, will have the automated system operating at
the targeted opening date. If the automated system is not yet operational,
United will also be served by the conventional system. Whether the
automated system will eventually serve all areas of the airport or whether
some parts will continue to be served by the conventional system is yet to
be resolved.
The airport was originally scheduled to open in October 1993; however,
debt service did not begin until January 1, 1994. Up to that date, revenues
from Stapleton were sufficient to cover the operating costs at Stapleton as
well as the costs associated with the new airport. After January 1, 1994,
the costs of operating both airports, combined with the debt service
requirements, exceeded the revenues generated by Stapleton. The deficit
GAO/RCED-95-35BR New Denver AirportPage 2
B-258641
currently is between $18 million and $19 million each month. If all the
costs of delay are counted, including foregone net income, the total cost of
the delay will be about $360 million if the airport opens at the end of
February 1995.
The airport should be able to meet its financial obligations once it opens if
current traffic forecasts are realized and if cost estimates are correct.
Traffic projections are based on current levels at Stapleton, which has
about 16 million enplanements annually, and are expected to increase to
18.3 million in 2000. The agreement between the airport and the airlines
limits the amount that the airlines pay in user fees to $20 per enplaned
passenger (in 1990 dollars). These user fees are calculated after all other
revenues are applied to cover operating costs and debt service. If current
traffic, revenue, and cost projections are accurate, the airlines’ user fees
should be several dollars under the cap.
The accuracy of the Denver Airport System’s forecasts depends on several
assumptions: (1) savings from bond refinancing, (2) Continental Airlines’
revenues at projected levels, (3)
FAA discretionary funds’ being awarded,
and (4) an operational baggage system in place.
Problems With the
Baggage Handling
System Have Delayed
the Opening of the
New Airport
Significant mechanical and software problems have plagued the
automated baggage handling system. Denver airport officials are still
uncertain of how long it will take to correct all the problems. In a recent
report, BAE listed 72 tasks that must be completed before the system is
ready for testing. Then, the baggage system will be put through a series of
tests before it is certified as operational. It is possible that these tests
could reveal additional problems.
To open the airport by the end of February 1995, Denver has decided to
install a conventional baggage system to serve as an alternative to the
automated system. The alternative system, using conveyors, tugs, and
carts, will handle baggage between the terminal and all three concourses
until the automated system is operating properly. The automated system
will be operating first at Concourse B, which will serve United, and within
6 months at Concourse A, which will serve Continental and international
carriers. When the system for Concourse A becomes operational, airport
system officials will decide whether Concourse C will receive the
automated system or whether airlines on that concourse will continue to
use the conventional system. The alternative system is scheduled to be
ready by January 1995.
GAO/RCED-95-35BR New Denver AirportPage 3
B-258641
In addition to developing the alternative system, Denver has negotiated
with BAE to make substantial modifications to the automated system.
These modifications include changing the routing of the telecarts so that
more of them serve United at Concourse B. As part of this agreement,
United will contract directly with BAE for these modifications. On
September 29, 1994, BAE, United, and the City reached agreement on the
modifications to be made to the automated system. The estimated cost to
Denver for the modifications is about $35 million.
Excessive time to move baggage can affect the efficiency of an airline’s
operations by creating scheduling problems and disrupting the efficient
use of its aircraft fleet. The original automated baggage system was
designed to deliver bags from the terminal to the aircraft within 20
minutes. Recent Denver Airport System studies indicate that transit times
will only be moderately longer with the alternative system—up to 5
minutes longer. The airlines have challenged this estimate as being overly
optimistic. United believes it could take up to 50 minutes for baggage to
reach the most remote gates on Concourse B. Airlines on Concourse C
claim that transit times to and from Concourse C will be 27 to 31 minutes.
Transit times for the modified automated system are not yet available.
(See sec. 3 for more detailed information on the automated and alternative
baggage systems.)
The Delayed Opening
Has Caused Sizeable
Increases in Total
Costs of the New
Airport
The Denver Airport System began to experience operating deficits after
January 1, 1994, when debt payments began. By the end of February 1995,
the operating deficit will total about $230 million. The Denver Airport
System has used the 1993 operating surplus from Stapleton, contributions
from the airlines, bond proceeds, and other moneys set aside in various
reserve accounts to cover the deficit. As of September 1, 1994, the Denver
Airport System had about $467 million available—including proceeds from
its recent bond issue—to cover the airport system’s future deficits.
However, according to bond analysts to whom we spoke, not all of these
funds, especially those in the bond reserve fund, could be committed to
debt coverage without compromising the new airport’s credit rating.
Precisely how much could be spent from these funds before the credit
rating could be affected is not known.
Operating deficits are only part of the cost of the delayed opening. The
total cost of the delays to the airport and the airlines might reach
$360 million by February 1995. In addition to the deficit, other costs are
$37 million in lost income that the new airport would have generated if it
GAO/RCED-95-35BR New Denver AirportPage 4
B-258641
opened on January 1, 1994, $86 million for the alternative baggage system
and the modifications to the automated system, and $8 million in fees
associated with issuing the additional bonds. (See sec. 4 for additional
details on the costs of the delay and available revenues.)
The New Airport’s
Ability to Meet
Operating and Debt
Service Costs Is
Linked to Current
Traffic Projections
To evaluate whether the current delays and added costs would materially
affect the airport’s ability to meet operating and debt service costs when it
opens, we reviewed current projections of the airport’s traffic, revenues,
and costs. A simulation model, developed by Hickling Corporation,
3
was
employed to identify how different traffic forecasts affected the airport’s
financial situation. The model included recent information on the traffic
forecasts, project costs, financing plan, and financial statements for the
airport.
Air traffic at Denver has recovered from the depressed level of 13.7 million
enplanements in 1989. Traffic at Stapleton has grown to 16.3 million
enplanements in 1993. The 1993 traffic level was used as a base for
projecting future airport revenues in the most recent bond prospectus, and
traffic was projected to increase to 18.3 million in 2000. If these forecasts
materialize, the new airport should produce sufficient revenues to cover
expenses and service the debt. Projected traffic would have to be
20-25 percent lower than what is now forecast for the airport to
experience a high probability of sustained revenue shortfalls.
The new airport will be a relatively expensive facility, as airline user fees
will be about 3 times higher than those at Stapleton. The agreement
between the airport and the airlines limits the amount that the airlines will
pay in user fees to $20 per enplaned passenger (in 1990 dollars). These
user fees are calculated after all other revenues are applied to cover
operating costs and debt service. If traffic, revenue, and cost estimates are
accurate, airlines’ user fees should be below the cap—about $14.50 in 1990
dollars.
4
(See sec. 5 for more information on the financial outlook of the
new airport.)
3
Hickling Corporation, a consulting firm that specializes in risk assessment for airport investment
projects, assisted us in our evaluation. Hickling also provided assistance during our 1991 review of the
Denver airport project. Hickling has developed a risk analysis model applicable to a wide range of
subjects; the model has been used for airport infrastructure projects in Minneapolis/St. Paul, Minn.,
and in Vancouver and Toronto, Canada.
4
Because the cap is in 1990 dollars it rises over time. The cap in current 1994 dollars is about $22.50
and actual fees per enplanement are estimated to be $17-$18.
GAO/RCED-95-35BR New Denver AirportPage 5
B-258641
The accuracy of the Denver Airport System’s revenue and cost projections
is dependent on several important assumptions: (1) that $121 million will
be saved from 1995 through 1999 by restructuring and refinancing 1984/85
bonds, (2) that Continental Airlines will provide $273 million from 1995
through 1999 for use of the airport, (3) that the airport will receive
$95 million from 1995 through 1998 in discretionary funds from
FAA’s letter
of intent, and (4) that the airport will achieve an operational baggage
system.
