1
BOLD®: Breakthrough Overhead Line Design
Transmission Line Design Considerations
Eric A. Miller, P.E., and Elizabeth Decima
BOLD® (Breakthrough Overhead Line Design) is a high‐capacity, high‐
efficiency transmission line design that optimizes structure geometry
through the use of curved steel arms and compact conductor phase spacing.
The unique geometry and electrical characteristics of a BOLD transmission
line can be designed and constructed in a manner similar to typical
transmission line projects; however, there are several considerations that
line engineers need to consider with BOLD projects.
The inaugural BOLD line constructed in Ft Wayne, Indiana was designed by
American Electric Power using a process similar to developing a new
structure or tower series. The BOLD structures developed are fully
compatible for use in PLS‐CADD™ and PLS POLE™. One key transmission line
design requirement for long lines, which are limited by voltage or stability
considerations, is that 95% of the line needs to retain the compact phase
spacing to maintain the electrical benefits of the BOLD technology. The
compactness of the conductor requires additional consideration for the line
engineer with regards to galloping criteria, rolling clearances, and structural
geometry. The unique electrical characteristics of BOLD also provide a line
engineer with a solution to install EHV transmission lines in a narrower
right‐of‐way corridor.
BOLD®: Transmission Line Design Considerations
2
Introduction
AEP has been a pioneer in extra high voltage (EHV) transmission technology, developing and
constructing the first 345kV and 765kV lines in the United States in the 1950s and
1960s, respectively.
AEP continues to lead this trend in transmission line innovation with the BOLD initiative.
With BOLD, or Breakthrough Overhead Line Design, AEP engineers set out to create a cutting edge
generation
of transmission lines that could achieve greater capacity and efficiency by increasing the
utilization of
rightofway (RoW) corridors. This more effective use of the RoW would reduce visual and
environmental impacts. BOLD offers both electrical and geometric benefits.
The BOLD technology leverages physics to maximize electrical performance. The phase separation is
reduced into a compact delta configuration (Figure 1) and the conductor diameter, number of sub
conductors, and bundle spacing are optimized. Figure 1 shows the BOLD insulator assembly for one
345kV circuit for a 3‐conductor bundle.
Figure 1
The electrical benefit of the compact configuration is a line with reduced inductance and increased
capacitance, which results in higher surge impedance loading (SIL). SIL is a measure of the relative loadability
among alternative line designs. By bundling with multiple subconductors per phase, the SIL capacity
increases and electric stress decreases to achieve desired corona and audible noise performance. A 345kV
doublecircuit BOLD 3‐bundled conductor design offers a 43% improved surge impedance loading over a
traditional doublecircuit 2‐bundled conductor design of the same voltage class [1].
When BOLD was developed, a goal of the project team was to address more than just optimizing the
electrical properties. The team also considered aesthetics and structural optimization to support the delta
configured phase conductors in a visually appealing way to appeal to the general public and facilitate public
acceptance during siting. The compact deltaconductor configuration is attached to a curved arm that also
offers geometric benefits by minimizing the structure height. This feature of BOLD is most beneficial to
transmission line engineers.
BOLD®: Transmission Line Design Considerations
3
The end result of BOLD is a highly efficient line operating on shorter structures with less visual impact to the
general public (Figure 2). BOLD has been developed for 345kV tubular and lattice designs and current
efforts are underway to fully develop 230kV and 138kV designs.
Figure 2
BOLDTransmission Line Design Considerations
The responsibility to successfully implement the BOLD technology in real world transmission line projects
ultimately falls on the transmission line engineer. Once a project has been identified as a candidate for
BOLD, the transmission line process will be similar to a traditional line design project. As with any new
structure family or technology, there are some key considerations the line engineer needs to keep in mind
as the project is advanced from concept to construction.
This paper will provide a high level overview of the inaugural BOLD project process and then discuss key
topics for a line engineer, such as PLSCADDTM modeling, compact spacing requirements, galloping and
rolling clearances, RoW width, and geometric considerations.
BOLD®: Transmission Line Design Considerations
4
Inaugural BOLD Project- Structure Development
The challenge of turning the BOLD concept into reality began with the identification of a candidate project in
Fort Wayne, Indiana. Several planning solutions were analyzed before deciding that the optimal solution was
to rebuild the 22mile doublecircuit, 6‐wired, 138kV existing tower line as a doublecircuit BOLD
construction with one circuit operating at 138kV and the other circuit at 345kV. It was decided that the
project would be a structureforstructure replacement to minimize impacts to property owners. Average
span length for the existing towers was 900’ with a maximum span length of 1219’ in a flat terrain
environment. Figure 3 shows the optimized BOLD 345kV tubular structure overlaid on the existing 138kV
tower. The 345kV circuit uses a 3 bundle 954 kCM ACSR conductor and the 138kV circuit uses a 2 bundle
954 kCM ACSR conductor.
