6 BuildHoustonOnline.com February / March 2020
W
hat happens when an owner fails to pay or a
contractor continually fails to properly perform
its work? Termination provisions exist to prevent
uncertainty when unexpected and undesired events occur
and should be carefully drafted in every construction contract.
Generally, there are two types of termination provisions
in a construction contract: 1) termination for cause and 2)
termination for convenience.
TERMINATION FOR CAUSE
A termination for cause provision provides rights and
remedies in the face of a breach by the other party. Owners,
general contractors and subcontractors should consider their
risks under a construction contract and allocate those risks
through a termination provision. A well-written termination
for cause provision will protect contracting parties by
providing a clear mechanism to terminate, as well as, the
resulting remedies. Each party to a construction contract will
have dierent goals for a termination for cause provision.
For example, a general contractor may want to consider a
provision allowing it to terminate if:
• The work has stopped for a period of days due to no fault
of the contractor;
• The Owner has not issued a Certicate of Payment or the
Owner has not made payment in a timely manner; or
• The Owner les bankruptcy
If one of these events are triggered, a termination provision
needs to provide the contractor’s post termination remedies,
such as recovering payment for the work executed,
reasonable overhead and prot, and costs incurred as a
result of termination.
An owner may want to consider a provision if the general
contractor, for example:
• Fails to pay its subcontractors; Repeatedly fails to supply
enough workers or materials; or
• Delays completion of a project.
Examples of Owner’s post termination remedies might
include getting an assignment of the general contractor’s
subcontracts, limiting payment to the general contractor for
work actually performed, or excluding the general contractor
from the site.
While termination for cause provisions provide clarity, they
can also limit a party’s ability to terminate the contract. To
avoid this, a catch-all provision that allows termination for a
party’s “material breach of any provision of the contract” is
suggested. The party on the other side of a termination for
cause provision should attempt to add a notice period and
opportunity to cure to the provision to prevent an automatic
termination in the event it defaults.
DETERMINING FOR CAUSE
In case of disagreement between parties, a termination
Terminating
a Construction Contract
BY JP VOGEL AND JULIA EDWARDS
LEGAL