We performed our review between May 1994 and September 1994 in
accordance with generally accepted government auditing standards.
Because the analyses presented in this report are based on traffic,
revenue, and cost forecasts that depend on key assumptions, caution must
be used in arriving at conclusions regarding the experience of the airport
in the first few years of operation. The extent to which these assumptions
materialize will be important ingredients in the near-term financial
experience of the new airport. The details of our scope and methodology
are contained in appendix I.
At the end of our field work, we discussed the facts contained in this
briefing report with senior officials from the Department of
Transportation, including the Department’s General Counsel, and the City
of Denver, including the City’s Director of Public Works and the Denver
Airport System Finance Director. They generally agreed with the
information presented, and we have incorporated their comments as
appropriate.
Unless you publicly release its contents earlier, we plan no further
distribution of this briefing report until 3 days from the date of this letter.
At that time, we will send copies of this briefing report to the Secretary of
Transportation; the Director, Office of Management and Budget; the City
of Denver; and interested congressional committees. We will also make
copies available to others on request.
GAO/RCED-95-35BR New Denver AirportPage 6
B-258641
Please contact me at (202) 512-2834 if you or your staff have any questions
concerning this briefing report. Major contributors to this briefing report
are listed in appendix II.
Sincerely yours,
Kenneth M. Mead
Director, Transportation Issues
GAO/RCED-95-35BR New Denver AirportPage 7
Contents
Letter
1
Section 1
Total Cost of Denver
International Airport
10
Section 2
Federal Funds for DIA
12
Section 3
DIAs Automated
Baggage Handling
System
14
Problems With DIA’s Automated Baggage Handling System 17
Modifications to DIA’s Baggage Handling System 18
Remaining Uncertainties 21
Section 4
Cost of DIAs Delayed
Opening
22
Cumulative Deficit Through February 28, 1995 23
Actual Deficit of the Denver Airport System—January 1, 1994,
Through June 30, 1994
25
Sources of Funds Used to Cover $80.08 Million Deficit—
January 1, 1994, Through June 30, 1994
27
Projected Deficit of the Denver Airport System—July 1, 1994,
Through February 28, 1995
29
Funds Available to Finance Future Delay Costs 30
Application of Proceeds of the Series 1994A Bonds 33
Forecast of Cumulative Operating Deficits 35
Summary of Total Delay Costs 37
Section 5
Impact of Delayed
Opening on DIAs
Ability to Meet
Operating and Debt
Service Costs
38
Passenger Traffic Volume 39
Annual Enplanements at DIA Between 1994 and 2000 Under Low,
Median, and High Traffic Forecasts
41
Mean Cost per Enplaned Passenger for Two Opening Dates 43
Reduced DIA Enplanement Estimates to Levels Where There
Would Be a Significant Risk of Costs Exceeding Revenues
47
GAO/RCED-95-35BR New Denver AirportPage 8
Contents
Appendixes
Appendix I: Objectives, Scope, and Methodology 48
Appendix II: Major Contributors to This Briefing Report 51
Tables
Table 1.1: Cost of Denver International Airport 10
Table 2.1: Summary of Federal Funds for DIA 12
Table 4.1: Actual Deficit of the Denver Airport
System—January 1, 1994, Through June 30, 1994
24
Table 4.2: Projected Deficit of the Denver Airport System—July 1,
1994, Through February 28, 1995
28
Table 4.3: Reserve Funds in the Denver Airport System and
Amounts Available to Cover Future Delay Costs
31
Table 4.4: Application of Proceeds of the Series 1994A Bonds 32
Table 4.5: Comparison of Budgets for the January 1, 1994, to
February 28, 1995, Period for Two DIA Opening Dates
37
Table 5.1: Annual Enplanements at DIA Between 1994 and 2000
Under Low, Median, and High Traffic Forecasts
40
Table 5.2: Mean Cost per Enplaned Passenger if DIA Opens by
March 1, 1995
42
Table 5.3: Mean Cost per Enplaned Passenger if DIA Opens by
July 1, 1996
42
Table 5.4: Reduced DIA Enplanement Estimates to Levels Where
There Would Be a Significant Risk of Costs Exceeding Revenues
46
Abbreviations
AIP Airport Improvement Program
DIA Denver International Airport
FAA Federal Aviation Administration
F&E facilities and equipment
O&M operations and maintenance
PFC passenger facility charge
RAP risk analysis process
SIA Stapleton International Airport
GAO/RCED-95-35BR New Denver AirportPage 9
Section 1
Total Cost of Denver International Airport
Table 1.1: Cost of Denver International
Airport
Dollars in millions
Cost category Cost
Costs to Denver Airport System
Airport planning, land, and construction $3,214
Capitalized interest 919
Bond discounts and issuance expense 136
Total costs to Denver Airport System 4,269
Costs to others
FAA facilities 224
United Airline’s special facilities 261
Continental Airline’s special facilities 73
Rental car facilities 66
Total costs to others 624
Grand total costs of Denver International Airport $4,893
Legend
FAA = Federal Aviation Administration.
GAO/RCED-95-35BR New Denver AirportPage 10
Section 1
Total Cost of Denver International Airport
If Denver International Airport (DIA) opens by February 28, 1995, we
estimate that the costs of the airport, including facilities funded by
airlines, rental car companies, and
FAA will be about $4.9 billion. Of this
amount, the Denver Airport System (airport system) has funded $4.269
billion, including capitalized interest and Airport Improvement Program
(
AIP) grants. Details on AIP grants and FAA facilities and equipment funds
are in table 2.1, page 12.
FAA, the airlines, and rental car companies have
contributed another $624 million for their facilities.
The total cost encompasses all projects approved as of September 1, 1994.
It excludes costs for a sixth runway, which has not yet been authorized,
and other potential costs or recoveries arising from future legal
settlements between the airport system and its contractors. Since
September 1, 1994, Denver has agreed to build an alternative baggage
system estimated to cost $51 million and has agreed to further
modifications to the automated baggage system, which will cost an
estimated $35 million.
GAO/RCED-95-35BR New Denver AirportPage 11
Section 2
Federal Funds for DIA
Table 2.1: Summary of Federal Funds
for DIA
Airport Improvement Program funds
Dollars in millions
Fiscal
year
Entitlement
funds
Discretionary
funds Total
Facilities
and
equipment
funds Total
1988 $ 0.2 $ 0 $ 0.2 $ 0 $ 0.2
1989 34.2 25.8 60.0 4.2 64.2
1990 31.0 59.0 90.0 39.2 129.2
1991 0 25.0 25.0 60.0 85.0
1992 2.2 42.3 44.5 41.7 86.2
1993 5.9 42.0 47.9 24.0 71.9
1994 2.9 32.0 34.9 1.2 36.1
1995 6.0 31.0 37.0 0 37.0
1996 6.0 25.0 31.0 12.4 43.4
1997 6.0 25.0 31.0 19.2 50.2
1998 6.0 25.0 31.0 18.0 49.0
1999 6.0 22.9 28.9 1.3 30.2
2000 0 0 0 2.4 2.4
Total $106.4 $355.0 $461.4 $223.6 $685.0
In 1988, the federal government began funding DIA through the Airport and
Airway Trust Fund. As of September 1, 1994,
FAA planned to spend
$685 million from the Trust Fund; $472.8 million has already been
transferred to
DIA. Moneys for DIA have come from two major Trust Fund
accounts—the Airport Improvement Program (
AIP) and Facilities and
Equipment (
F&E).
GAO/RCED-95-35BR New Denver AirportPage 12
Section 2
Federal Funds for DIA
The majority of the federal funding, $461.4 million, for DIA comes from the
AIP. Not all of this amount has been transferred to DIA. As of September 1,
1994, about $302.5 million had been transferred—$132.1 million under a
letter of intent and $170.4 million in other
AIP grants.
