Page 1 of 15
Issued June 2023
Guidance on using NEC contracts for ground investigations
NEC contracts have been designed to be used in most types of work relating to the built
environment. Ground investigation contract works can be procured using NEC forms. This
guidance gives advice on how to implement this and deal with the specific requirements of
ground investigation contracts.
Ground investigation works generally consist of two parts:
the physical work of drilling, boring, excavation, sampling, in situ testing and
monitoring, and
surveying, analysis, laboratory testing and reporting of findings.
Because of the nature of the physical work, one of the “works” contracts in the NEC family
will normally be appropriate, either the Engineering and Construction Contract (ECC) or the
Engineering and Construction Short Contract (ECSC). Whilst a Professional Service
Contract (PSC) could be appropriate for desk studies, guidance and reporting, it is not
suitable for site works.
For simple, straightforward ground investigations the ECSC could be suitable. For larger
scale, more complex and higher risk projects the ECC would normally be used.
Whichever of these forms is used, the detailed requirements for the investigation are set out
in the Scope. This should include any constraints on how the work is done, for example
restrictions on access and reinstatement of access routes. The way the Scope is drafted will
allow flexibility where needed for the investigation. For example, it may give specific depths
for boring, or it may require specific strata to be investigated.
The purpose of a ground investigation is to provide data that will be used to assess the
ground conditions. A contract that allows flexibility in obtaining this data is essential in
providing the best information for a proposed project.
ECC and ECSC both provide for compensation when specified events occur. Of particular
relevance to the ground investigation contract is the compensation event relating to physical
conditions. This provides compensation for conditions which have “such a small chance of
occurring that it would have been unreasonable to have allowed for them”. For more
complex investigations, it may be appropriate for a client to specify “reference conditions”
which identify the conditions beyond which a contractor will be compensated. These should
be defined in ECC through “additional compensation events” in Contract Data part one or a
Z clause, and in ECSC by including “additional conditions” in the Contract Data.
The dates for starting and completing the work are stated in the Contract Data. The ECC
provides substantial detail of what a contractor must include in its programme for the work,
which would normally be appropriate only for the more complex projects. The ECSC allows
a client to specify the level of detail required in the programme, and the interval when the
programme is to be updated. This provides the flexibility needed to manage a simpler
ground investigation.
Page 2 of 15
If using the short contract, payment for the work is made through the prices in the Price List.
These can be quantity related or lump sum payments for specified activities. The quantities
at the time of awarding the contract would normally be those estimated by the client, whilst
payment would be based on the actual quantities encountered. If payment for analysis and
reporting is made on a time basis, then again estimated quantities of time for particular
categories of people should be included within the Price List. The method of measurement
for these quantities needs to be explained, either by reference to a published model or by
including statements in the Price List, setting out the method and rules used.
If using the ECC, a number of pricing models are available. Normally for ground
investigation the bill of quantities option would be used in which a client takes the risk of the
actual quantities of the work. In the ECC this is payment option B. ‘Priced contract with bill
of quantities’.
If a client wanted to use a target contract to better encourage collaboration, but still needed
to retain the risk of the quantities the ECC’s option D (Target contract with bill of quantities)
could be used. However, the client would then need to measure the quantities of the work
and to audit the contractor’s costs.
In an extreme case where the level of investigation was likely to be identified only during the
investigation stage itself, a cost reimbursement option could be adopted. In ECC that would
be option E.
The bill of quantities for options B or D needs to be prepared by the client and included for
completion by the bidder in the bidding document. The approach to preparing this should be
similar to that used for the Price List in the ECSC but may need to be more detailed. Again,
the method of measurement needs to be specified to ensure that both parties are recording
quantities on the same basis.
Further details setting out the key differences between the ECC and the ECSC can be found
here.
A commonly used specification for ground investigations, particularly in the UK is that
published by the Institution of Civil Engineers (ICE), which includes a standard Bill of
Quantities and method of measurement. Further guidance on how to use the ICE’s
Specification and the documents that it requires in an NEC contract is detailed below.
