Sent: Monday, February 14, 2022 3:08 PM
To: Smith, Justin L <SmithJL@gru.com>
Cc:
Huggins, Richard <Hugg[email protected]>; Behan, Frank <Behan.Frank@epa.gov>; Celeste, Laurel Subject: Deerhaven - CCR Part A Demonstration, Request for Additional Information
Dear Mr. Smith,
On November 29
th
, EPA contacted GRU to determine whether the date to cease receipt of waste requested in the
demonstration submitted pursuant to 40 C.F.R. § 257.103(f)(1) for the Deerhaven Generating Station was met. GRU
explained that they were unable to start construction for the new alternative capacity due to unusually wet conditions
and therefore fell behind schedule. In light of this and as provided for under 40 C.F.R. § 257.103(f)(3)(ii), EPA is
requesting additional information to complete its review of GRU’s demonstration for the Deerhaven Generating Station.
EPA requests that GRU submit the following:
1. A narrative explaining the progress made and current activities and phase/step at Deerhaven to achieve
alternative capacity.
GRU’s gas conversion project has allowed GRU to continue to operate its coal-
fired boiler without generating CCR
(as anticipated and described in the April 12, 2021 letter). GRU has submitted unit heat input data to EPA through
EPA’s Emissions Collection and Monitoring Plan System demonstratin
g that GRU has not generated CCR since July
2021. Since CCR has no longer been generated, GRU is not seeking alternative capacity for CCR.
Information on the schedule/timeline of the currently in-
progress closure of the surface impoundment system can
be found in Attachment A of the updated CCR Surface Impoundment System Closure Plan posted on GRU’s publicly-
accessible internet site.
2. A discussion of the issues that led to the delay to the requested date to cease receipt of waste.
Precipitation records f
rom Gainesville Regional Airport indicate two intense storm events occurred in April 2021.
The first occurred over April 11 - 12 and the next occurred over April 17-
19. A review of the liquid elevations of each
pond indicate that the second pond (i.e., the
pond in operation) was already operating within 1 foot of its maximum
operating level on April 8, 2021, prior to the first storm event. To avoid an unsafe operating condition of the second
pond, the first pond had to again be utilized to receive plant process waters and stormwater.
3. An updated requested date to cease receipt of waste.
GRU ceased generation and concomitant deposition/receipt of CCR in its surface impoundment system in July 2021.
GRU has already commenced closure and ceased operation/receipt of non-
CCR waste in its first pond and plans to
cease operation/receipt of non-
CCR waste in the second pond in October 2022 (as described in the CCR Surface
Impoundment System Closure Plan). Once each pond of the surface impoundment system is successivel
removal and decontamination of CCR, the ponds will be repurposed to exclusively manage non-
as needed for continued operation of the plant.
4. An updated narrative justifying the new date to cease receipt of waste.
October 202
2 is the beginning of the “dry” season for the Gainesville area and is the earliest date GRU can safely
(i.e., to minimize the risk of exceeding the maximum operating level of the first pond) remove the second pond
from service to complete closure of the C
CR Surface Impoundment System. Please note that removing one of the