1
The remainder will
be distributed by the end of 1999. The
AIP moneys have been used at DIA for
such things as land acquisition, the construction of runways, taxiways, and
aprons, and installation of a rail passenger transportation system. Federal
funds will not be used to fund the automated baggage system. In 1990,
FAA
gave DIA a letter of intent for $351 million;
2
however, this was significantly
reduced because the airport system imposed a passenger facility charge in
January 1992. By law, a portion of certain
AIP moneys must be turned back
if airports impose a passenger facility charge.
In addition to the
AIP moneys received under the letter of intent, DIA
received $170.4 million in other AIP moneys. Most of this
amount—$150.2 million—was granted prior to the 1990 letter of intent. In
fiscal years 1992 and 1993,
DIA also received separate AIP grants (not under
the letter of intent) totaling $20.2 million to procure incursion lighting,
conduct a light rail study, and begin work on a sixth runway.
DIA expects
to receive an additional $50 million in
AIP funds to complete the sixth
runway. An
FAA official told us, however, that FAA has not yet formally
committed this amount. On September 22, 1994, congressional
appropriators approved an amendment to the 1995 Department of
Transportation Appropriations bill to prohibit the planning, engineering,
design, and construction of a sixth runway at
DIA unless the runway is
needed to improve safety or performance.
DIA will receive about $223.6 million of F&E moneys through 2000. Since
1989, the Congress has appropriated $170.3 million in
F&E funds for DIA.
3
This money has been used for new air traffic control facilities; equipment
such as an airport surveillance radar system, instrument landing systems,
approach lights, weather sensors, and navigational aids; and transition
operations from Stapleton International Airport (
SIA) to DIA.
1
A letter of intent is a mechanism used to support projects at primary and reliever airports that will
significantly enhance systemwide airport capacity. Typically, letters of intent allow airports to begin
project development sooner and receive multiyear funding.
2
These funds are not guaranteed. They must be appropriated each year.
3
The congressional appropriation was $170.3 million; however, FAA has reprogrammed about
$2 million to other projects.
GAO/RCED-95-35BR New Denver AirportPage 13
Section 3
DIAs Automated Baggage Handling System
GAO/RCED-95-35BR New Denver AirportPage 14
Section 3
DIA’s Automated Baggage Handling System
The automated baggage handling system, with a contract price of
$193 million, will be one of the largest and most sophisticated systems of
its type in the world. It was designed to provide the high-speed transfer of
baggage to and from aircraft, thereby facilitating quick turnaround times
for aircraft and improved services to passengers. Baggage will travel
between the terminal and concourses through interconnecting tunnels.
The most distant concourse is located about a mile from the terminal.
Even after modifications are complete, the automated baggage handling
system will have two main components: (1) high-speed, bag-carrying
telecarts mounted on tracks and (2) connecting conveyor belts to load and
off-load baggage. The tracks are suspended from the basement ceilings of
the terminal and concourses. Electric motors and synchronous drives
move the telecarts along the tracks at varying speeds. Photocells and radio
frequency reading devices direct each telecart to the right location. In
total, the original system included over 17 miles of track; 5.5 miles of
conveyors; 4,000 telecarts; 5,000 electric motors; 2,700 photocells; 59 laser
bar code reader arrays; 311 radio frequency readers; and over 150
computers, workstations, and communication servers. The automated
system was originally designed to carry up to 70 bags per minute to and
from the baggage check-in and baggage claim areas at speeds of up to 24
miles per hour. This would allow the airlines to receive checked baggage
at their aircraft within 20 minutes.
GAO/RCED-95-35BR New Denver AirportPage 15
Section 3
DIA’s Automated Baggage Handling System
Problems with DIA’s Automated
Baggage Handling System
Baggage jams undetected
Double loading of telecarts
Conveyor belts not synchronized
with telecarts
Telecarts lock together when they
collide
Empty car management
GAO/RCED-95-35BR New Denver AirportPage 16
Section 3
DIA’s Automated Baggage Handling System
Problems With DIAs
Automated Baggage
Handling System
Significant mechanical and software problems have plagued the
automated baggage handling system. In tests of the system, bags were
misloaded, were misrouted, or fell out of telecarts, causing the system to
jam. Video cameras were installed at several known trouble spots to
document problems, such as the following:
The baggage system continued to unload bags even though they were
jammed on the conveyor belt. This problem occurred because the photo
eye at this location could not detect the pile of bags on the belt and hence
could not signal the system to stop.
The baggage system loaded bags into telecarts that were already full.
Hence, some bags fell onto the tracks, again causing the telecarts to jam.
This problem occurred because the system had lost track of which
telecarts were loaded or unloaded during a previous jam. When the system
came back on-line, it failed to show that the telecarts were loaded.
The timing between the conveyor belts and the moving telecarts was not
properly synchronized, causing bags to fall between the conveyor belt and
the telecarts. The bags became wedged under the telecarts. This occurred
because telecarts were bumping into each other near the load point.
Although the contractor—BAE Automated Systems
Incorporated—believes that these problems have been resolved, other
problems remain. To resolve these problems and make the system
operational, a number of critical tasks must be completed. A recent BAE
system status report listed 72 hardware, software, and testing activities
that must be completed, such as the following:
The telecarts’ front bumpers have to be replaced so that they will not slip
under the back bumpers when telecarts collide. These collisions have
caused telecarts to lock together.
Additional track, synchronous drives, and related software changes must
be installed to improve “empty car management,” that is, allocating the
correct number of telecarts to specific locations at appropriate times.
BAE and City of Denver officials recognize that the system’s testing might
uncover additional problems.
GAO/RCED-95-35BR New Denver AirportPage 17
Section 3
DIA’s Automated Baggage Handling System
Modifications to DIA’s Baggage
Handling System
Build an Alternative System
Conventional system
Could serve all concourses
Estimated costs—$51 million
Changes to Automated System
United Airlines may oversee
Phased in service to concourses
Estimated costs—$35 million
Modifications to DIAs
Baggage Handling
System
Because of continuing problems with the automated system, the City
decided to build an alternative (i.e., conventional) baggage handling
system and make substantial modifications to the automated system. The
alternative system will use conveyor belts, tugs, and carts to move bags to
and from the terminal and concourses. The alternative system will be the
primary system until the automated system comes on-line. Once the
automated system is operational, the alternative system will serve as a
backup system if the automated system malfunctions.
GAO/RCED-95-35BR New Denver AirportPage 18
Section 3
DIA’s Automated Baggage Handling System
With facility modifications and equipment, the alternative system is
currently projected to cost over $51 million, which includes the cost to
procure tugs and carts. The system is scheduled to be completed by
January 15, 1995, and testing completed about February 15, 1995.
To build the alternative system, major modifications to the physical
structures must be made. Five areas of the third floor parking garage will
be enclosed and converted into staging areas for airlines’ baggage. The
terminal building will be modified by the cutting of holes in walls at the
third level to allow conveyor belts to enter from ticket counters and from
curbside check-in to the staging areas.
Extensive use of tugs and carts to transport bags will be necessary. Tugs
and carts will move bags from the terminal through existing tunnels to the
concourses. To do this, the ventilation systems in tunnels will have to be
modified to keep the level of exhaust fumes from the tugs at acceptable
levels. The City plans to purchase tugs powered by natural gas to minimize
exhaust emissions. Inbound baggage will be transported from the aircraft
on carts to the terminal basement, where they will be loaded onto
conveyors leading up to the baggage claim area. Bags for passengers on
connecting flights will be transferred between aircraft on carts operating
via the tarmac.