Page 3 of 15
Appendix 1 - Guidance on the use of UK specification for ground investigation
Interface between NEC contracts and the ICE Specification for Ground
Investigation
Contents
Guidance on using NEC contracts for ground investigations .................................. 1
1. Purpose of this document .............................................................................................. 4
2. Scope and Site Information ............................................................................................ 4
3. Entries in the contract .................................................................................................... 5
2.2 Investigation Supervisor ........................................................................................... 6
3.3 Quality Management ................................................................................................ 6
3.4.3 Risk assessment and method statements. ............................................................ 6
3.5.1 Utilities. ................................................................................................................. 8
3.5.2 – 3.5.8 Other information ....................................................................................... 8
4.3 Site establishment .................................................................................................... 9
4. Schedules within the Specification .............................................................................. 9
Schedule 1. Information and site-specific requirements ................................................. 9
5. Documents in the NEC contract ............................................................................... 11
Scope .......................................................................................................................... 11
Site Information ............................................................................................................ 11
Payment documents .................................................................................................... 11
ECC Bill of Quantities................................................................................................... 12
ECSC Price List ........................................................................................................... 12
6. Other issues ............................................................................................................. 13
Rates for people........................................................................................................... 13
Expenses ..................................................................................................................... 13
Physical conditions ...................................................................................................... 14
People ......................................................................................................................... 14
7. Defined Terms .............................................................................................................. 14
8. Definitions ................................................................................................................ 14
Page 4 of 15
1. Purpose of this document
This document is to set out guidance to properly incorporate the well-used ICE Specification
for Ground Investigation 3
rd
Edition 2022 (the ‘Specification’) into an NEC contract.
Ground investigation works can be procured using either:
the NEC Engineering and Construction Contract (ECC), usually Option B, priced
contract with bill of quantities or
the NEC Engineering and Construction Short Contract (ECSC).
Separate guidance on the choice between the ECC and the ECSC is included above
and available on the NEC website.
There are some differences relating to the Specification between the requirements of
the ECC and
the ECSC.
These differences are addressed in this document.
The convention of using italics for terms which are identified the Contract Data and capital
initials for terms defined in the relevant NEC4 contracts has been used in the section of the
guidance.
2. Scope and Site Information
Key documents in an NEC contract are the Scope and the Site Information.
In both ECC and ECSC the Scope is defined as:
‘Scope is information which
specifies and describes the works or
states any constraints on how the Contractor Provides the Works
and is either
in the documents which the Contract Data states it is in or
in an instruction given in accordance with the contract.’
Hence the Scope will usually include drawings and specifications.
The conditions of contract point to the Scope for certain information.
The NEC’s guidance notes ‘Preparing an engineering and construction contract’ and
‘Preparing an engineering and construction short contract’ include guidance on the
preparation of and a possible contents list for the Scope.
The Site Information is a separate document in ECC and ECSC. This is defined as:
‘Site Information is information which
describes the Site and its surroundings and
is in the documents which the Contract Data states it is in.’
Page 5 of 15
Unlike that of the Scope, this definition does not actually explain what the Site Information is
for. Site Information is provided in the contract so that the Contractor can understand the
physical conditions likely to be encountered and so prepare for and price the risk through its
method of working, programme and designs.
The Site Information may include factual information such as
geotechnical information,
as built drawings,
surveys of existing services and
other surveys - unexploded ordnance, contamination etc.
In the UK this factual information about the physical conditions is, in any case, required to
be passed to the bidder in the Pre-Construction Information required by the Construction
(Design and Management) Regulations (2015).
The ECC has a compensation event for physical conditions at clause 60.1(12):
‘The Contractor encounters physical conditions which
are within the Site,
are not weather conditions and
an experienced Contractor would have judged at the Contract Date to have
such a small chance of occurring that it would have been unreasonable to
have allowed for them.
Only the difference between the physical conditions encountered and those for which
it would have been reasonable to have allowed is taken into account in assessing a
compensation event.’
The compensation event in the ECSC (Clause 60.1(8) is the same.
The compensation event must be read in conjunction with Clause 60.2:
‘In judging the physical conditions for the purposes of assessing any compensation
event, the Contractor is assumed to have taken into account
the Site Information,
publicly available information referred to in the Site Information,
information obtainable from a visual inspection of the site and
other information which an experienced Contractor could reasonably be
expected to have or to obtain.’
Site information is therefore a key document in determining whether a compensation event
has occurred.
3. Entries in the contract
Specific issues in the body of the Specification
Page 6 of 15
2.2 Investigation Supervisor
The ‘Investigation Supervisor’ is the person acting for the Client to manage the contract. The
duties of the Investigation Supervisor’ under an ECC contract will be carried out by the
Supervisor in relation to quality related issues, but by the Project Manager for other issues.