Figure 3
BOLD structure development started with a conceptual design based on the optimized phase spacing in the
compact delta configuration. The optimized design was an iterative process to balance the electrical
benefits, and the associated impacts on audible noise, corona, and EMF, with the geometric constraints of
insulating lengths, arm length, and real world conductor motion from wind and ice.
Once the geometry was conceptually developed, the next step was electrical and structural modeling of the
conductor and structure to refine a prototype structure to be used for full scale structural testing, hardware
testing, and electrical testing.
Full scale structural testing was conducted at the ValmontNewmark structural testing facility in Valley,
Nebraska. Figure 4 shows the structural test setup. The full scale testing confirmed the structure strength
was consistent with the calculated values and confirmed that some of the unique aspects of the BOLD
construction, such as the curved arm bending process (Figure 5) and interconnected insulator assemblies,
could be accurately modeled and had no impact on structural performance. The structural testing was
conducted using the actual insulator assemblies.
BOLD®: Transmission Line Design Considerations
5
Figure 4 Figure 5
Hubbell Power Systems conducted single phase testing on the prototype insulators and hardware to
conclude that they met AEP’s design criteria. Threephase electrical testing was also conducted at the EPRI
Power Delivery Laboratory in Lenox, Massachusetts, for power frequency, corona effects, audible noise,
lightning surges, and switching surges.
Completion of the prototype testing series allowed the project development team to move into the next
design phase of the structure development to produce an optimized BOLD structure family in PLSCADDTM.
It was determined that the line would require a range of tangent and dead end structures, as well as a
running angle structure. The lightest and most frequently used tangent structure was designed for wind
spans up to 900’ and 0‐ line angles (Figure 6). Two heavier tangent structures were designed for longer
wind spans and line angles up to 6°. The running corner structure was developed for wind spans up to 1,000’
and 515° line angles (Figure 7). One dead end structure was designed for line angles of 030° and a heavier
dead structure was designed for 3060° line angles (Figure 8).
Figure 6 Figure 7 Figure 8
PLS-CADD Modeling
The BOLD PLSCADD models are developed using standard functions within the program and are a
collaborative effort between the line engineer and pole manufacturer. The line engineer delivers structure
performance drawingswhich provide load case, geometry, and attachment detailsto the pole
manufacturer. The pole manufacturer then develops the pole shaft model and provides the dimensions of
the curved BOLD arm. At this time, the pole manufacturer cannot provide PLS pole models of the curved
arm but can provide the arm dimensions. The line engineer then uses the arm dimensions provided by the
BOLD®: Transmission Line Design Considerations
6
manufacturer to create the arm, similar in PLSCADD to a typical davit arm, using a series of short tangent
segments and tapering the arm diameter (Figure 9). The process is similar to ordering a typical davit arm
structure but designing the davit arms as a separate component not provided by the pole manufacturer.
Figure 9
Connections, such as the insulator vangs and the “knuckle,” or the top section of the pole shaft where the
arms attach, are structurally designed and checked by the pole manufacturer. The line engineer designs the
insulators using the 2‐part insulator function in PLSCADD. Limits should be set within the model to check
that insulators do not go into compression under wind cases, as dictated by the project design criteria,
similar to typical V‐string insulators. The insulator attachment points will be vangs on the structure or the
vertex of an adjacent V‐sting insulator, depending on which insulator is being modeled. Figure 10 shows a
typical BOLD 2‐part insulator connectivity table from PLSCADD.
Figure 10
It should be noted that due to the interconnected property of the BOLD insulators, some of the insulator
strings will be subjected to loads that are doubled in magnitude. As shown in Figure 11, two insulator
strings, with the load magnitude labeled 2*TL and 2*TR, will support the load from the conductor attached
to the vang and the load from an interconnected insulator attached to the same vang.
Short tangent sections to
simulate curved BOLD
Short tangent sections to
simulate curved BOLD
BOLD®: Transmission Line Design Considerations
7
Figure 11
Figure 11
95% Phase Compaction Requirement
One key requirement for all line engineers working on a long BOLD transmission line project, limited by
voltage or stability considerations, is to maintain the compact phase spacing for 95% of the overall line
length. Typically, lines in excess of 50 miles are considered “long” transmission lines, and are therefore
subjected to the 95% phase compaction requirement. Increasing phasetophase clearances is a possible
design option that may be considered for long spans, at dead end structures (due to increased dead end
spacing needs), or when rolling to a horizontal configuration. However, electrical modeling of long
transmission lines has shown that the compact phase spacing is required for 9095% of the line length to
maintain the electrical benefits discussed previously. Setting the requirement at 95% will conservatively
ensure that the line will operate as intended. Deviation from this requirement would require additional
electrical modeling to ensure intended performance of the line is achieved.