The automated system also will undergo substantial modifications. The
City and United entered into an agreement that allows United to contract
directly with BAE to modify portions of the automated system to provide a
separate outbound automated baggage system for United by February 28,
1995. These modifications include changing the routing of the telecarts so
that more of them serve United at Concourse B. The inbound portions will
not be completed until later. The agreement also includes a requirement
for BAE to complete an automated baggage system for Concourse A by
August 31, 1995. The City will evaluate the need for an automated system
for Concourse C carriers within 6 months after the airport opens.
On September 29, 1994, BAE, United, and the City reached agreement on
the modifications to be made to the automated baggage handling system.
These modifications are estimated to cost the City about $35 million. BAE
will be paid $17.5 million on February 28, 1995, assuming that the system is
operational, and the remainder after the system is substantially completed.
If the automated system is not operational by opening day, United will be
served by the conventional baggage system.
GAO/RCED-95-35BR New Denver AirportPage 19
Section 3
DIA’s Automated Baggage Handling System
Remaining Uncertainties
Timing
Performance
Final System Configuration
Resource Requirements
Unresolved Claims
GAO/RCED-95-35BR New Denver AirportPage 20
Section 3
DIA’s Automated Baggage Handling System
Remaining
Uncertainties
A number of outstanding, unanswered questions surround the baggage
handling system. Among the remaining uncertainties are the following:
Timing. The automated system is undergoing modifications, and
construction of the alternative system is just getting under way. Both
systems must still be tested before the airport can open. Prior tests have
not gone well.
Performance. The original automated system was designed to transport
outbound baggage from the terminal to the aircraft within 20 minutes. It is
not yet known whether the modified automated system will meet design
standards. The City estimates that bags can be delivered using the
alternative system in 20 to 25 minutes. United and carriers on Concourse C
have expressed concern about whether the conventional system can
deliver bags in the times estimated by the airport system. United believes
that using the alternative system may take up to 50 minutes to deliver bags
to aircraft at
DIA’s most remote gates. Airlines at Concourse C believe that
it will take 27 to 31 minutes to deliver bags using this system.
Final system configuration. It has not been decided whether Concourse C
will eventually be reconnected to the automated system. This could result
in lower levels of baggage service to airlines and their passengers on
Concourse C.
Resource requirements. The conventional system is much more
labor-intensive than the automated system. United told us that it currently
has about 1,100 employees working the baggage system at
SIA; an
additional 600 people would be needed to handle baggage using
DIA’s
alternative system. The usefulness of the conventional tug-and-cart
operation as a backup system after the automated system becomes
operational is also in question because of the additional standby
employees required.
Unresolved claims. The final cost of the baggage system is uncertain
because of the potential for litigation after the baggage system is
completed. The City has not paid BAE $22 million of the $193 million
contract for the automated baggage system. On September 29, 1994, BAE,
United, and the City reached an agreement for modifying the automated
baggage system. The agreement calls for the City to pay BAE
$17.75 million of the unpaid $22 million but reserves the rights of both
parties to assert claims for alleged damages. They agreed to attempt to
resolve their claims through mediation, but if unsuccessful, they agreed to
file any unresolved claims in court.
GAO/RCED-95-35BR New Denver AirportPage 21
Section 4
Cost of DIAs Delayed Opening
Cumulative Deficit Through
February 28, 1995
Total Deficit $230
(in Millions)
Actual 80
(1/94-6/94)
Projected 150
(7/94-2/95)
GAO/RCED-95-35BR New Denver AirportPage 22
Section 4
Cost of DIA’s Delayed Opening
Cumulative Deficit
Through February 28,
1995
On the basis of current monthly deficits, the total operating deficit
incurred by the airport system from January 1, 1994, through February 28,
1995, will be $230 million. Financial data are available through June 30,
1994. For the period after July 1, 1994, the deficits must be estimated. Our
projection of the total deficit included the $80 million through June 30,
1994, and the projected deficit of $150 million for the period July 1, 1994,
through February 28, 1995.
GAO/RCED-95-35BR New Denver AirportPage 23
Section 4
Cost of DIA’s Delayed Opening
Table 4.1: Actual Deficit of the Denver
Airport System—January 1, 1994,
Through June 30, 1994
Dollars in millions
Deficit
Revenue and cost
breakdown
Revenue
and cost
Operating revenues generated at SIA
Landing fees $ 23.64
Terminal complex rentals 22.33
Concessions 24.24
Aviation fuel taxes 6.06
Other 2.66
Total SIA operating revenues 78.93
Less: SIA’s operating costs
Personnel & professional svcs. 16.28
Cleaning & utilities 9.62
Maintenance, supplies, materials 6.70
Other 3.42
Total SIA operating costs 36.02
SIA’s operating surplus 42.91
Less: SIA’s net debt service 17.19
Surplus produced by SIA 25.72
DIA’s costs
Operating costs
Personnel & professional svcs. 10.86
Cleaning & utilites 6.41
Maintenance, supplies, materials 4.47
Baggage system maintenance 1.83
Other 2.28
Total DIA operating costs 25.85
Debt service requirements on bonds 122.35
Less: passenger facility charges (20.89)
Interest income (16.51)
Continental’s payments (5.00)
Net debt service costs 79.95
Total DIA costs 105.80
Net deficit 80.08
Average monthly deficit, Jan. through June 1994 $ 13.35
GAO/RCED-95-35BR New Denver AirportPage 24
Section 4
Cost of DIA’s Delayed Opening
Actual Deficit of the
Denver Airport
System—January 1,
1994, Through June
30, 1994
The airport system incurred a net operating deficit of $80.08 million from
January 1, 1994, through June 30, 1994—an average of $13.35 million each
month. This deficit occurred because the revenues generated by
SIA did
not cover the debt servicing requirements and operations and maintenance
(
O&M) costs at both airports. For this same period, DIA officials had earlier
estimated a net monthly deficit of $16.4 million; however, they took a
conservative approach that led to the understating of
SIA revenues and the
overstating of operations costs at the two airports. Our calculations were
based on actual monthly deficits. There was no deficit prior to January 1,
1994.
The following were key elements of our calculations:
Operating costs at SIA and DIA are based on total obligations recorded in
the airport system’s accounting records for January 1 through June 30,
1994. The airport system’s accountants allocated costs between the two
airports according to which airport benefitted from the expenditure of
those funds.
Passenger facility charges (PFC) are generated from a special $3 fee that
was added to the price of a ticket for each enplaned passenger at Denver
airport starting in July 1, 1992. The airport system’s bond ordinance
requires that
PFCs be used to pay debt service requirements.
Interest income is generated from several investment pools managed by
the airport system, principally the bond reserve fund.
Depreciation was excluded as a cost category because SIA will not be an
airport after
DIA opens, and depreciation is an expense requiring no cash
outlay.
GAO/RCED-95-35BR New Denver AirportPage 25
Section 4
Cost of DIA’s Delayed Opening
Sources of Funds Used to
Cover $80.08 Million Deficit
39% •
Airlines
$31.0 Million
32%
Aviation Fuel Tax
$25.92 Million
8%
Surplus Bond Reserves
$6.45 Million
6%
1993 Operating Surplus
$4.75 Million
15%
Capitalized Interest
$11.96 Million
GAO/RCED-95-35BR New Denver AirportPage 26
Section 4
Cost of DIA’s Delayed Opening
Sources of Funds
Used to Cover $80.08
Million Deficit—
January 1, 1994,
Through June 30, 1994
The airport system used funds from five sources to cover the
$80.08 million operating deficit for the first 6 months of 1994, as follows:
Payments from airlines
. During the 6-month period, United and
Continental airlines paid $36.53 million to the airport system to cover
delay costs. The airport system applied $31 million of this amount against
the $80.08 million deficit. United’s $23.9 million contribution came from
special facility bond funds that remained from a construction project for
its maintenance hangar at
DIA. The airport system’s agreement with United
stipulated that these funds would be used to offset facility upgrades to
Concourse B requested by United.
