26
originate from failure. All lessons, however, are beneficial to learn from, in terms of what worked well or what
went wrong. The main questions to ask are:
What are the lessons to be learned and how can they be disseminated within the project team
and
fed back to the organization as a whole?
Are experiences and knowledge shared within a project team and its stakeholders?
What can most likely be replicated in another project phase or component, i.e. transferability?
For lessons to be drawn, project teams need to understand what worked – or did not work – where, with
whom, under what circumstances and why. This requires being able to analyse the project implementation
arrangements and context.
It is only possible to learn lessons when there is enough time to reflect on practice, identify lessons and
publicise them to others, and when others have the chance to absorb and apply the lessons. Ideally project
teams should schedule regular meetings for this type of reflection on the project, and to record monitoring
information. In the first instance, monitoring should give the project team and stakeholders the chance to
discuss/exchange, identify some lessons, and learn from lessons identified in order to improve their practice.
4.2. MONITORING AND EVALUATION TOOLS FOR TC PROJECTS
A range of tools can be applied to M&E. A mixture of tools is recommended in order to ensure that M&E is
balanced with other project management functions, and is useful and relevant in achieving its purpose.
The following tools and mechanisms are proposed for the M&E of TC projects: Project Progress Assessment
Report (PPAR), field monitoring mission, and Self-Evaluation.
4.2.1. Project Progress Assessment Report (PPAR)
The PPAR is the main monitoring tool for TC projects. It is used during the lifetime of a project to capture
progress made towards achieving the expected/planned results. It is also used at the end of the project for
the submission of Project Completion Report (PCR). Its submission is mandatory for CPs (see frequency
§2.4) using the PCMF (web-based) platform (http://pcmf.iaea.org). The information contained in the PPARs
submitted is used by the TC Department to compile reports.
The format is presented in Annexes F and G and an example is given in Annex H. The PPAR comprises six
sections: Basic information, Outputs, Equipment, Overall Analysis, Outcome, and Lessons to
learn/Recommendations. Explanations are provided below for each section.
Basic information:
This is an introductory section that provides information on the country, name of the main CP and institution,
project number and title, year of approval and year of effective start up, total approved budget (by donor),
reporting period (e.g. 01/2011 to 06/2011), and report contributors, i.e. other project members.
The section ends with a question to point out any change that has occurred during the period under review
that has affected the implementation of the project.
Outputs achieved
This section addresses output achievements. The CP is requested to report on outputs that have been
achieved fully, partially or not at all, taking into consideration Actual versus Target for each output indicator.
A TC project team includes CP, NLO/NLA, PMO/PMA, TO and other DTMs (in the case of regional and interregional
projects).