If the ground investigation is only a part of the works, the Supervisor or the Project Manager
may find it appropriate to appoint delegates (under Clause 14.2) to act as the Investigation
Supervisor in accordance with the Specification. In an ECSC contract, the Client may find it
appropriate to appoint a delegate (under Clause 14.5) to act as the Investigation Supervisor
in accordance with the Specification.
3.3 Quality Management
The Specification 3.3 includes:
When specified in Schedule S1.8.2, all work shall be carried out in accordance with a
quality management system(s) established in accordance with BS EN ISO 9001:2015, BS
EN ISO 14001:2015 and BS OHSAS 18001:2007/BS ISO 45001:2018.’
In the ECC and the ECSC the Contractor must comply with the Scope (clause 20.1). If the
words in Specification 3.3 are included, there is no need to say more about quality
management.
In addition ECC Clause 40.1 states:
‘The Contractor operates a quality management system which complies with the
requirements stated in the Scope’
further underlining the obligation of the Contractor to operate the quality management
system.
3.4.3 Risk assessment and method statements.
Clause 3.4.3 of the Specification incudes:
‘At tender stage or during early Contractor involvement in the project the Client shall
provide a Designer’s Risk Assessment or (safety) risk register (including mitigation) to
the Contractor’.
Whilst this is true, the Scope should not state what is to be done ‘at tender stage’ (ie prior to
award). However, the Designer’s Risk Assessment or (safety) risk register (including
mitigation) should be provided to tenderers in a single stage tender process or passed to the
Contractor during ‘Stage One’ of an early Contractor involvement (ECI) process.
Note that neither the ECC nor the ECSC include a ‘Designer’s Risk Assessment’ or
a’(safety) risk register’.
In the ECC (but not the ECSC) there is an entry in the Contract Data part one
‘The following matters will be included in the Early Warning Register.’
This has the same effect as an ‘early warning’ after award of contract. It gets the item on the
Early Warning Register and so on the agenda for early warning meetings. It does not
Page 7 of 15
change risk allocation. It may be appropriate to include in this list some of the matters on the
Designers Risk Assessment or (safety) risk register if they could affect time, cost or quality.
If the (safety) risk register (including mitigation) includes things that the Client has decided it
wants the Contractor to be required to actually do, then these requirements must be
included in the Scope.
Clause 3.4.3 of the Specification also states:
‘Pre-construction Information (in accordance with CDM 2015), including a Desk Study
and field reconnaissance information, shall be provided by the Client to the Principal
Designer and Designer.’
This part of the Specification only applies to contracts in the UK. The Pre-construction
Information is not part of the contract but is required by CDM to be provided by the Client to
bidders. This would normally be provided as an appendix to the instructions to tenderers. It
may be appropriate for some or all of the factual Pre-Construction Information to be included
in the contract as Site Information.
Clause 3.4.3 of the Specification also states:
‘Prior to the start of site operations, the Contractor shall assess the available information
and provide to the Investigation Supervisor developed site-specific risk assessments and
method statements covering all aspects of their work to be carried out.’
The Management of Health and Safety at Work (Amendment) Regulations 2006 (The
‘Management Regulations’) require the Contractor to carry out a risk assessment and
design a safe method of working. However, neither the Management Regulations or the
Construction (Design and Management) Regulations 2015 (CDM) explicitly require a
‘method statement’. However, in the UK it has become standard practice for a contractor to
prepare method statements for its operations showing how they will be carried out safely.
In the ECC (but not the ESCS) there are detailed requirements of things to be included in
the programme (Clause 31.2 and 32.1). Clause 31.2 requires the ECC programme to
include:
‘• for each operation, a statement of how the Contractor plans to do the work
identifying the principal Equipment and other resources which will be used’
The ECC’s ‘statement of how’ is not intended to be a full ‘method statement’ of how the
Contractor plans to carry out the works but should be sufficiently detailed for the project
manager to understand the programme.
If the Client requires detailed method statements under an ECC or ECSC (in addition to the
statements provided as part of the programme (in the ECC)), then the Scope must include:
what is required to be submitted by the Contractor,
whether such documents are to be submitted to the Project Manager / Client for
information or for acceptance,
Page 8 of 15
if for acceptance then whether the Contractor has to obtain acceptance from the
Project Manager/ Client prior to doing the work and
in the ECC, if for acceptance, then to follow the standard procedure in the contract,
what would be acceptable reasons for the Project Manager to not accept a method
statement.
Those ‘reasons’ might include that ‘the method statement does show how the work is to be
carried out safely’.