In April and May 1994, both United and Continental paid $6.63 million and
$6 million, respectively, to help offset delay costs from March 9 to May 15,
1994. United also agreed to pay an additional $9.9 million and Continental
an additional $1.4 million before December 31, 1994. The airport system
does not plan to compensate the airlines for these payments.
Aviation fuel tax fund
. On January 1, 1994, the airport system had about
$36.6 million in the aviation fuel tax fund, a special purpose fund
established to retire
SIA’s portion of 1984 and 1985 revenue bonds. The
airport system used $25.92 million from this fund to cover the net
operating deficit; $10.8 million from the proceeds of the 1994A bond issue
has been transferred back into this fund.
Capitalized interest
. Capitalized interest is money from the original bond
proceeds set aside to pay debt service payments during the airport’s
construction period; $11.96 million was used to cover part of the deficit.
Surplus in bond reserve fund
. Under the bond ordinance, the airport
system is required to set aside enough money in a bond reserve fund to
pay debt service requirements for a full year. The funding requirement for
Denver’s bond reserve fund was $304.63 million, excluding the 1994A
bonds. On January 1, 1994, the airport system had $315.11 million in the
fund, leaving a surplus of about $10.5 million; $6.45 million of this surplus
was used to cover the deficit.
Operating surplus from 1993
SIA operations. Net revenues from operations
at
SIA are held in an operating fund, which had a balance of $7.65 million
on January 1, 1994. During the first 6 months of 1994, $4.75 million was
used to cover the deficit.
GAO/RCED-95-35BR New Denver AirportPage 27
Section 4
Cost of DIA’s Delayed Opening
Table 4.2: Projected Deficit of the
Denver Airport System—July 1, 1994,
Through February 28, 1995
Dollars in millions
Deficit
Revenue and cost
breakdown
Revenue
and cost
Operating revenues generated at SIA
Landing fees $31.0
Terminal complex rentals 29.0
Concessions 32.0
Aviation fuel taxes 8.0
Other 4.0
Total operating revenues 104.0
Less: SIA’s operating costs
Personnel & professional svcs. 26.2
Cleaning & utilities 15.5
Maintenance, supplies, materials 10.8
Other 5.5
Total operating costs 58.0
SIA’s operating surplus 46.0
Less: SIA’s debt service 23.0
Surplus produced by SIA 23.0
DIA’s costs
Operating costs
Personnel & professional svcs. 17.6
Cleaning & utilities 10.4
Maintenance, supplies, materials 7.3
Other 3.7
Total operating costs 39.0
Debt service requirements on bonds 182.0
Less
Passenger facility charges (27.0)
Interest income (17.0)
Continental’s payments (4.0)
Net debt service costs 134.0
Total DIA costs 173.0
Net deficit 150.0
Average monthly deficit, July 1994 through Feb. 1995 18.75
GAO/RCED-95-35BR New Denver AirportPage 28
Section 4
Cost of DIA’s Delayed Opening
Projected Deficit of
the Denver Airport
System—July 1, 1994,
Through February 28,
1995
We estimate that the net deficit projected from July 1, 1994, through
February 28, 1995, will be about $150 million—an average of $18.75 million
each month. The monthly deficit increased from $13.35 million for the first
6 months of 1994 because of increased
O&M costs and debt service
requirements from the $257 million 1994A bond issue.
The following were key elements of our calculations:
We assumed that the pattern of revenues for 1994 will follow the pattern of
revenues experienced in 1993, when the revenues were split evenly
between the first and second halves of the year. Total revenues at
SIA for
the first half of 1994 were $78.9 million, or just over $13 million a month.
Operating costs at SIA and DIA are based on recently completed budgets for
the airport system, which estimated monthly operating costs of
$12.1 million at both airports for the last half of 1994.
The debt service requirement on the 1994A bond issue has increased by
about $2 million a month.
GAO/RCED-95-35BR New Denver AirportPage 29
Section 4
Cost of DIA’s Delayed Opening
Funds Available to Finance
Future Delay Costs
45% •
Bond Reserve Fund
$209 Million
26%
New 1994A Bond Issue
$119.6 Million
27%
Capital Fund
$128.2 Million
2%
United’s Delay Cost
$9.9 Million
Funds Available to
Finance Future Delay
Costs
The airport system has $467.2 million available to cover further delay costs
to
DIA.
GAO/RCED-95-35BR New Denver AirportPage 30
Section 4
Cost of DIA’s Delayed Opening
Table 4.3: Reserve Funds in the
Denver Airport System and Amounts
Available to Cover Future Delay Costs
Dollars in millions
Source Total amount Available
Bond reserve fund $308.6 $209.5
New 1994A bond issue 192.6
a
119.6
Capital fund 167.7 128.2
United’s delay cost payments 9.9 9.9
Total $678.8 $467.2
a
The total amount shown for the new bond issue excludes $64.4 million transferred to the capital
fund.
Bond Reserve Fund
The bond reserve requirement for DIA is now $308.6 million. Under the
terms of the bond ordinance, funds can be withdrawn from this account
only if they are needed to meet debt service requirements. Funds
withdrawn must be paid back at the rate of 1/60th of the amounts owed
each month. Given this requirement, $209.5 million of the $308.6 million
could be used before outside sources would have to be tapped. However,
according to bond analysts to whom we spoke, drawing on these
resources before
DIA opens could affect the airport’s credit standing.
Capital Fund
All of the airport system’s surpluses are paid into a capital fund after O&M
costs, debt service requirements, and O&M reserve account requirements
are made. The capital fund can be used to pay capital costs, extraordinary
costs, or bond requirements. The projected balance in the capital fund as
of December 31, 1994, was $167.7 million, of which $128.2 million is
available.
Monthly Payments on
Delay Costs by United
Airlines
In accordance with an earlier agreement with the airport system, United
will make monthly payments of $1.7 million during the last half of 1994,
which cumulatively totals $9.9 million. This amount will cover United’s
share of the airport system’s delay costs for the period March 9 through
May 15, 1994.
GAO/RCED-95-35BR New Denver AirportPage 31
Section 4
Cost of DIA’s Delayed Opening
Table 4.4: Application of Proceeds of
the Series 1994A Bonds
Dollars in millions
Application Proceeds
Available for funding delay costs $119.6
Fund costs of alternative baggage system 50.6
Transfer to capital and project funds 64.4
Transfer to aviation fuel tax fund 10.8
Transfer to bond reserve fund 3.3
Underwriters’ discount and cost of issuance 4.4
Original issue discount 3.9
Total proceeds $257.0
GAO/RCED-95-35BR New Denver AirportPage 32
Section 4
Cost of DIA’s Delayed Opening
Application of
Proceeds of the Series
1994A Bonds
The airport system sold $257 million in airport system revenue
bonds—Series 1994A—with an effective date of August 30, 1994. The
airport system plans to apply these proceeds as follows:
$50.6 million to install an alternative baggage handling system.
$64.4 million for other capital projects, including funds to cover the costs
for modifications to the automated baggage system.
$10.8 million to partially replenish funds used to cover earlier deficits.
Airport officials told us that the $10.8 million will bring the total in this
fund to the amount needed to retire
SIA’s 1984 and 1985 revenue bonds.
$3.3 million to increase the bond reserve fund to its new minimum
requirement.
$4.4 million for costs associated with selling the bonds.
$3.9 million for the original issue discount on the bonds.
After satisfying these requirements, $119.6 million of the $257 million in
bond revenues will remain for future delay costs. The airport system
classifies this money as capitalized interest, which is money set aside to
pay debt service requirements before
DIA opens.