Short lines, or lines which are thermally limited and not limited by voltage or stability considerations, are not
subject to the 95% phase compaction requirement. For these lines, the compact phase spacing should be
maintained for structure height minimization and aesthetic reasons, but the electrical performance will not
be affected by increasing the phase spacing in more than 5% of the line.
Galloping Criteria
For areas where galloping is either historically known to occur or is expected, the line engineer will need to
consider the potential for galloping in the design. Special consideration is required for BOLD projects due to
the compact phase spacing of the conductors.
Several galloping analysis methods are used in the transmission industry and the results of these different
methods can vary dramatically. Studies have shown that installing inspan interphase insulators, or I3
insulators, can reduce the galloping magnitude by half [2]. Figure 12 shows a picture of a typical midspan
insulator. Depending on the project span lengths and galloping specifications, the line engineer has several
options to mitigate galloping concerns. The following mitigation options can be applied to lessen other
forms of conductor motion:
o
Decrease span lengths (also may allow narrower corridor, as discussed
in RoW considerations)
o
If only a few of the longer spans have excessive galloping ellipses, phase spacing can be
increased
on those spans only, keeping in mind the 95% compact spacing requirement
o
Install I
3
insulators at the time of initial construction
o
Install conductor with compact spacing and monitor performance over time; install I
3
insulators at a later date, if deemed necessary
o
Use antigalloping conductor
BOLD®: Transmission Line Design Considerations
8
Figure 12
Rolling Clearances
Rolling from a compact vertical BOLD configuration to a horizontal configuration, such as a station bay, can
also require some consideration from the line engineer. Depending on the span lengths and geometry, the
line engineer has several options to meet the design criteria minimum phasetophase rolling clearances:
o
Increase phase spacing at a dead end structure outside the station, keeping in mind the 95%
compact spacing requirement
o
Install an intermediate suspension structure between a BOLD dead end and the station bay,
keeping in mind the 95% compact spacing requirement (see Figure 13)
o
Vary the tensions in each phase for the entrance span into the station (i.e., install the top
phase with higher tension than the middle phase and the bottom phase with lower tension
than the middle phase)
o
Install I3 insulators on the rolling spans at the time of initial construction
Figure 13
BOLD®: Transmission Line Design Considerations
9
Right-of-Way (RoW) Requirements
One additional benefit to a BOLD line is the flexibility it provides a line engineer to install EHV lines using a
narrower RoW width due to lower audible noise and magnetic fields. This can be a particularly useful
solution for RoW constrained areas, such as urban settings, or if the engineer intends to limit the galloping
ellipses.
As shown in Figure 14, audible noise and magnetic fields of a 345kV BOLD line with three subconductors at
the edge of 105’ RoW compares favorably to traditional 345kV designs at the edge of 150’ RoW. The
audible noise from BOLD is more than 1‐2 dBA lower than that of conventional design at the edge of 105’
RoW and less than that of traditional designs measured at the edge of the 150’ RoW. The magnetic field
from BOLD is 50% of that produced from traditional designs at equal electrical loading at the edge of each
RoW. The magnetic field from BOLD at the edge of the 105’ RoW is less than that of traditional designs at
the edge of the 150’ RoW. If the electric load of BOLD is doubled, the resulting magnetic field at the edge of
either the 105’ or 150’ RoW will equal the magnetic field of traditional designs with the base loading.
Figure 14
For a greenfield project without a constrained RoW, the line engineer will typically determine structure
locations to optimally minimize the number of structures and project costs. For these projects, RoW width
will be determined by conductor blowout. Conductor blowout for BOLD structures is similar to the blowout
of a typical suspension I‐string insulated conductor, even though the BOLD arm is longer and the middle
phase is further from the pole shaft than traditional designs. For typical transmission span lengths, the I‐
string insulator swing on a traditional 345kV structure will horizontally position the conductor in a vertical
plane close to the location of the outermost BOLD phase when both are loaded under 6#/ft wind cases, as
shown in Figure 15. In Figure 15, the pink lines represent the BOLD conductor blown out position at midspan
and the blue lines represent the traditional conductor in a similar condition for 1,000’ span lengths.
Figure 16 shows RoW widths required for a 345kV doublecircuit structure optimized line (150’ RoW with
optimized structure spacing), a 345kV doublecircuit RoW optimized line (105minimum RoW with shorter
spans to limit blowout), and a 345kV singlecircuit line RoW optimized line (50’ minimum RoW with shorter
spans to limit blowout). Some structures, which have design features to address galloping concerns, may
have middle phase davit arms that are longer than the top and bottom phase arms to reduce or eliminate
the galloping ellipse overlap. Structures with this design feature would have greater RoW width
requirements due to the increased blowout width. The traditional design selected for the blowout
comparison in Figure 15 does not have this design feature.