Note that if the Project Manager/ Client is required to accept such method statements, they
must have the competence or have access to competent parties to do such a review and
acceptance.
The Client must decide if there is merit in requiring the Project Manager (ECC) or Client
(ECSC) to review and accept the method statements.
It is considered good practice to require the Contractor to name (as a key person in the case
of the ECC) its ‘Temporary Works Coordinator’ and require all method statements to be
approved by that Temporary Works Coordinator.
3.5.1 Utilities
Clause 3.5.1 of the Specification includes:
‘The Client, or the Designer where instructed by the Client, shall supply all available
utilities drawings and documentation with the Pre-construction Information, as
required by CDM 2015. The positions of all known mains, utilities, drains, sewers,
tunnels and pipelines owned by statutory undertakers, public authorities and private
individuals, shown on the drawing(s) detailed in Schedule S1.7, are based on
information extracted from the records of the various bodies and shall be regarded
as approximate only.’
The Pre-construction Information is not part of the contract but is required by CDM to be
provided by the Client to bidders. This would normally be as an appendix to the instructions
to tenderers. As noted in section 0, the drawings in Schedule S1.7 showing the location of
utilities should be Site Information rather than Scope.
3.5.2 3.5.8 Other information
These sections cover factual information relating to:
3.5.2 Hazardous ground and land affected by contamination
3.5.3 Protected Species
3.5.4 Notifiable and invasive species
3.5.5 Natural and anthropogenic cavities
3.5.6 Archaeology
3.5.7 Designated sites
3.5.8 Past ground investigations or water wells
Page 9 of 15
In each case the Specification requires information to be included in the Schedules.
In each case this information should be included in the Site Information.
4.3 Site establishment
Clause 4.3.1 of the Specification includes:
‘The Designer shall provide an initial estimation of the plant, equipment and utilities
necessary to complete the works and include itemisation in Bill A of the Bill of
Quantities.
The Contractor shall review the minimum itemisation provided by the Designer in
Bill A and identify any additional such items to complete the works. Where
additional items or quantities are identified i.e., independent post-delivery pre-use
inspections of drilling machines, the Contractor shall make appropriate
amendments to the proposed Bill A items and quantities and add additional
contract-specific items, if required.’
The ‘Designer’ is not defined in the Specification but is clearly the person designing the
required investigation and writing the Scope. The text here is unusual. It will normally be left
to the Contractor to determine the ‘plant, equipment and utilities necessary to complete the
works’. If the Designer has done this in the Bill of Quantities then, as part of the tender
process the Contractor might propose amendments to the Bill of Quantities but it is most
unusual for the Contractor to be allowed to change the Bill of Quantities in this way.
To enable this, it would be necessary to define a procurement process that allowed for
changes to the bill to be proposed by tenderers and reviewed by the Client.
The scope should not include requirements relating to the tender stage (ie prior to award),
so this section should not form part of the Scope.
4. Schedules within the Specification
The Schedules are specific contract-specific information which are stated to ‘form part of the
Specification’ (Clause 1.1).
The Schedules are:
Schedule 1. Information and site-specific requirements
Schedule 2. Exploratory holes
Schedule 3. Investigation Supervisor’s facilities
Schedule 4. Specification amendments
Schedule 5. Specification additions.
Some elements in the Schedules risk overlapping specific data in an NEC Contract.
Schedule 1. Information and site-specific requirements
S1.1 Name of Contract.
Page 10 of 15
In the NEC there is no specific place for the ‘Name of the Contract’ and ‘contract’ is not a
defined term. It will be logical, however, to have the ‘Name of the Contract’ here consistent
with the entry for the works in Contract Data part one.
S1.6 Geology and ground conditions.
The guidance for the completion of this section states:
‘ A summary description is required of the geology and ground conditions expected to
exist at the site. This should be based on information obtained from the British
Geological Survey (BGS) website (https://www.bgs.ac.uk), and from BGS maps and
memoirs, other readily accessible publications and records, and any previous
investigations. Difficult ground or groundwater conditions, mine workings, and so on
should also be noted. Where hazardous or contaminated ground is known to exist, full
details must be made available’.
In NEC this information is Site Information and not Scope.
S1.7 Schedule of drawings (and documents).
This Schedule must separate
those drawings which are Scope from
those drawings which show factual information about the site including utilities and
which, in NEC, are Site Information.
The relevant documents must be included in either Scope or Site Information.
S1.8.3 Project management, supervision and execution personnel.