GAO/RCED-95-35BR New Denver AirportPage 33
Section 4
Cost of DIA’s Delayed Opening
Forecast of Cumulative Operating
Deficits
Dollars in Millions
0
50
100
150
200
250
300
350
400
2/28/95 7/1/95 9/30/95 12/31/95
Date of DIA Opening
230
305
360
415
2/28/95 is the latest announced DIA opening date.
GAO/RCED-95-35BR New Denver AirportPage 34
Section 4
Cost of DIA’s Delayed Opening
Forecast of
Cumulative Operating
Deficits
The deficit likely will continue to accumulate by $18 million to $19 million
each month if the opening of
DIA is delayed beyond February 1995. If DIA
does not open in 1995, the total deficit will grow to $415 million by
December 31, 1995. However, if the airport is not open by October 1995,
the City will need to tap the bond reserve fund to pay for the operating
deficit.
GAO/RCED-95-35BR New Denver AirportPage 35
Section 4
Cost of DIA’s Delayed Opening
Summary of Total Delay Costs
(in Millions)
Net Deficit $230
Opportunity Costs 37
Changes to Baggage
Systems 86
Fees From Bond
Issue 8
——
Total $361
GAO/RCED-95-35BR New Denver AirportPage 36
Section 4
Cost of DIA’s Delayed Opening
Summary of Total
Delay Costs
If DIA had opened by January 1, 1994, and operated in accordance with its
final 1994 budget, the airport system would have incurred a $37 million
surplus instead of a $230 million deficit through February 1995. (See table
4.5.) This means that the real costs from the delayed opening of
DIA will
total about $267 million by February 1995. In addition, the airport system
would not have had to incur $8.3 million for underwriting costs and issue
discounts from the 1994A bond issue. Furthermore, about $86 million for
modifications to the baggage handling systems would have been avoided.
Therefore, the true delay costs are about $361 million.
Table 4.5: Comparison of Budgets for
the January 1, 1994, to February 28,
1995, Period for Two DIA Opening
Dates
Dollars in millions
Revenues and costs to Denver Airport
System
Jan. 1, 1994,
opening date
Feb. 28, 1995,
opening date
Revenue from airlines
a
(landing fees and
terminal rent)
$ 313.2 $ 106.0
Other operating revenues (mostly
concessions)
92.8 62.9
Nonoperating revenues (PFCs, interest,
aviation fuel tax)
91.9 104.5
Total revenues 497.9 273.4
O&M cost
b
(171.3) (158.9)
Debt service cost (289.8) (344.5)
Net surplus (deficit)
c
$ 36.8 $(230.0)
a
Revenue from airlines, mainly through landing fees and rents, would increase substantially at DIA
compared with revenue from airlines at SIA.
b
O&M costs in DIA’s budget included about $6 million for the 14 months for residual operations at
SIA. Until disposal of SIA occurs, it will remain part of the airport system. The airport system’s
funds will be used to pay any costs at SIA, but those costs will not be included in airlines’ rates
and charges. Instead, SIA costs will be paid from DIA’s net revenues. After SIA closes, airport
system officials expect to spend about $25 million on capital projects through 1998 for
environmental cleanup, demolition of structures, and structural repairs. Airport system officials are
currently developing a master plan for the disposition of SIA and have begun a 5-year leasing
program for SIA facilities. Ultimately, airport system officials expect that the disposition of SIA will
produce $75 million in net proceeds.
c
Airlines receive 75 percent of net revenues produced from operations at DIA.
GAO/RCED-95-35BR New Denver AirportPage 37
Section 5
Impact of Delayed Opening on DIAs Ability
to Meet Operating and Debt Service Costs
Impact of Delayed Opening on DIA’s
Operating and Debt Costs
Traffic and Revenue Forecasts
Key Assumptions
Sensitivity Analysis
Airline Situation
Results From Risk Analysis
GAO/RCED-95-35BR New Denver AirportPage 38
Section 5
Impact of Delayed Opening on DIA’s Ability
to Meet Operating and Debt Service Costs
In September 1991, we reported on the likelihood that DIA would earn
sufficient revenues to cover its operating costs and meet obligations to
bondholders. We estimated the probabilities of various factors, such as
alternative traffic levels, and then calculated whether revenues would be
adequate to cover all costs.
1
The 1991 risk analysis found that the
probability that the airport would experience a shortfall in revenues was
low. We updated our analysis to take into account a number of recent
events that could affect the airport’s ability to meet its operating and debt
service costs.
The new analysis is based on the models developed for the 1991 report.
Modeling risk assessment is highly sensitive to the assumptions made
governing key variables. We paid particular attention to traffic estimates,
as they are critical to predicting airport revenues. The details of the
approach are discussed in appendix I.
Passenger Traffic
Volume
Passenger traffic is a direct source of revenue to DIA via the $3.00 PFC per
enplanement. More importantly, in accordance with the agreements
between the City of Denver and the airlines, all costs not covered through
other means such as
PFCs and rents from airport concessionaires must be
paid by airlines’ user fees. The agreements between Denver and the
airlines specify that these charges are not to exceed $20 per passenger
enplaned at
DIA in 1990 dollars. The cap is allowed to rise with inflation, so
that today, the maximum charge to the airlines per enplaned passenger is
$22.50 in current dollars. If airline payments combined with revenues from
other sources are not sufficient to cover an airport’s operating costs and
repay debt, the airport has a shortfall.
Airlines’ passenger traffic in Denver rose steadily after 1970, peaking in
1986 at slightly over 16 million enplaned passengers. Traffic declined to
below 14 million enplanements in 1989 and 1990 and our September 1991
study used this lower base in developing traffic forecasts and revenue
projections. However, traffic grew by 2.8 percent in 1991 and recovered
strongly in 1992 and 1993, when enplanements grew by 8.9 percent and 5.7
percent, respectively. In 1993, there were 16.32 million enplanements at
SIA.
1
We contracted with Hickling Corporation, a consulting firm that specializes in risk assessment for
airport investment projects, to assist us in this evaluation.
GAO/RCED-95-35BR New Denver AirportPage 39
Section 5
Impact of Delayed Opening on DIA’s Ability
to Meet Operating and Debt Service Costs
Table 5.1: Annual Enplanements at DIA
Between 1994 and 2000 Under Low,
Median, and High Traffic Forecasts
Enplaned passengers in millions
Year
Lower bound
estimate
Median
estimate
Upper bound
estimate
1994 14.573 16.192 17.002
1995 14.719 15.962 17.451
1996 14.866 16.422 17.900
1997 15.014 16.882 18.349
1998 15.165 17.343 18.798
1999 15.316 17.803 19.247
2000 15.469 18.263 19.697
Note: Actual enplanements in 1993 were 16.32 million.
GAO/RCED-95-35BR New Denver AirportPage 40
Section 5
Impact of Delayed Opening on DIA’s Ability
to Meet Operating and Debt Service Costs
Annual Enplanements
at DIA Between 1994
and 2000 Under Low,
Median, and High
Traffic Forecasts
To forecast traffic for 1994 and beyond, the current analysis took, as a
starting point, recent projections made by the consultant to the airport
system prior to the latest bond prospectus. Those projections indicated no
growth in 1994 and a decline to 16 million enplanements in 1995. Traffic is
then expected to increase and reach 18.3 million annual enplanements in
2000.
FAA also projected traffic at Denver, but while it also assumed no
growth in 1994,
FAA estimates that enplanements will increase to 17 million
in 1995 and to 21.9 million in 2000. The present analysis is based on the
more conservative estimates developed for the bond prospectus as a
median forecast.
Upper and lower bound estimates of enplanements were then developed.