BOLD®: Transmission Line Design Considerations
10
Figure 15 Figure 16
Arm Geometry
BOLD arms are typically longer than traditional steel pole davit arms due to the optimized insulator
geometry. Some traditional tubular structures designed for galloping may have a longer middle davit arm,
comparable to the length of the BOLD arm, but most traditional designs will utilize davit arms considerably
shorter than the BOLD arm. For a 345kV BOLD structure, the tiptotip distance of the arms is 73’4”
compared to 43’0” for the traditional tubular structure with davit arms shown in Figure 17. The line
engineer needs to account for this additional length and may need to adjust typical offsets when placing
BOLD structures adjacent to public road RoW or railroads to avoid overhanging these facilities.
Corridor construction, or constructing parallel lines in a common RoW easement, is another situation where
the line engineer may need to evaluate typical offset distances between adjacent lines. Depending on the
geometry of the lines, the longer BOLD arms may present phasetoground clearances that are less than
those of traditional lines in corridor construction. In most cases, placing BOLD structures near the adjacent
line structures, and not at midspan where maximum conductor blowout occurs, will alleviate inadequate
phasetoground clearances.
Figure 17
BOLD®: Transmission Line Design Considerations
11
BOLD Dead End Structure Geometry
BOLD dead end structures are similar to traditional dead end structures and consist of two independent
poles with one circuit terminated on each pole. Ideally the compact delta phase spacing will be maintained
at the dead end structures. For light line angles, this can be achieved by terminating the top and bottom
phase on the pole shaft, similar to traditional tubular structures, and installing a davit arm to terminate the
middle phase (see Figure 18).
Figure 18
The compact phase spacing presents a unique geometry for the line engineer to consider, particularly for
heavy line angles. One clearance to check for medium to heavy line angles is the phase to ground clearance
between the middle phase, which terminates on a davit arm, and the steel pole as shown in Figure 19. As
the line angle increases, the middle phase davit arm will need to be lengthened to maintain the compact
delta phase spacing of the adjacent tangent structures. Installing a second davit arm, with both arms
perpendicular to the middle phase conductor, is a solution if the arm length becomes excessive for heavy
line angles.
Figure 19
Some projects may require one face of the poles to be “clean of wires for maintenance access purposes.
For these projects, it would be necessary to install all jumper loops on the same side of the pole as the
BOLD®: Transmission Line Design Considerations
12
middle phase davit arm. The compact phase spacing with heavy line angles can create challenges for
construction crews to make up jumper loops that maintain adequate clearance between the top phase
jumper loop and the middle phase corona rings on the energized end of the insulator (Figure 20). A
recommended best practice is to create 3D models of the jumper loops and insulator assemblies to discover
where design modifications may be needed prior to finalizing the insulator assembly designs. The line
engineer has several options for increasing clearances at the dead end insulators:
o
Space the phases out and use a typical dead end vertical configuration with all three phases and
shield wire terminated on the pole shaft, keeping in mind the 95% compact spacing
requirement.
Jumper loops would be installed on the inside angle of the pole, similar to
traditional construction.
o
Maintain the BOLD delta configuration but increase the vertical distance between the top and
bottom phases as required per the 3D model clearance check, keeping in mind the 95%
compact
spacing requirement. Depending on the line angle, two post insulators may be needed
to walk” the
jumper loop around the larger exterior angle.
o
If maintaining a clean pole face for maintenance is not a requirement, then installing the top
and
bottom jumpers around the inside angle of the pole, and installing the middle phase
jumper
around or under the davit arm, will provide adequate room for all three phase jumpers
Figure 20
Conclusion
BOLD offers transmission utilities with a solution to address many of the challenges faced in the current
environment, including increased public opposition, difficulty obtaining new RoW easements, and cost
sensitivities. The transmission line engineer plays an integral role in promoting the BOLD solution [1] and
successfully integrating this technology. As discussed in this paper, BOLD technology can be seamlessly
integrated with little modification to the traditional transmission line design procedures and tools used by
most utilities today. It has been successfully implemented on two 345kV projects in Indiana and has been
conceptually developed for numerous other applications.
BOLD®: Transmission Line Design Considerations
13
Figure 21
References
1.
R. Gutman and M.Z. Fulk, “AEP’s BOLD Response to New Industry Challenges,” Transmission
& Distribution World, November 2015.
2.
D.G. Havard. “Conductor Galloping” IEEE ESMOL and TP&C Meeting. Las Vegas, Nevada.
January
2008