This section of the Specification is for the requirements of a contractor’s team.
In both ECC and the ECSC the Contractor is required to comply with these requirements as
they will be included in the Scope.
The ECC (but not the ECSC) has the concept of ‘key people’. The jobs of those key people
can be included by the Client in the Contract Data part two along with the minimum required
qualifications and/or minimum experience for the jobs, The bidder then offers stated people
for the roles. The Contractor is then required by Clause 24.1 to provide the named key
persons or propose alternatives with equivalent qualifications and experience.
S1.8.5 Hazardous ground, land affected by contamination and notifiable and invasive
weeds.
S1.8.6 Additional information on utilities not shown on Contract drawings.
S1.8.7 Known/suspected mine workings, mineral extractions, etc.
S1.8.8 Protected Species.
S1.8.9 Archaeological remains.
In NEC all these items (S1.5.5 to S1.8.9) are Site Information and not Scope.
Page 11 of 15
5. Documents in the NEC contract
Scope
Most of the Specification will be included as part of the Scope of an NEC contract.
However, the NEC document needs to be clear that the following parts of the Specification’s
Schedule 1 are Site Information and not Scope.
S1.6 Geology and ground conditions.
S1.7 Schedule of drawing(s) (and documents) - the subset of those drawings (and
documents) that are factual information about the Site. Hence the list of drawings
should be clearly split between Scope and Site Information.
S1.8.5 Hazardous ground, land affected by contamination and notifiable and invasive
weeds (Clauses 3.5.2 and 3.5.4).
S1.8.7 Known/suspected mine workings, mineral extractions, etc. (Clauses 3.5.2 and
3.5.5).
S1.8.8 Protected species.
S1.8.9 Archaeological remains.
The Specification document also gives guidance on the required Bill of Quantities.
In the NEC, the pricing document is separate from the Scope. The pricing document is
an Activity Schedule in an ECC Option A or C
a Bill of Quantities in an ECC Option B or D and
a Price List in an ECSC contract.
Hence the Bill of Quantities that is provided as part of the Specification and used to produce
the pricing document pre-contract and must not be included in the NEC’s Scope.
In writing the NEC’s Scope note that many issues, e.g. welfare facilities and quality
management are already covered by the Specification. The additional Scope should not
duplicate provisions that are already in the Specification.
The ECSC was developed with the intention that the Parties could write in their
requirements in the NEC’s standard document. However, the document may be put together
electronically, in which case it is essential that the Scope and other documents (Price List,
Site Information) are adequately identified as part of the contract.
Site Information
The Site Information should include the information included in parts of the Specification
identified above.
In addition to the material identified in the Specification, there may be other Site Information
that should also be included in the document called ‘Site Information’.
Payment documents
In the NEC, the pricing document is separate from the Scope. The pricing document is
Page 12 of 15
an Activity Schedule in an ECC option A (priced contract with activity schedule) or
Option C (target contract with activity schedule)
a Bill of Quantities in an ECC option B (Priced contract with bill of quantities) or
Option D (target contract with bill of quantities) or
a Price List in an ECSC.
For most contracts for ground investigation a Bill of Quantities is most likely to be
appropriate. This is clearly why a model Bill of Quantities is included within the Specification.
In an ECSC contract, the Bill of Quantities is used to create the Price List
ECC Bill of Quantities
If a Bill of Quantities option is chosen, the Bill of Quantities needs to be prepared by the
Client based on the model of the Bill of Quantities in the Specification. The Specification
gives standard words for the preamble to the Bill of Quantities and suggestions relating to
the items in the Bill of Quantities. These standard words should be included as appropriate,
and added to if necessary, as a preamble to the Bill of Quantities.
The entry in the ECC Contract Data part one for the method of measurement should be the
preamble in the bill of quantities.’
Note that in clause 60.6 there is a compensation event if:
‘The Project Manager gives an instruction to correct a mistake in the Bill of Quantities which
is
a departure from the rules for item descriptions or division of the work into items in
the method of measurement or
due to an ambiguity or inconsistency.’
Clearly the Bill of Quantities must be prepared and checked carefully.
Note that in an ECC contract if the Scope is changed the default process to evaluate the
effect on the ‘Prices’ is based on the Contractor’s Defined Cost (clause 63.1). It does not
automatically use the rates for items in the Bill of Quantities. However, under clause 63.2,
the Project Manager and the Contractor can agree instead of Defined Cost to use any ‘rates
or lump sums’. Therefore the Project Manager and the Contractor may choose to agree to
use the rates in the Bill of Quantities.