The lower bound projection assumed that traffic in 1994 would be 10
percent lower than the current forecast, or about 14.6 million
enplanements annually. Traffic, thereafter, is assumed to grow by only 1
percent per year, yielding 15.5 million enplanements in 2000, nearly
1 million fewer than in 1993. It is assumed that there is a 90-percent
probability that this lower bound forecast will be exceeded. The upper
bound forecast assumes that traffic in 1994 is 5 percent higher than
projected in the prospectus and grows linearly, so that it reaches
90 percent of
FAA’s forecast for 2000. It is assumed that there is only a
10-percent chance that traffic growth will exceed this forecast.
GAO/RCED-95-35BR New Denver AirportPage 41
Section 5
Impact of Delayed Opening on DIA’s Ability
to Meet Operating and Debt Service Costs
Table 5.2: Mean Cost per Enplaned
Passenger If DIA Opens by March 1,
1995
Year Current dollars 1990 dollars
1995 $17.35 $14.46
1996 19.50 15.57
1997 18.08 13.83
1998 18.47 13.54
1999 17.64 12.41
2000 19.32 13.01
Table 5.3: Mean Cost per Enplaned
Passenger If DIA Opens by July 1,
1996
Year Current dollars 1990 dollars
1996 $20.62 $16.47
1997 19.43 14.89
1998 19.60 14.37
1999 18.96 13.30
2000 20.68 13.89
Note: The calculations for these tables are based on assumed enplaned levels of 14.6 million to
17 million enplaned passengers in 1994 and subsequent years as shown earlier in this section.
These levels are associated with the median of the forecast. The airport recently announced its
intention to accelerate principal repayment on the 1994A bonds, and this could increase the cost
per enplaned passenger by about $1 between 1995 and 2000.
GAO/RCED-95-35BR New Denver AirportPage 42
Section 5
Impact of Delayed Opening on DIA’s Ability
to Meet Operating and Debt Service Costs
Mean Cost per
Enplaned Passenger
for Two Opening
Dates
The Mayor of Denver has announced a new opening date of February 28,
1995, but there is no guarantee that
DIA will, in fact, open then. Therefore,
we examined the impact on operating revenues and debt service costs if
the airport is not open until July 1, 1996. On the basis of information
provided by the airport system, we assumed that any further delays in
opening
DIA will cost at least $18 million per month and would be debt
financed.
2
If current traffic forecasts materialize and if the current projections of the
airport’s operating costs are accurate, then regardless of whether
DIA
opens by March 1, 1995, or by July 1, 1996, expected revenues appear to be
sufficient to allow the airport to meet scheduled debt payments. Despite
the fact that airlines’ user fees will be almost 10 percent higher than they
would have been had the airport opened on time, the cost per enplaned
passenger will be several dollars below the $20 cap in 1990 dollars. With a
1995 opening, the cost per enplaned passenger will peak at about $15.57 in
1996 (in 1990 dollars) and then decline. With a 1996 opening, the peak
again occurs in 1996 at $16.47 in 1990 dollars.
Our analysis depends on cost and revenue forecasts that were developed
for the recent bond prospectus. Those projections, in turn, depend on
several key assumptions made by the Denver Airport System. First, the
airport assumes that it will be able to refinance the 1984 and 1985 bonds in
1995 and to restructure debt service. Doing so will reduce the airport’s
debt service by $121 million over the 1995-99 period. If the airport does not
refinance and restructure this debt, debt service costs will be higher and
the airport will need to find alternative revenue sources or to raise the fees
paid by the airlines.
2
The debt service figures used in our analysis were provided by the Denver Airport System in
August 1994.
GAO/RCED-95-35BR New Denver AirportPage 43
Section 5
Impact of Delayed Opening on DIA’s Ability
to Meet Operating and Debt Service Costs
Second, the revenue projections to the year 2000 are based on Continental
Airlines’ agreement to lease 20 gates over that period at a cost of
$273 million. However, Continental is reducing its presence at Denver. The
airport’s projections account for a reduced presence by Continental after
the year 2000, when it will have a commitment for only four gates, but
assume that Continental will either pay for the space or will sublet the
space to another airline. Third, the airport’s projections assume that
$95 million committed by
FAA in its letter of intent from the discretionary
account of the
AIP will be funded as planned. Finally, airport financial
forecasts were based on an assumption that a baggage system with
sufficient operational reliability would permit the airport to open.
Another key element of the airport’s cost is its debt service, and there are
differences in various reports on debt service requirements. An analysis of
1996 debt service requirements can illustrate the problem. The audited
financial statements for the Denver Airport System prepared by Deloitte &
Touche as of December 31, 1993, reported a 1996 debt service requirement
of $302.5 million. The latest Denver Airport System plan of finance shows
a 1996 debt service requirement of $289.6 million. The bond prospectus
financial analysis prepared by Leigh Fisher Associates, the airport’s
consultant, reported a 1996 debt service requirement of $243.7 million.
Denver Airport System officials and their consultants provided the
following rationale to reconcile these differences.
The audited financial statements did not include debt service on the 1994A
bonds, amounting to $24.4 million in 1996, because these bonds were
issued after the last audit which was done as of December 31, 1993.
Denver’s plan of finance assumes a $30.5 million debt service reduction in
1996 based on the refinancing in 1995 of the 1984 and 1985 airport system
revenue bonds.
The bond prospectus debt service requirement was inconsistent with
those in the other two reports largely because it excluded $40.5 million of
passenger facility charges (
PFC) in 1996. It assumed that PFCs would be a
revenue source that should be offset against total debt service.
GAO/RCED-95-35BR New Denver AirportPage 44
Section 5
Impact of Delayed Opening on DIA’s Ability
to Meet Operating and Debt Service Costs
DIA, in its plan of finance and in its bond prospectus, reduced debt service
requirements from the audited amount by $10.7 million in 1996 to account
for estimated market rates of interest on variable rate bonds. The audited
financial statements were prepared assuming maximum rates of interest
on variable rate bonds.
Several other variables that involve smaller dollar amounts were included
in the reconciliation.
GAO/RCED-95-35BR New Denver AirportPage 45
Section 5
Impact of Delayed Opening on DIA’s Ability
to Meet Operating and Debt Service Costs
Table 5.4: Reduced DIA Enplanement
Estimates to Levels Where There
Would Be a Significant Risk of Costs
Exceeding Revenues
Enplanements in millions
Year
Lower bound
estimate
Median
estimate
Upper bound
estimate
1994 11.075 12.306 12.921
1995 11.186 12.131 13.263
1996 11.298 12.481 13.604
1997 11.411 12.831 13.945
1998 11.525 13.180 14.287
1999 11.640 13.530 14.628
2000 11.757 13.880 14.969
Note: Actual enplanements in 1993 were 16.32 million.
GAO/RCED-95-35BR New Denver AirportPage 46
Section 5
Impact of Delayed Opening on DIA’s Ability
to Meet Operating and Debt Service Costs
Reduced DIA
Enplanement
Estimates to Levels
Where There Would
Be a Significant Risk
of Costs Exceeding
Revenues
The financial risk model was run by using different assumptions of
depressed levels of traffic in order to determine the sensitivity of
DIA’s
financial situation to the traffic forecast. We undertook this analysis partly
because Continental, one of the principal airlines expected to operate a
hub at
DIA, is scaling back its scheduled operations substantially. Today,
Continental handles about 24.2 percent of the traffic at
SIA and United
handles about 57.4 percent. No other airline handles as much as 5 percent,
although Delta and American handle 4.1 percent and 3.7 percent,
respectively. Continental plans to reduce the number of daily flights out of
Denver from 94 to 23 by the end of October 1994.
3
United plans to increase
its daily departures from 277 to 300 by the end of 1994.
Projected traffic levels would need to be nearly 20-25 percent lower before
the model found that there would be significant risk that
DIA’s estimated
costs might exceed revenues. We are not making an independent analysis
of traffic at
DIA; however, several points are relevant to Denver’s air traffic.