ECSC Price List
The Price List needs to be prepared by the Client based on the model of the Bill of
Quantities in the Specification. The Specification gives standard words for the preamble to
the Bill of Quantities and suggestions relating to the items in the Bill of Quantities. The
ECSC’s method and rules used to compile the Price List should refer to the preamble in the
Bill of Quantities.
Note that under ECSC 14.3 ‘
‘The Client gives an instruction to correct a mistake in the Price List which is
Page 13 of 15
a departure from the method and rules stated in the Price List and used to
compile it or
due to an ambiguity or inconsistency.’
And this is a compensation event under 60.1(12).
Clearly the Price List, like all other parts of the draft contract must be carefully prepared and
thoroughly checked.
Note that in an ECSC contract (unlike in the ECC contract) if a compensation event (e.g.
from a change in Scope) only affects the quantities of work shown in the Price List the rates
in the Price List are used to assess the change to the Prices (clause 63.1). Defined Cost
(the default process for assessment in ECC) is used only if the compensation event does
not ‘only affect the quantities of work shown in the Price List’ (clause 63.2).
6. Other issues
Rates for people
The Bill of Quantities included within the Specification includes under ‘A20 Provide project
management, supervision and execution personnel’ a list of names and roles calling for a
daily rate from the bidder.
The Client will decide whether or not this is appropriate or whether the bidder should include
for people in the rates for other items.
If such rates are included, they will be used to pay for the work in the Scope. However, the
assessment of people costs for compensation events is made using the ‘People Rates’ plus
the Fee for both ECC Option B and the ECSC. The Client should logically use the same
categories of staff for the People Rates as are included in part A20 of the Bill of Quantities
of the Specification. The Client might require in its instructions to tenderers that the People
Rates + Fee are equal to the rates given in the Bill of Quantities.
Expenses
The Bill of Quantities within the Specification has items (M11-M14) allowing for certain
stated expenses to be paid. The Bill of Quantities will include an estimate of the quantity of
each type of expense. Any expenses in the Bill of Quantities will therefore be included in the
Price for Work Done to Date when they are measured.
ECC
The ECC has limited reference to expenses but any included in the bill of quantities will be
included in the Price for Work done to Date when they are measured.
ECC Option B includes the ‘Short Schedule of Cost Components (SSCC), which defines
what is included in Defined Cost. Defined Cost is used only for compensation events.
Page 14 of 15
ECSC
The ECSC has no reference to expenses but any included in the Price List will be included
in the Price for Work Done to date when they are measured.
Physical conditions
The Client should check that the standard compensation events are appropriate for the
works and decide if any further compensation events are required to reflect any risks that
the Client wants to retain so that the Contractor does not have to price the risk of the event
happening.
ECC
Additional compensations events can be added in the Contract Data, but any changes to
standard compensation events must be made by additional conditions of contract (Option
Z).
ECSC
Additional compensations events or changes to standard compensation events must be
included in the ‘additional conditions’ at the end of the Client’s Contract Data.
People
Clause 2.3 of the Specification includes:
‘Categories of personnel who may be required by the Contract are as follows:
(a) Technician
(b) Graduate ground engineer
(c) Experienced ground engineer
(d) Registered Ground Engineering Professional
(e) Registered Ground Engineering Specialist
(f) Registered Ground Engineering Adviser’
S1.8.3 of the Specification deals with project management, supervision and execution
personnel. The NEC’s means of specifying requirements for particular roles is covered in
the comment on Specification part S1.8.3.
7. Defined Terms
8. Definitions
The following text is required as a preface to the ICE Specification for Ground Investigation,
under the heading of ‘Preface to the Specification’. It should state:
Terms in the Specification are replaced with the following.
ECC and ECSC
‘Contractor’ means Contractor.
‘Contract ‘means this contract.
Any requirement for ‘approval’ by or ‘agreement of’ the Investigation Supervisor or the
Employer means ‘acceptance’.
Page 15 of 15
ECC
‘Employer’ means Client.
‘Investigation Supervisor’ means “Supervisor” for actions which the Supervisor carries out in
the contract, andProject Manager’ for other actions.
ECSC
‘Employer ‘means Client.
‘Investigation Supervisor’ means Client.
Acknowledgement:
NEC Contract Board
Richard Patterson, BA MBA CEng MICE NEC and Procurement Specialist, Mott
MacDonald
Neil Parry, AGS.