First, United will be handling almost 60 percent of the enplanements, and
that airline is committed to
DIA. Second, approximately 46 percent of the
traffic is originating or ending in Denver, and that traffic is dependent on
factors such as Denver’s economy, rather than on airlines’ user fees. Third,
in Continental’s 100 largest markets connecting through Denver, United
offers competing service in 77. In Continental’s top 1,000 markets that
connect through Denver (which account for more than three-fourths of all
Continental’s traffic over Denver), United offers competing service in 547.
4
Finally, while airlines’ user fees at Denver will be high, the costs of using
alternative hub airports can lead to higher airline operating costs, which in
many cases offset the higher fees at
DIA.
3
Although Continental is scaling back its operations, other airlines may increase their operations at
DIA to compensate for Continental’s reduction in flights. DIA’s revenue flow assumes revenues from
the reduced level of Continental’s operations; however, any additional change would affect the
airport’s revenues.
4
These data are for the first quarter of 1994, the most recent for which data are available. We define
United as “competing” if it has at least a 10-percent share of the market.
GAO/RCED-95-35BR New Denver AirportPage 47
Appendix I
Objectives, Scope, and Methodology
To determine the problems with the baggage handling system, we
interviewed officials of the
DIA management team, including contractors,
the airlines, an airline baggage consultant, and the consultant hired by the
City of Denver to evaluate the system. We reviewed the system’s
completion schedules including lists of tasks remaining to be completed,
specifications for the system, and other contract documents such as
agreements between the City, United, and BAE; and we observed tests of
the automated system.
To determine the cost of the delayed opening of
DIA, we reviewed cost
estimates and the resources available to pay these costs. In addition, we
performed an analysis of projected revenues and operating costs to
determine the reasonableness of those projections and to identify the
financial effects of continued delays. For our analysis, we (1) interviewed
appropriate officials of the Denver Airport System and the City Treasurer’s
Office, consultants responsible for projecting airport revenues and debt
service, and airline representatives; (2) reviewed and analyzed
DIA’s
accounting records, documents, and procedures, including the audited
1993 financial statement; and (3) reviewed relevant financial information
contained in official statements for issued bonds. We did not audit, and do
not express an opinion on, the data provided by
DIA that are used in our
analysis. We identified the underlying assumptions included in
DIA’s
revenue and cost projections. We note the key assumptions used in the
analysis where appropriate.
Certain information such as the airport system’s 1993 financial statement
was independently audited by Deloitte & Touche. The auditor issued an
unqualified opinion on the airport system’s financial position as of
December 31, 1993.
To address the financial outlook of the
DIA project, we discussed the costs,
including delay costs and available funding sources to finance those costs,
with
DIA officials, officials from the City’s Revenue Department, the
airport’s financial adviser at First Albany Corp., bond analysts, and
officials from credit-rating agencies. We also contacted United and
Continental—the two principal airlines serving the airport—for their views
on the proposed fees and charges. As part of these discussions, we
collected relevant information on the airport’s costs, revenues, debt, user
fees, and traffic levels.
To determine whether expected revenues would be sufficient to cover
operating costs and service the debt, we contracted with Hickling
GAO/RCED-95-35BR New Denver AirportPage 48
Appendix I
Objectives, Scope, and Methodology
Corporation, an airport consulting firm, to perform a risk analysis.
Hickling developed a risk assessment model to assist us in our 1991 study.
That model included six submodels: traffic,
O&M costs, project costs,
nonairline revenues, project finance, and airline revenues. We updated the
analysis using the most recent information on traffic projections, the
project’s cost, the financing plan, and the airport’s financial statements.
The model uses this information to simulate possible outcomes and
develops an estimate of the probability that net revenues will be sufficient
to service the debt.
Modeling risk assessment is highly sensitive to the assumptions made
governing key variables. The approach that was taken was to construct a
range of possible values for the key factors such that there is only a
10-percent chance that the actual value will be higher than the top of the
range and a 10-percent chance that the actual value will be lower than the
bottom of the range.
In addition to the assumptions surrounding traffic levels and traffic growth
discussed in section 5, several other assumptions were key to the analysis.
According to the information we developed from the airport system’s
provided data, the cost of further delays is assumed to be about
$18 million per month. If
DIA does not open by February 28, 1995, it is
assumed at a 90-percent certainty level that subsequent delay costs will be
at least $17 million per month and it is assumed that there is a 10-percent
chance that they will exceed $20 million per month. It is further assumed
that all costs associated with delays after February 28, 1995, will require
additional debt financing. The analysis assumes that the terms of the new
debt would be 30-year bonds with equal annual payments. The interest
rate on the new debt issue is assumed to have a median value of
7.8 percent. The 80-percent confidence interval for interest rates has an
upper bound of 9.5 percent and a lower bound of 7.2 percent.
Originally, the goal was to estimate the probabilities that
DIA would open
on certain dates given as the best estimates of technical specialists
involved in correcting the problems with the baggage system. A
questionnaire was developed to elicit responses on the likelihood of
failure of key subsystems of the baggage handling system. We received
some response to our questionnaire, but several key organizations did not
wish to speculate on when the problems with several subsystems would
be corrected, even though their speculations represented the best
informed judgments. When Denver’s Mayor announced that the airport
would open on February 28, 1995, with an alternative baggage handling
GAO/RCED-95-35BR New Denver AirportPage 49
Appendix I
Objectives, Scope, and Methodology
system, we refocussed our analysis to look at the impact on the airport’s
revenues and costs at different opening dates.
Hickling Corporation used its proprietary Risk Analysis Process (
RAP)
software and modified it to represent
DIA. The RAP model is a Monte Carlo
simulation that uses the uncertainty ranges for key variables to make
repeated estimates of forecast outcomes in the form of probability
distributions.
We did not review the documentation of the
RAP model’s internal logic or
attempt to verify the
RAP model. Therefore, we cannot attest to its validity.
As with the output of other policy-assisting tools, its outputs cannot be
relied upon as exact predictors of the future.
GAO/RCED-95-35BR New Denver AirportPage 50
Appendix II
Major Contributors to This Briefing Report
Allen Li, Associate Director
Randall B. Williamson, Project Manager
Francis P. Mulvey, Assistant Director
Lowell E. Hegg, Assistant Director/Denver Regional Office
Ted B. Baird
Steven N. Calvo
John Furutani
Stephanie K. Gupta
Madhav S. Panwar
Keith A. Rhodes
Francis W. Sutherland
Arthur D. Trapp
(341430) GAO/RCED-95-35BR New Denver AirportPage 51
Ordering Information
The first copy of each GAO report and testimony is free.
Additional copies are $2 each. Orders should be sent to the
following address, accompanied by a check or money order
made out to the Superintendent of Documents, when
necessary. Orders for 100 or more copies to be mailed to a
single address are discounted 25 percent.
Orders by mail:
U.S. General Accounting Office
P.O. Box 6015
Gaithersburg, MD 20884-6015
or visit:
Room 1100
700 4th St. NW (corner of 4th and G Sts. NW)
U.S. General Accounting Office
Washington, DC
Orders may also be placed by calling (202) 512-6000
or by using fax number (301) 258-4066.
Each day, GAO issues a list of newly available reports and
testimony. To receive facsimile copies of the daily list or any
list from the past 30 days, please call (301) 258-4097 using a
touchtone phone. A recorded menu will provide information on
how to obtain these lists.
PRINTED ON RECYCLED PAPER
United States
General Accounting Office
Washington, D.C. 20548-0001
Official Business
Penalty for Private Use $300
Address Correction Requested
Bulk Mail
Postage & Fees Paid
GAO
Permit No. G100
GAO/RCED-95-35BR New Denver Airport